Western I ndonesia National Roads I mprovement Project 1 - 6
Evaluation by POKJA of Request For Expression of Interest of interested Consultants for shortlisting purposes has been completed.
Evaluation result were forwarded to World Bank their review and comment
2. Technical Assistance for Capacity Building for Environmental Management
Propose to be deleted.
3. Technical Assistance for Capacity Building for Road Safety
Propose to be deleted.
1.6 Consolidated Update of the Progress of the Project
Other brief updates of the pre-construction activities of this reporting month are shown in Table 1.1.
Western I ndonesia National Roads I mprovement Project 1 - 7
Consolidated Project Status As Of End April 2015 Table 1.1
DED
Technical Design
Review Road Safety
Audit
Status
Doc Requirement Status
Doc Requirement Status
Budget Allocation
Status Estd.
Start Duration
Months
1 Krui - Bha
Completed Completed
Completed SPPL AMDAL
No.1 17 SPPL OK P2JN 2010
AMDAL Subdit TLKJ OK 2012 . WB NOL issues on
20 Nov 2013 1.LARAP
2. LARAP Mon Report
1.NOL WB 4 Jan 13 2.NOL LARAP
Monitoring 18 April 2013, Rev 26 June 2013.
Satker PJN Prov insi
98. Remaining issues: 1 four
plots due to the alignment changing not y et paid by
project. 2 Certification process of the PAP w ill be as
soon as resolv ed by Satker Completed
Jan-14 21.00
A Padang Saw ah - Sp. Ampat
Including Air Gadang Bridge 3
Manggopoh - Padang Saw ah Completed
Completed Completed
SPPL OK P2JN 2010.No need
NOL WB for SPPLUKLUPL
1.LARAP 2. LARAP Mon
Report 1.NOL WB 13 Dec 12
2. NOL WB_1: 26 Apr 2013, NOL WB_2: 5 Mar
2014, NOL WB_3: 23 Jun 2014, NOL WB_4:
12 Feb 2015, NOL WB_5: 17 Mar 2015
APBD Prov insi 99.
Pending issue: Compensation for the remaining 1 PAP being
resolv ed by Local Gov ernment
Completed Jan-14
24.00 A
4 Ipuh - Bantal
Completed Completed
Completed SPPL UKLUPL
SPPL OK P2JN 2010 UKLUPL presentation on
Balai III on 27 Aug 14. 1.LARAP
2. LARAP Mon Report
1.NOL WB 10 Dec 12 2. NOL MR-1: 6 Jan
2014, MR-2: 5 Mar 2014, MR-3: 12 Feb 2015
Satker PJN Prov insi
100 Completed
Jan-14 24.00
A 5
Sp. Rampa - Poriaha Completed
Completed Completed
UKLUPL OK Balai 1 2011. No
need NOL WB for SPPLUKLUPL
1.SLARAP 2. LARAP Mon
Report 1.Nol WB 10 Dec 12
2. Mon Report: - Satker PJN
Prov insi 99, Relocation 1 kiosk
affected being done by project Contract
Aw arded Dec-14
18.00 M
6 Ps. Pedati - Kerkap
Completed Completed
Completed UKLUPL
OK TLKJ 2011. NOL WB issued on 20 Nov 2013
1.LARAP 2. LARAP Mon
Report 1.NOL WB 20 Nov 2013
2. NOL WB_1: 23 Mar 2015.
Satker PJN Prov insi
Compensation pay ment for the remaining 56 PAP w ill be
resolv ed on Apr - Jun 2015 Completed
Mar-15 15.00
A 7
Indrapura - Tapan Completed
Completed Completed
AMDAL OK TLKJ , 20 Feb 2014.
NOL WB issued on 8 Aug 2014
1.SLARAP 2. LARAP Mon
Report 1.NOL WB 10 Oct 2014
2. Target of a Mon Report on April - Jun
2015 APBD Prov insi
2015 Inv entory affected asset under
process On-Going
Jan-15 21.00
G 8
Bts. Kota Pariaman - Manggopoh Completed
Completed Completed
AMDAL OK TLKJ 2013 . NOL WB
issued on 14 April 2014 1.LARAP
2. LARAP Mon Report
1.NOL WB 12 Aug 2014 2. Target of a Mon
Report on May 2015 APBD Prov insi
2015 Inv entory affected asset under
process On-Going
Feb-15 24.00
G 9
Rantau Tijang - Kota Agung be changed w ith Bengkunat - Biha
UKLUPL OK TLKJ 2011. NOL WB
issued on 20 Nov 2013 Social and Env
safeguards screening Being prepared by
Consultant Balai 3 Satker PJN
Prov insi -
Jun-15 21.00
L 10
Sp. Empat - Sp. Air Balam Completed
Completed Completed
AMDAL OK TLKJ 2013 . NOL WB
issued on 14 April 2014 1.LARAP
2. LARAP Mon Report
1.NOL WB 12 Aug 2014 2. Target of a Mon
Report on Apr - Jun 2015 APBD Prov insi
2015 Inv entory affected asset under
process Not Yet Started
Feb-14 24.00
G 11
Bantal - Mukomuko Completed
Completed Completed
AMDAL OK TLKJ 2014. NOL WB
issued on 8 Aug 2014 1.LARAP
2. LARAP Mon Report
1.Nol WB: 20 Nov 2013 2. NOL WB-1: 2 Dec
2014, NOL WB-2: 12 Feb 2015
Satker PJN Prov insi
73. Compensation pay ment for the
remaning 51 w ill be resolv ed on Apri - Jun 2015
Completed Feb-15
24.00 A
12 Kambang - Indrapura
Completed Completed
Completed AMDAL
OK TLKJ 2014 .NOL WB issued on 8 Aug 2014
1.LARAP 2. LARAP Mon
Report 1.NOL WB 10 Oct 2014
2. Target of a MR on Apr - Jun 2015
APBD Prov insi 2015
Inv entory affected asset under process
on going Feb-15
24.00 G
13 Sp. Rukis - Tj.Kemuning
Completed Completed
Completed UKLUPL
OK P2JN 2011. No need NOL WB for
SPPLUKLUPL 1.LARAP
2. LARAP Mon Report
1.NOL WB:20 Nov 2013 2. Target a MR in Jun
2015 Satker PJN
Prov insi Process of appraisal affected
asset by Appraisal Independent
Contract Aw arded
Dec-14 24.00
M 14
Painan - Kambang On Going
AMDAL OK TLKJ 2014 .NOL WB
issued on 8 Aug 2014 1.LARAP
2. LARAP Mon Report
1.NOL WB 19 Des 2014 2. Target of a MR on
Jun 2015 APBD Prov insi
2015 Socialization under process
Not Yet Started Mar-15
21.00 B
15 Sibolga - Bts.Tap Sel
Completed Completed
Completed UKLUPL
OK Balai 1 2011. No need NOL WB for
SPPLUKLUPL 1.LARAP
2. LARAP Mon Report
1.NOL WB: 5Feb 2014 2.Target a MR Apr - Jun
2015 Satker PJN
Prov insi 80 from total 1148 PAP
already receiv ed compensation from Satker
on going Feb-15
30.00 J
Seblat - Ipuh including Air Lalang Air Guntung Bridge
18 Mukomuko - Bts.Sumbar be changed
w ith Sibolga - Sorkam UKLUPL
OK TLKJ 2011. No need NOL WB for
SPPLUKLUPL Social and Env
safeguards screening Being prepared by
Consultant Balai 1 Satker PJN II
Prov insi -
May -15 18.00
L 19
Lais - Bintunan Completed
Completed Completed
UKLUPL OK TLKJ 2011.No need
NOL WB for SPPLUKLUPL
1.LARAP 2. LARAP Mon
Report 1.NOL WB 20 Nov 2013
2. NOL WB_1: 23 Mar 2015.
Satker PJN Prov insi
Compensation pay ment for the remaining 117 PAP w ill
be resolv ed on Apr - Jun 2015 Completed
Mar-15 10.00
A 20
Lubuk Alung - Sicincin On Going
UKLUPL OK TLKJ 2011.No need
NOL WB for SPPLUKLUPL
1.LARAP 2. LARAP Mon
Report 1.NOL WB 19 Des 2014
2. Target of a MR on Jun 2015
APBD Prov insi 2015
Socialization process Not Yet Started
Feb-15 18.00
B 21
Lubuk Alung - Kurajati On Going
UKLUPL OK TLKJ 2011. No need
NOL WB for SPPLUKLUPL
1.LARAP 2. LARAP Mon
Report 1.NOL WB 19 Des 2014
2. Target of a MR on Jun 2015
APBD Prov insi 2015
Socialization process Not Yet Started
Feb-15 18.00
B Remarks :
A On going Construction
= 3 Packages in 1 study AMDAL West Sumatera Prov ince
B DED Draw ing are under final preparation
C Technical Design Rev iew by CTC
= 2 Packages in 1 study AMDAL Bengkulu Prov ince
D Under Rev iew by Directorate of Technical Affairs
E Final Detailed Engineering Design by DSC
F Under Rev iew by BALAI
G Ow ners Estimate approv ed
H World Bank rev iew for issuance of NOL
I Currently on Tendering stage
J Bid Ev aluation Report Submitted to World Bank
K Bid Ev aluation Report BER finalized by POKJA
L Propose to be replaced
M Contract aw arded NTP COW still to be issued
Group Pack.
No. Procurement
Status
AWP-1
1.LARAP 2. LARAP Mon
Report 1.NOL WB 13 Dec 12
2. NOL WB 19 Juli 2013, NOL_2 WB 12
Feb 2015 APBD Prov insi
90. Pending issues:
Compensation for the remaining 3 PAP and 24 new
PAP being resolv ed by Local Gov ernment
Completed Jan-14
AWP-2
Remarks
Contract Implementation Plan
Loan Package Name
2 Completed
Completed Completed
SPPLUKL UPL Bridge
OK P2JN 2010 No need NOL WB for
SPPLUKLUPL
Environmental Social
Land Acquisition
24.00 A
M B
AWP-3
On going appraisal process Contract
Aw arded Oct-14
24.00 OK TLKJ 2011. NOL WB
issued on 20 Nov 2013 1.LARAP
2. LARAP Mon Report
1.NOL WB: 16 Sep 2014 2. Target a MR in Jun
2015 16
On Going On Going
17 Sp.Gunung Kemala - Pg.Tampak
Completed Completed
21.00 Mar-15
Not Yet Started Compensation pay ment for the
remaining 311 w ill be resolv ed on Apr - Jun 2015
Satker PJN Prov insi
Satker PJN II Prov insi
OK TLKJ 2014 . NOL WB issued on 8 Aug 2014
On Going AMDAL
Completed AMDAL No.1 17
1.NOL WB: 20 Nov 2014
2. NOL WB-1: 12 Feb 2015
1.LARAP 2. LARAP Mon
Report
Western I ndonesia National Roads I mprovement Project 2 - 1
2 PROJECT DESCRIPTION
2.1 Background
The Government of Indonesia wishes to continue strengthening of the National Road system in Indonesia while the Eastern Indonesia National Roads Improvement Project EINRIP which is
assisted by AusAID through the Australian Indonesia Partnership or AIP, is providing support program of National road and bridge improvement works in Eastern Indonesia. The Western
Indonesia National Road Improvement Project WINRIP will provide similar support for National road and bridge in the Sumatera region of Indonesia. The focus of WINRIP will be roads
administered directly by the National Government, including those currently classified as Provincial, Kabupaten District or non-status roads which are in process of being reclassified as
National roads. In addition, provision will be made for major bridge repair works, rehabilitation, duplication and replacement as necessary to complement road betterment works.
2.2 Project Development
The loan effectiveness date for the WINRIP is 12 March 2012 and key project data is shown in the following detail.
Key Project Data WINRIP Loan No. 8043-ID
Project Cost US350 million
Original Loan Amount US250 million
Revised Loan Amount NA
Board Approval Date 26 May 2011
Loan Signing Date 14 December 2011
Effectiveness Date 12 March 2012
Disbursement as of 30 April 2015 US 18.42 million 7.37
Original Closing Date 31 December 2017
Environmental Category B-Partial Assessment
The IBRD loan amount is US250 million. The Project is intended to finance a part of the DGH investment program for national roads with a particular focus on the Western corridor of
Sumatera. The corridor is one of the three main corridors in Sumatera and connects the city of Padang with a population of around one million to major towns along the west coast Bukittinggi,
Sibolga and Bengkulu. It also connects through connector roads on the West coast to Medan in the northeast and to Pekanbaru in the centre of the island. The project has four components:
Project Component 1: Betterment and Capacity Expansion of National Roads
According to the Loan Agreement, this component will cover three work programs of betterment and capacity expansion of approximately 715.6 km including replacement of 194 meters of bridges.
This civil works program will be executed in three Annual Work ProgramsAWP, as summarized in
Table 2.1. The table shows the IBRD assisted scope and costs of civil works at estimated current
year of implementation prices, excluding taxes.
Western I ndonesia National Roads I mprovement Project 2 - 2
Table 2.1 Proposed Physical Works by DGH Program Type of Works
AWP-1 AWP-2
AWP-3
Km USD
Million
Km USD
Million
Km USD
Million
Road Betterment -
- 53.10
22.77 -
-
Capacity Expansion 137.10
79.70 314.60
127.67 207.60
74.58
Bridge works 0.100
1.94 -
- 0.08
2.06
TOTAL
excluding tax current prices
137.20 81.64
367.70 150.45
207.68 76.65
The batches of projects are termed Annual Work Programs AWPs in line with terminology used in other Bina Marga projects. They are not in fact annual programs as such but rather a series of
multi-year programs, each commencing in consecutive years. Hence, hereinafter it will call as just Work Programs WPs. It is expected that implementation of the first Works Program WP-1 will
commence in the third quarter of 2013 and be completed by third quarter or late 2015. The second Work Program WP-2 is expected to commence in early 2014 and be completed by late
2015 or middle 2016. The third Work Program WP-3 is expected to commence in early 2015 and
be completed by mid-2017. The loan will be closed on December 2017. Table 2.2 presents details of the First Works Program WP-1. The four packages in this group
should have been free from any land acquisition issues, but in fact two packages Krui Biha and
Manggopoh Padang Sawah had land issues which were solved by the DGH properly. Thus, there
are no foreseeable impediments to implementation.
Table2.2 IBRD Assisted WINRIP Civil Work WP-1
No Province Link
No. Link
Name
C la
ss R
o a
d T
y p
e Road Works
Bridge Works Total Cost
Fr o
m T
o Le
n g
th T
re a
tm e
n t
C o
st 2
1 No
Le n
g th
C o
st 2
1 2
1 P
ri ce
s E
q u
iv a
le n
t
Km Km
Km Rp mill
m Rp mill
Rp mill US mill
1 Lampung
053.0 Krui
Biha K1
IU 221.5
246.5 25.0 Bett nt
to 7 m. 148,668
148,668 16.52
2
West Sumatera
047.2 PadangSa
wa SimpangE
mpat K1
IU 0.0
40.9 40.9 Bett nt
to 7 m. 189,810
189,810 21.09
2a
West Sumatera
34.1 AirGadan
gBridge K1
IU New
Bridge 1
100 17.580 17,580
1.95
3
West Sumatera
047.1 Manggop
oh PadangSa
wah K1
IU 102.2
134.2 32.0 Bett nt
to 7 m. 152,435
152,435 16.94
4 Bengkulu
015.3 Ipuh -
Bantal K1
IU 0.0
49.7 49.7 Bett nt
to 7 m. 226,275
226,275 25.14
Western I ndonesia National Roads I mprovement Project 2 - 3
It should be noted that all road sub-projects have been subject to economic appraisal and have estimated Economic Internal Rates of Return EIRR in excess of 15. These were selected for
inclusion and are subject to completion of environmental and social screening, to confirm that there is no land acquisition or resettlement requirements remain outstanding.
Final Engineering Designs, Engineer s Estimates and bidding documents have been completed for all projects proposed for WP-1.
Sub-projects to be included in WP-2 and WP-3 have also been determined as listed in Table 2.3.
Final Engineering Designs and Engineer s Estimates for all WP-2 and WP-3 proposed works require preparation or finalization. In the cases of some projects, preliminary Engineering Designs were
prepared during Project preparation which will require review and possible amendment by the Design and Supervision Consultant prior to procurement.
The revised costs presented in Table 2.3 are planning estimates only, and the revised
implementation plan is based on the Revised Timeline of implementation of the civil works.
Table2.3: IBRD Loan WINRIP Civil Work WP-2 and WP-3
NO. SUBPROJECT LINK NO. AND NAME
LENGTH KM
ENGINEER S ESTIMATE
RP. MILL WIDTH
M REVISED IMPLEMENTATION PLAN
START DURATION
MONTHS WP-2
5. Sumut : Link No. 015.xx,
Sp. Rampa Poriaha
9.70 152,870
6.0 Mar 2015
18 6.
Bengkulu : Link No. 010.0, Ps. Pedati
Kerkap 20.88
92,127 7.0
Apr 2015 15
7. Sumbar : Link No. 019.0,
Indrapura Tapan
19.50 175,812
7.0 Jan 2016
21 8.
Sumbar : Link No. 024.0, Bts. Pariaman
Manggopoh 46.80
374,647 7.0
Jan 2016 24
9. Lampung : Link No. 026.1,
Rantau Tijing - Kota Agung -
- -
- Proposed to be
Deleted 10.
Sumbar : Link No. 034.1, Sp. Empat - Sp. Air Balam
61.70 511,375
7.0 Jan 2016
24 11.
Bengkulu : Link No. 015.2, Bantal
Mukomuko 50.10
246,500 6.0
Mar 2015 24
12. Sumbar : Link No. 017.2,
Kambang Indrapura
55.20 438,674
7.0 Jan 2016
24 13.
Bengkulu : Link No. 006.1, Simpang Rukis - Tanjung Kemuning
56.30 316,305
7.0 Jun 2015
24
WP-3
14. Sumbar : Link No. 017.1,
Painan Kambang
31.50 252,000
7.0 May 2016
21 15.
Sumut : Link No. 016.0, Sibolga - Bts. TapSel
36.00 376,479
7.0 Oct 2015
27