Western I ndonesia National Roads I mprovement Project 6 - 5
• Community Development conducted monitoring on TPM activity for packages 07,12 in west
Sumatera Province and package 13 in Bengkulu Province. •
Conducted HIV-AIDS socializations for Package No 14 Painan Kambang on November 29, 2016 .
• RKPPL Training for Package 14, 20, 21 on October 26, 2016 in Padang City.
• Monitoring of RKPPL Implementation on packages 5,6,11,13,15,17 19 submit to WB in November
28, 2016 •
Monitoring Larap for Package 7,8,12,14,21 on November 21 until 26, 2016. •
Introducing TFAC World Bank Mission for Package 8,12,14,16,20 and 21 in Padang City.
6.2.2 Design and Supervision Consultant DSC
The Design and Supervision Consultant DSC will be responsible for design of WP 2 and WP 3 civil works and supervision of all civil works. They will have the role of Engineer under a FIDIC-type
contract. The tasks include the preparation and maintenance of a quality assurance plan, validation and updating of designs, supervision of all civil works, environmental and social monitoring and
management, and support for financial and progress monitoring and reporting. The DSC will also be responsible for quality assurance of materials and workmanship, certifying
whether or not contractors have achieved the required results, as well as documentation and reporting based on the financial management plan. They will prepare a Quality Assurance system
covering all subprojects, and continuously monitor the effectiveness of their supervision procedures. The team will be contracted and managed by DGH through the Bina Marga Regional Office Balai II,
and will be based in Padang, West Sumatera. DSC contract was negotiated in Balai Besar Pelaksanaan Jalan Nasional II Balai-II of DGH. The
negotiation result and draft contract have been sent to WB on 25 March 2013 for review and approval. The Bank issued no objection letter on the negotiation results and draft contract with
letter dated 19 April 2013.
6.2.3 Study on Development of Slope Stabilization Design and Management
This component consists of technical assistance for analytical work of an alternative design for road segment that pass through critical environmental assets and vulnerable areas especially on slope
protection design and management.
6.3 Anti Corruption Issues
6.3.1 Anti-Corruption Action Plan ACAP
The main duties of the Community Development Officer are implemented of Anti-Corruption Measures, and Monitoring their Effectiveness. Provide assistance as required with the establishment
of anti-corruption measures necessary to support the project, and monitor and report their effectiveness based on the Anti-Corruption Action Plan ACAP agreed between the World Bank and
the DGH. The following tasks particularly need to establish procedures to be undertaken:
Western I ndonesia National Roads I mprovement Project 6 - 6
Selection of Community Representative Observers CROs of civil society groups to attend the
procurements process on key procurement steps including pre-bid meeting and site visit, bids submission and bids opening, and the announcement of the bid winner. These CROs will be
invited from local universities or other selected independent institutions, and will sign the attendance list for the procurementselection process.
Establishment of a Third Party Monitoring TPM mechanism, whereby the media and civil
society groups can become involved in monitoring the progress of the project. This Mechanism will include regular sharing of information with the media.
Establishment and Management of a Complaints Handling Mechanism System CHS, which
includes maintaining project complaint log and filing to monitor status of follow-up of each complaint. This mechanism will include provision for follow up investigations of substantial
complaints by the Inspectorate General of Ministry of Public Works or third party audit to ensure independence and reliability of the system. The CTC assignment concerns the monitoring of the
aspects of Anti-Corruption Action Plan ACAP implementation and where required act pro- active in resolving issues when such a matter arises. The Community Development Officer has a
major role in monitoring performance and assists PMU in the set-up and follow-through of the Complaints Handling Unit CHU for the ACAP related incidents
Enhanced Disclosure Provisions and Transparency, Ministry of Public Work MPW have been
provided necessary information in the Project Implementation Plan PIP, Project Management Manual PMM on their website, and in the bidding documents, such as contract point for
complaint mail and e-mail address, phone, fax, text message. The contact will also include the Bank s Fraud and Corruption Hotlines. MPW will hold Annual Accountability Meetings to
enhance accountability and project information sharing with civil society. The PMM will provide guidelines on disclosure of information related to the project. MPW official website will display
critical information on WINRIP to enhance both internal and external monitoring of the project
6.3.2 Community Representative Observers CRO
The Anti-Corruption Action Plan ACAP activity on Community Representative Observers CROs aspect as is follow:
The selection and establishment of CROs for all 19 packages was finish on November 2015.
The last announcement of the winner of the procurement bidding is for Package 16: Seblat
Ipuh was announced by No Objection Letter from the World Bank and from the Ministry of Public Works and Housing Letter No. KU.03.01-Mn902, dated September 26, 2016.
The activities progress of Community Representative Observers CROs from January 2013 until
November 2016, as shown in Appendix H1.
6.3.3 Third Party Monitoring TPM
The Third Party Monitoring TPM component activity during November 2016 was as follow: