Performance Indicators World Bank and GOI Compliance .1
Monthly Progress Report May 2013
Western I ndonesia National Roads I mprovement Project 29
Bintunan submitted by DSC during May 2013. •
Joined the Bank mission visiting the site of package No.2 and 3 Manggopoh – Padang Sawah – Sp. Empat on 21 to 22 May 2013, and package No.1 Krui –
Biha on 23 to 24 May 2013.
• Monitor WINRIP Procurement Plan and Progress.
• Submit updating PMM Project Management Manual regarding Financial
Management aspects. •
Mobilization the Senior Road Safety Audit Engineer. The following table summarized the CTC personnel field activities during May 2013.
Date Position
Destination Purpose
8 – 9 May 2013 Senior Highway
Engineer, Senior Road Safety Audit Engineer,
Environmental Specialist, and Social
Impact Specialist. Simpang
Rampa – Poriaha, and
Sibolga – Batas Tapsel
Join survey for technical review and environmental aspect.
21 – 24 May 2013
Environmental Specialist
Manggopoh – Padang
Sawah – Sp. Empat in West
Sumatra, and Krui – Biha in
Lampung World Bank Review Mission.
22 – 24 May 2013
Community Development Officer
and Assistant Community
Development Officer Palembang
Selection and training of WPM for Krui – Biha and Ipuh –
Bantal.
26 – 28 May 2013
Community Development Officer
and Assistant Community
Development Officer Padang
Selection and training of WPM for Manggopoh – Padang
Sawah.