Civil Works Progress WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227

Western I ndonesia National Roads I mprovement Project 4 - 5 Package No. 2 : Padang Sawah Sp. Empat Including Air Gadang Bridge As of end of this month the total overall work progress is 55.71 against scheduled progress of 67.95 which is still behind schedule by -12.23 . Major problems that are still unresolved are the carryover problems from previous months such as low production of asphalt hotmix and the delayed construction of Air Gadang Bridge. To date, the delayed work is still on a manageable level, but it is still a bit of concern that unless the current problems are addressed immediately, the delayed works will further fall behind in the coming months. As of end of this period April 2015, there are still 44 remaining works to be completed within the remaining eight 8 of the contract time. In order for the Contractor to complete the works on the target date of completion, a minimum progress of at least 5.50 per month have to be accomplished. At the rate the Contractor executes the works, most likely the Project could be completed within the contract period. ANNEX P-2 Executive Summary Report present a more detailed status of the Contract Package. Package No. 3 : Manggopoh Padang Sawah The current overall work progress of only 39.72 against scheduled progress of 73.03 since the works commenced 16 months ago is of much concern due to the very limited remaining contract time left which is only 8 months till the target date of completion. As of end of this month, the remaining contract time is only 35 or 257 calendar days with still 60 of the works to be completed. For the Contractor to deliver the completion of the contract package on the target date of completion on January 5, 2016, a per month progress of 7.50 shall be attained for the duration of the eight 8 months remaining contract time. The problem of slow and delayed work progress have be going-on for the past nine 9 months. Problem which the Contractor have to immediately address and resolve are the frequent out of order of the Asphalt Mixing Plant, inadequate number of units of dump truck, shortage of labor for drainage works and low output of the crusher plant to produce quantity of aggregate requirements. Due to urgency to maximize the output of paving works to attain the projected 7.50 progress per month till end of the Contract period, the Contractor shall maintain the AMP regularly and address and resolve all issues that are presently hampering the progress of the works. A more detailed status of the project progress are shown in ANNEX P-3 Executive Summary Report . Package No. 4 : Ipuh Bantal The current status of this contract package still remain in critical situation with respect to completion date on January 9, 2016 although the negative slippage showed sign of slight improvement as the month ended.