Performance Indicators World Bank and GOI Compliance .1
Monthly Progress Report December 2013
Western I ndonesia National Roads I mprovement Project 37
• Submission of Agreement of Payment F384 for Contract of Package No 01
Biha-Krui di Provinsi Lampung; Package 02 Padang Sawah-Simpang Empat di Provinsi Sumbar; Package 04 Ipuh-Bantal di Provinsi Bengkulu;
• Submission of the Propose Detail Engineering Desain DED and Engineering
Estimate EE Documents for Package No.15 : Sibolga-Bts. Tapsel on Sumatera Utara Province ;
• World Bank Mission 9-18 December 2013 to Bengkulu
• Post review Submission Technical Design Review and Road Safety Review WP-
2 Package No.15 Sibolga-Bts.Tapsel, North Sumatera •
Submission of LARAP Reports for Package No. 13 : Sp. Rukis-Tanjung Kemuning; Package; No.6 : Psr.Pedati-Kerkap; Package No. 11 : Mukomuko-
Bantal ; Package No.16 : Seblat-Ipuh; and Package No.19 Bintunan-Lais in Bengkulu Province
• Post Review Submission for the Verfication Request for The Prequalification
Documents about Package No.5 Sp. Rampa-Poriaha North sumatera, Package No.11. Bantal-Mukomuko and Package No.13 Sp.Rukis-Tj Kemuning Bengkulu
• LARAP Implementation Monitoring Report for Package No.4 : Ipuh-Bantal,
Kabupaten Mukomuko, Province Bengkulu
The following table summarized the CTC personnel field activities during December 2013.
.
Date Position
Destination Purpose
3 – 5 Dec Environmental
Specialist, Social
Impact Specialist North
Sumatera Survey Market on LARAP
Study Package
No. 15
Sibolga-Batas TapSel
9-12 Dec Procurement
Specialist 2 Bengkulu
World Bank Review Mission dan Finalisasi Document PQ
and NCB
Package in
Bengkulu
9-11 Dec Environmental
Specialist, Social
Impact Specialist Bengkulu
World Bank Review Mission dan Finalisasi Document PQ
and NCB
Package in
Bengkulu