Monitoring Report of the LARAP Package No. 1 Monitoring Report of the LARAP Package No. 2

Western I ndonesia National Roads I mprovement Project 4 - 12 a PMU waiting report of the completed relocation of the kiosk from Satker C. Update during this reporting month of April 2015 a Monitoring Report for the concerning the completed relocation of the kiosk still to be prepared for submission to World Bank. b No Update this period

6. Monitoring Report of the LARAP Package No. 6

: Pasar Pedati - Kerkap Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2015 a No Objection Letter on the revised LARAP documents for implementation. • Monitoring Report concerning the compensation payment for 546 out of 602 PAP was given No Objection Letter NOL on March 23, 2015. B. Pending Issues, Concern and Actions a Remaining 56 from the 602 PAP will be resolved on Apr Jun 2015. C. Update during this reporting month of April 2015 a No update this period

7. Monitoring Report of the LARAP Package No. 7

: Indrapura - Tapan Province : Sumatera Barat A. Previous Status : • LARAP documents approved by World Bank on October 14, 2014. • Implementation action plan of the LARAP was issued No Objection Letter NOL on March 17, 2015 by the World Bank. B. Pending Issues, Concern and Actions a LARAP Implementation Report to be prepared and submitted to PMUCTC for review. b No allocated budget in 2014 for payment of land acquisition. c Implementation cost of LARAP will be included by Local Government in the 2015 budget. C. Update during this reporting month of April 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

8. Monitoring Report of the LARAP Package No. 8

: Bts. Pariaman - Manggopoh Province : Sumatera Barat A. Previous Status : • LARAP documents submitted to World Bank on August 7, 2014. • LARAP documents approved by World Bank on August 12, 2014. Western I ndonesia National Roads I mprovement Project 4 - 13 B. Pending Issues, Concern and Actions a Implementation cost of LARAP will be included by the Local Government in the 2015 budget. C. Update during this reporting month of April 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

9. Monitoring Report of the LARAP Package No. 9

: Rantau Tijang Kota Agung Province : Lampung A. Previous Status : • Proposed to be replaced. B. Pending Issues, Concern and Actions a Proposed to be replaced. C. Update during this reporting month of April 2015 a Nothing to report this period. b Proposed to be replaced.

10. Monitoring Report of the LARAP Package No. 10

: Sp. Empat Sp. Air Balam Province : Sumatera Barat A. Previous Status : • LARAP documents submitted to World Bank on August 7, 2014. • LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions a Implementation cost of LARAP will be included by the Local Government in the 2015 budget. C. Update during this reporting month of April 2015 a Inventory of affected assets and measurements by Land Acquisition Committee of Local Government are on-going.

11. Monitoring Report of the LARAP Package No. 11

: Bantal - Mukomuko Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. • Monitoring Report No.1 and No.2 were issued No Objection Letters NOL from the World Bank. B. Pending Issues, Concern and Actions a Compensation payments for the remaining 51 PAP is in process and to be paid from 2015 National Budget.