Western I ndonesia National Roads I mprovement Project 5 - 3 b. Document Management System DMS, used to record all information of letter and document files. The URL address of the DMS application will be at http:dms.winrip- ibrd.com . The DMS have 2 main modules below: 1. Letter Database System, used to record all information of incoming and outgoing letter. 2. Document Library System, used to record all information of document and report files. Western I ndonesia National Roads I mprovement Project 6 - 1 6 PROJECT PERFORMANCE

6.1 World Bank and GOI Compliance

6.1.1 World Bank Missions

During the month, there was no mission by the World Bank nor monthly coordination meeting to update the Action Plans.

6.1.2 Agreed Key Actions and Mission Plans during Recent World Bank Mission

A list of the key actions monitored during the period are listed below. No. Action By Whom Updated Status November 7, 2016 New Deadline s 1. Issue SPMK Notice to Procee for package 16 PPK • Done: Nov 8, 2016 2. Hold workshop with BPKP on price escalation for packages 1, 2, 3 and 4 to be able to disburse the respective amounts which are available in the 2016 budget, except for package 4 PMU and CTC • November 24-25, 2016 3. Send Bank informally the contract modification request for package 5 this needs to include or be accompanied by a separate extension request since the contract finishes on December 8, 2016 PPK through PMU and CTC • November 15, 2016 4. Inform the Bank about the contract modification to include the additional drainage and accesses to houses in package 6 contact finishes on January 28, 2017 PMU and CTC • November 25, 2016 5. Inform the Bank about the outcome of the meeting with Waskita, the contractor of package 13 to accelerate project implementation PMU and CTC • November 21, 2016 6. Inform the Bank about the outcome of the meeting with the contractor of package 15 to accelerate project implementation PMU and CTC • November 21, 2016 7. Inform the Bank about the outcome of the internal meeting in Bina Marga to discuss possible contract changes for package 20 since this package is in good condition PMU and CTC • November 21, 2016 . 8. Submit the RfP for the slope stabilization, design, and management to the firms on the shortlist PMU and CTC • Done November 02, 2016 9. Send the Bank a letter asking for the NOL to extend the DSC contract contract finishes in December 2016 PMU and CTC • November 15, 2016 10. Send to the Bank the 2 DSC contract modification for price escalation PMU and CTC • Mid of January 2017 After workshop with BPKP 11. Formally send to the Bank the request for NOL to CTC contract amendment no. 5 PMU and CTC • November 15, 2016 12. Send the environmental management and monitoring plans RKPPLs for packages 7, 14, 16, 20 and 21 to the Bank PMU and CTC • End-Nov 2016 p.7 • Mid-Dec 2016 p. 14, 20 and 21 • End Jan 2017 p. 16 • RKPPL Training first week of Jan 2017 13. Cary out HIVAIDS workshops PMUCTC DSC • 29 Nov 2016: Package 14