Western I ndonesia National Roads I mprovement Project 4 - 12
a PMU waiting report of the completed relocation of the kiosk from Satker C. Update during this reporting month of April 2015
a Monitoring Report for the concerning the completed relocation of the kiosk still to be prepared for submission to World Bank.
b No Update this period
6. Monitoring Report of the LARAP Package No. 6
: Pasar Pedati - Kerkap Province
: Bengkulu
A. Previous Status : •
World Bank issued on May 30, 2015 a No Objection Letter on the revised LARAP documents for implementation.
• Monitoring Report concerning the compensation payment for 546 out of 602 PAP was
given No Objection Letter NOL on March 23, 2015. B. Pending Issues, Concern and Actions
a Remaining 56 from the 602 PAP will be resolved on Apr Jun 2015.
C. Update during this reporting month of April 2015 a No update this period
7. Monitoring Report of the LARAP Package No. 7
: Indrapura - Tapan Province
: Sumatera Barat
A. Previous Status : •
LARAP documents approved by World Bank on October 14, 2014. •
Implementation action plan of the LARAP was issued No Objection Letter NOL on March 17, 2015 by the World Bank.
B. Pending Issues, Concern and Actions a LARAP Implementation Report to be prepared and submitted to PMUCTC for
review. b No allocated budget in 2014 for payment of land acquisition.
c Implementation cost of LARAP will be included by Local Government in the 2015 budget.
C. Update during this reporting month of April 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of
Local Government are on-going.
8. Monitoring Report of the LARAP Package No. 8
: Bts. Pariaman - Manggopoh Province
: Sumatera Barat
A. Previous Status : •
LARAP documents submitted to World Bank on August 7, 2014. •
LARAP documents approved by World Bank on August 12, 2014.
Western I ndonesia National Roads I mprovement Project 4 - 13
B. Pending Issues, Concern and Actions a Implementation cost of LARAP will be included by the Local Government in the
2015 budget. C. Update during this reporting month of April 2015
a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.
9. Monitoring Report of the LARAP Package No. 9
: Rantau Tijang Kota Agung
Province : Lampung
A. Previous Status : •
Proposed to be replaced. B. Pending Issues, Concern and Actions
a Proposed to be replaced. C. Update during this reporting month of April 2015
a Nothing to report this period. b Proposed to be replaced.
10. Monitoring Report of the LARAP Package No. 10
: Sp. Empat Sp. Air Balam
Province : Sumatera Barat
A. Previous Status : •
LARAP documents submitted to World Bank on August 7, 2014. •
LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions
a Implementation cost of LARAP will be included by the Local Government in the 2015 budget.
C. Update during this reporting month of April 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of
Local Government are on-going.
11. Monitoring Report of the LARAP Package No. 11
: Bantal - Mukomuko Province
: Bengkulu
A. Previous Status : •
World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation.
• Monitoring Report No.1 and No.2 were issued No Objection Letters NOL from the
World Bank. B. Pending Issues, Concern and Actions
a Compensation payments for the remaining 51 PAP is in process and to be paid from 2015 National Budget.