Technical Assistance for Capacity Building for Disaster Risks Reduction
4.2 Procurements
Procurement shall be conducted under the Bank s Procurement Procedures as mentioned in the Loan Agreement. The International Competitive Bidding ICB based on the Bank letter Ref. WINRIP136 will apply to the packages with the construction estimated cost more than US 25 Million to comply with the new Bank s threshold for ICB. According to the GOI regulation, a prequalification shall be applied for the packages with the construction estimated cost more than IDR 10 Billion. Review from previous procurement process, the World Bank in the Aide Memoire requested to GOI, for next 4 ICB subprojects qualification still used Pre-Qualification and for remaining sub-project must be process with Post Qualification. As well as for all NCB the World Bank also requested to follow Post Qualification in procurement process. All subprojects for WP-1 have been started with prequalification since 30 December 2011 for ICB multiple contract. This was an advanced procurement action agreed by both DGH and the World Bank prior to the CTC establishment. As of the reporting month April 2015, a more detailed current updates are fully indicated in Sub-Chapter 1.4 Procurement on Page 1-4 of this Report and consolidated project status in a tabulated format shown in Table 1.1 on page 1-7 of this Report. Under Category 3 of Loan Agreement there are three 3 consultancy packages namely ; 1. Capacity Building For Disaster Risks Reduction 2. Capacity Building For Environmental Management 3. Capacity Building For Road Safety Consultant for Capacity Building For Disaster Risks Reduction is still to be procured, while the other two 2 consultancy packages are proposed to be deleted. A more detailed updates can be found in Sub-Chapter 1.5 Procurement on Page 1-5 of this Report.
The WINRIP updated Procurement Plan and Progress is attached as Appendix F.4.3 Civil Works Implementation
All 4 contract packages under original implementation schedule AWP-1 are currently under construction by different contractors. Commencement of works for all the 4 packages commenced on the 2 nd week of January 2014. As of end of this reporting months April 2015, there are three 3 new sub-projects that has recently commenced. Two 2 of the contract packages are under implementation schedule AWP-2 and the other contract package is under AWP-3. In addition, three 3 contract packages under AWP-2 and AWP-3 has been awarded with NTP s are still to be issued.Parts
» WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» Current Implementation Situation Civil Works
» Disbursement WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» Package 17 Sp. Gunung Kemala Package 13 Sp. Rukis Packages 5 Simpang Rampa Package No.15 Sibolga
» Technical Assistance for Capacity Building for Disaster Risk Reduction
» Technical Assistance for Capacity Building for Environmental Management
» Technical Assistance for Capacity Building for Road Safety
» Background WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» Project Development WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» Project Objective WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» CTC Consultants WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» DSC Consultants WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» Technical Assistance for Capacity Building for Disaster Risks Reduction
» Detailed Design Preparation WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» Procurements WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» Civil Works Implementation WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» Civil Works Progress WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 32.67 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 55.71 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 39.72 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» - 33.66 5.59 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» -0.17 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» Quality Assurance WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» Monitoring Report of the LARAP Package No. 1 Monitoring Report of the LARAP Package No. 2
» Monitoring Report of the LARAP Package No. 5
» Monitoring Report of the LARAP Package No. 8
» Monitoring Report of the LARAP Package No. 11
» Monitoring Report of the LARAP Package No. 14
» Monitoring Report of the LARAP Package No. 15
» Monitoring Report of the LARAP Package No.16
» Monitoring Report of the LARAP Package No.17
» Monitoring Report of the LARAP Package No.18
» Monitoring Report of the LARAP Package No.19
» Monitoring Report of the LARAP Package No. 20
» Monitoring Report of the LARAP Package No. 21
» Anti Corruption Issues WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» Road Safety Audit WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» Letter Database System, used to record all information of incoming and
» Document Library System, used to record all information of document and
» Implementation Support Components WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» TRAINING TO SUPPORT PROJECT IMPLEMENTATION
» Publication Disclosures Masitoh Hasibuan, ST as the member.
» Management Information System WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» Project Risks and Mitigation Measures
» 7.22 0.01 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 1.83 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 23.78 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 3.80 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 3.34 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 6.56 0.11 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 4.64 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 0.94 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 2.10 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 46.76 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 2.46 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 27.18 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 5.36 0.14 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 3.21 1.91 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 35.31 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 47.72 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 65.59 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 84.21 100.00 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» - Delayed relocation of existing PDAM pool
» 5.41 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 3.40 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 4.19 - WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 0.10 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 9.30 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 16.74 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 21.75 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 6.28 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 0.96 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 0.62 2.04 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 1.09 0.00 11.00 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 11.46 17.58 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» 1.18 0.17 35.43 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» -15.06 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
» -12.23 WINRIP DOC MPR CTC MPR No.28 2015 04 20150430 00227
Show more