Document Library System, used to record all information of document and
Western I ndonesia National Roads I mprovement Project 6 - 2
15. Procurement training for Pokjas of package 7,8,10,12
Bank and PMU •
Middle of May 2015 16.
Send the engineering designs for packages 14, 16, 20 and 21 to the Bank
PMU •
End of May 2015
17. Package 1 all permits have now been received:
• Respond to the letter of the Bank regarding
contract modification 1 with respect to the stone masonry calculations and the capacity of the
reduced U Ditches
• Take the necessary steps, including legal to make
sure the works advance PMU
• Early May 2015
• Early of May
18. Package 2: Accelerate the processing of the necessary
contact modification, which needs to cover all accesses to property and any time extension and send it to the
Bank if it is above 15 PMU
• End of May
19. Package 3:
• Send draft amendment for package 3 19 for
prior Bank no-objection, which needs to cover all accesses to property
• DSC needs to push contractor to submit sharp
drawing of cross section to propose variation order PMU
• Early May 2015
• End of May 2015
20. Package 4:
• BM finalize and approve the contract modification,
which needs to accommodate access to all properties
PMU •
End of May 2015
21. Report back to the Bank on how DGH has implemented
the recommendations of the auditors in the auditing report of the 2012 and 2013 financial statements
partial response at least while waiting for feedback from the Balai
PMU •
Early of June 2015
22. Send to the Bank the 2014 audit report
PMU •
June 30, 2014 23.
Follow up on the meeting with the Inspectorate General of MPW on the financial and technical audits
Bank team •
June 2015 24.
Send revised version of PMM, including the web application
PMUCTC •
End of April 2015 25.
Send to the Bank a request for modification of the contract with CTC
PMU •
Beginning of June 2015 26.
Send to the Bank a request for modification of the contract with DSC
PMU •
Beginning of June 2015 27.
Send the Bank the results of the random checks to verify if DGH s AADT data is correct and the simple
regression analysis to compare it with the data from the mobile survey
PMU •
May 15, 2015
28. Regularly submit the quarterly progress reports to the
Bank INCLUDE DETAILED INFORMATION ON THE IMPLEMENTATION OF THE RKPPLs
PMU •
July 2015 29.
Send letter to Pak Harris urging to accelerate the submission of the restructuring request to
BappenasMinistry of Finance Bank
• End of April 2015
30. Send restructuring request to the Bank
Ministry of Finance
• Early June 2015
31. Send the response to the Bank on the TFAC reports for
PMU •
June 3, 2015
Western I ndonesia National Roads I mprovement Project 6 - 3
packages 2 and 3 and the supervision mission report for package 1
32. Mission to follow up on findings of February 2015
safeguard audit CTC and Bank
• May 13, 2015
33. Send to Bank monthly supervision reports for packages
with problematic issues PMU
• End of May, 2015
Please note the following: •
All ICB needs prior review. Contract above USD 10m of NCB needs prior review •
All packages must involve CRO and TPM. It is possible to have one TPM for one province that will monitor all packages in the province.