Agreed Key Actions and Mission Plans during Recent World Bank Mission

Western I ndonesia National Roads I mprovement Project 6 - 3 No. Action By Whom Updated Status November 7, 2016 New Deadline s 29. Put the Mid-term review report on WINRIP website Please send link to the Bank • PMUCTC • January 31, 2017 30. Submit to the Bank the 2015 IRMS traffic data for the 19 road packages • PMUCTC • End of October 2016 • Mid-November 2016 31. Regularly submit the quarterly progress reports to the Bank • PMU • Noted for each calendar quarter 32. Disclose updated procurement plan after Bank approval in the Winrip website linked to MPW Website • PMU • November 30, 2016 33. Update the newsletter quarterly, including the list of contracts, implementation progress, project related workshops and number, typology and status of complaints • PMU • Every quarter 34. Send quarterly newsletter to the civil society forum in each project province in hard copy or through an electronic mailing system • PMU • Every quarter

6.1.3 Performance Indicators

Key Performance Indicators are developed and agreed between the World Bank and GOI, and will be monitored over the whole project period the changes in variables will be calculated annually. The set indicators are describe in the project Appraisal Document PAD and the Loan Agreement between the GOI and the World Bank. The overall progress towards achieving the PDO of increasing the effective use of selected sections of national roads along the Western Sumatra Corridor by reducing road user costs is considered moderately satisfactory. Progress in implementation has picked up, and there has been an advance with respect to several project indicators. In addition, a project restructuring is being processed which should bring the project largely back on track. The PMU provided an update on the achievement of the indicator targets. There has been relatively good progress on three of the five intermediate indicators. For one of the remaining intermediate indicators on bridge improvement, progress is expected within the next semester. The last intermediate indicator related to institutional strengthening will be cancelled in the framework of project restructuring. For the PDO indicator on AADT, CTC carried out static traffic counts in March 2015 and confirmed that the original indicator targets are adequate. The mission refined a few indicators definitionsbaselines and updated some indicator targets to take into account the project implementation delays. These changes will be reflected in the upcoming project restructuring. From the baseline 2010 AADT and estimated AADT for the year 20142015, the extrapolated AADT for the year 2013 resulted to 11,254 vehicles per day or 8.8 above the targeted 10,347 vehicles per day in 2013. Shown in Table 6.1 is the comparison between Western I ndonesia National Roads I mprovement Project 6 - 4 target and actual estimated AADT. Table 6.1 Year Targeted AADT Estimated Baseline 2010 7,837 FY1 2013 target 10,347 FY1 2013 actual 11,254 FY2 2014 target 11,351 FY2 2014 actual 12,696 FY3 2015 target 12,453 FY4 2016 target 13,304 FY5 2017 end target 14,214 Appendix I shows the updated WINRIP Performance Indicators.

6.2 Implementation Support Components

6.2.1 Core Team Consultant CTC

The CTC is responsible to provide support to the PMU and DGH in the management of the Project, based in Jakarta. The CTC tasks include financial and progress monitoring and reporting, information management and dissemination, quality assurance and performance review for the Design and Supervision Consultants DSC, implementation and monitoring of the anti-corruption action plan, support for project monitoring and evaluation, and support for implementation of a training program to support project management and implementation. The CTC contract No. 06-20CTCTALN80431112 was signed on 5 November 2012 by both DGH and a Joint Venture of PT. Perentjana Djaja, Yongma Engineering Co.Ltd., and PT. Epadascon Permata Engineering Consultant. The main CTC activities during November 2016 are as follows: • Preparation of Monthly Progress Reports. • Monitoring the implementations of the ESAMP, anti-corruption action plans, complains from project site, progress of LARAP, procurement activities and financial progress. • Prepared and issued various letters to PMU. • Submitted various Reports to PMU concerning environmental, the status of LARAP implementations and Site Visit Reports of each Specialist who conducted site inspection. • Monitored the actual construction progresses of the on-going contract packages and advised PMU of the current situations of the sub-projects. • Review technical justification variation order Package 5 and Package 17. • Assisted the POKJA in preparation and conducting Pre-Proposal Conference for the selection of consultancy service for Technical Assistance for Development of Slope Stabilization Design and Management. • Assisted the TFAC Team in conducting site audit inspection on Package 07. Western I ndonesia National Roads I mprovement Project 6 - 5 • Community Development conducted monitoring on TPM activity for packages 07,12 in west Sumatera Province and package 13 in Bengkulu Province. • Conducted HIV-AIDS socializations for Package No 14 Painan Kambang on November 29, 2016 . • RKPPL Training for Package 14, 20, 21 on October 26, 2016 in Padang City. • Monitoring of RKPPL Implementation on packages 5,6,11,13,15,17 19 submit to WB in November 28, 2016 • Monitoring Larap for Package 7,8,12,14,21 on November 21 until 26, 2016. • Introducing TFAC World Bank Mission for Package 8,12,14,16,20 and 21 in Padang City.

6.2.2 Design and Supervision Consultant DSC

The Design and Supervision Consultant DSC will be responsible for design of WP 2 and WP 3 civil works and supervision of all civil works. They will have the role of Engineer under a FIDIC-type contract. The tasks include the preparation and maintenance of a quality assurance plan, validation and updating of designs, supervision of all civil works, environmental and social monitoring and management, and support for financial and progress monitoring and reporting. The DSC will also be responsible for quality assurance of materials and workmanship, certifying whether or not contractors have achieved the required results, as well as documentation and reporting based on the financial management plan. They will prepare a Quality Assurance system covering all subprojects, and continuously monitor the effectiveness of their supervision procedures. The team will be contracted and managed by DGH through the Bina Marga Regional Office Balai II, and will be based in Padang, West Sumatera. DSC contract was negotiated in Balai Besar Pelaksanaan Jalan Nasional II Balai-II of DGH. The negotiation result and draft contract have been sent to WB on 25 March 2013 for review and approval. The Bank issued no objection letter on the negotiation results and draft contract with letter dated 19 April 2013.

6.2.3 Study on Development of Slope Stabilization Design and Management

This component consists of technical assistance for analytical work of an alternative design for road segment that pass through critical environmental assets and vulnerable areas especially on slope protection design and management.

6.3 Anti Corruption Issues

6.3.1 Anti-Corruption Action Plan ACAP

The main duties of the Community Development Officer are implemented of Anti-Corruption Measures, and Monitoring their Effectiveness. Provide assistance as required with the establishment of anti-corruption measures necessary to support the project, and monitor and report their effectiveness based on the Anti-Corruption Action Plan ACAP agreed between the World Bank and the DGH. The following tasks particularly need to establish procedures to be undertaken: