CTC Contract CTC Consultants

Western I ndonesia National Roads I mprovement Project 3 - 6 Description USD IDR Amendment No.3 including 10 VAT 1,473,917 26,328,054,500 Variance Against Original Contract +4.95 +11.76 Combine Variance Against Original Contract +9.29 Amendment No. 4 including 10 VAT 1,918,158 40,878,169,529 Variance Against Original Contract +36.58 +73.53 Combine Variance Against Original Contract +60.12 Amendment No. 5 including 10 VAT 1,914,495 41,215,451,529 Variance Against Original Contract

36.32 73.84

Combine Variance Against Original Contract 60.22 Tentative, pending approval of Amendment No. 5. Note : Combine variance USD+IDR is based on 1 USD = Rp. 9,558 exchange rate used during the time of signing the original Contract Agreement.

3.2 DSC Consultants

The Design and Supervision Consultant DSC is responsible to design of WP-2 and WP-3 civil works and supervision of all civil works. They will assume the role of Engineer under a FIDIC-type contract. The tasks include the preparation and maintenance of a quality assurance plan, validation and updating of designs, supervision of all civil works, environmental and social monitoring and management, and support for financial and progress monitoring and reporting. The DSC is also be responsible for quality assurance of materials and workmanship, certifying whether or not contractors have achieved the required results, as well as documentation and reporting based on the financial management plan. They will prepare a Quality Assurance system covering all subprojects, and continuously monitor the effectiveness of their supervision procedures. The team is being contracted and managed by DGH through the Bina Marga Regional Office Balai II, and is being based in Padang, West Sumatera. DSC has been established in Balai II Padang following the contract signing on 11 June 2013 between Balai II and Renardet SA in joint venture with PT. Cipta Strada, PT. Daya Creasi Mitrayasa, PT. Seecons and PT. Yodya Karya. The Notice To Proceed was issued by the Balai II on 19 June 2013. Shown in Table 3.3 is the present status of the Design Supervision Consultant DSC contract. Table 3.3 Description USD IDR Original Contract plus 10 VAT 902.660 57,000,575,500 Addendum No.1 plus 10 VAT 1,147,190 60,541,139,347 Variance Against Original Contract +27.09 +6.21 Note : 1 Addendum No.1 is still subject to approval by DGH with World Bank concurrence and issuance of No Objection Letter NOL. 2 Figures with asterisk are tentative pending approval of Addendum No.1 Western I ndonesia National Roads I mprovement Project 3 - 7

3.3 Technical Assistance for Development of Slope Stabilization, Design and

Management The TA s objective is to provide technical support to DGH in improving their capacity for road slopeembankment protection and management. It will include identification and inventory of the existing slope and embankment conditions, assesment of future potential land slide road erosion problems, development of risk maps, prioritization of high problemhigh risk areas, and development of the Detail Engineering Design for a limited amount of areas in the Western corridor of Sumatra. It will also include the review and revision of the National Standard and Manual NSPM related to the slope protection, and capacity building. Consultant to undertake the tasks in under the early stages to procurement. Western I ndonesia National Roads I mprovement Project 4 - 1 4 CIVIL WORKS

4.1 Detailed Design Preparation

Final Engineering Designs, Engineer s Estimates and bidding documents have been completed for all projects proposed for WP-1, WP-2, WP-3. A brief status of the nineteen 19 sub-projects relative to the procurement of Civil works contracts and implementation can be found in Implementation Status table on Page 1-1 of this Report. While progress of road safety audit are shown in Appendix B.

4.2 Procurements

Procurement shall be conducted under the Bank s Procurement Procedures as mentioned in the Loan Agreement. The International Competitive Bidding ICB based on the Bank letter Ref. WINRIP136 will apply to the packages with the construction estimated cost of more than US 25 Million to comply with the new Bank s threshold for ICB. According to the GOI regulation, a prequalification shall be applied for the packages with the construction estimated cost more than IDR 10 Billion. Review from previous procurement process, the World Bank in the Aide Memoire requested to GOI, for next 4 ICB subprojects qualification still used Pre-Qualification and for remaining sub-project must be process with Post Qualification. As well as for all NCB the World Bank also requested to follow Post Qualification in procurement process. As of this reporting month November 2016, a more detailed current updates are fully indicated in Sub-Chapter 1.4 Procurement of Civil Works Contract Under Category 1 on Page 1-5 of this Report . Under Category 3 of Loan Agreement the three 3 consultancy packages capacity building for disaster risk reduction, environmental management and road safety has been cancelled. As a result of the cancellation of the three 3 Technical Assistance, the Technical Assistance for Development of Slope Stabilization, Design and Management has been included as replacement, but to be part of the Loan Category-2 ; Procurement update of the new consultancy package can be found in Sub-Chapter 1.5 Procurement of Consultancy Package Under Category 2 on Page 1-5 of this Report. The WINRIP updated Procurement Plan and Progress are shown in Appendix F.

4.3 Civil Works Implementation

As of end of this reporting month November 2016, five 5 of contract packages were previously completed and currently under defects liability period for twenty four 24 months effective on the day the TOCs were issued and thirteen 13 packages are currently under construction. Details of each contract package are shown in Table 4.1.