Monthly Progress Report May 2013 Western I ndonesia National Roads I mprovement Project 15 CTC. Progress of Technical Design Reviewing up to the end of May 2013 is included as Appendix B.

4.2 Procurements

Procurement shall be conducted under the Bank’s Procurement Procedures as mentioned in the Loan Agreement. The International Competitive Bidding ICB will apply to the packages with the construction estimated cost more than US 10 Million to comply with the Bank’s threshold for ICB. According to the GOI regulation, a prequalification shall be applied for the packages with the construction estimated cost more than IDR 10 Billion. Therefore, all subprojects for WP-1 have been started with prequalification since 30 December 2011 for ICB multiple contract. This was an advanced procurement action agreed by both DGH and the World Bank prior to the CTC establishment. The deadline of Qualification Document submission by the Applicants was on 28 February 2012. There are twenty nine 29 Applicants who submitted and applied their qualification documents for various packages which are summarized as follow. • Package No. 1 Krui – Biha : 13 Applicants applied. • Package No. 2 Pd. Sawah – Sp. Empat : 13 Applicants applied. • Package No. 3 Manggopoh – Pd. Sawah : 18 Applicants applied. • Package No. 4 Ipuh – Bantal : 12 Applicants applied. All three 3 Procurement Teams or Pokja evaluated all qualification documents submitted by those Applicants. Submission of the Application Evaluation Report AER to the Bank was on 9 May 2012 for two packages Package No.1 and No.4 and on 20 June 2012 for other two packages Package No.2 and No.3. The Bank still reviews the AERs and requested the Pokja to submit supporting documents. The latest request from the Bank was sent to DGH on 15 March 2013 for board of director and board of commissioner information of the Government’s Entity participated in the prequalification. Finally, the Bank approved the AERs with issuance letter Ref. No. WINRIP120 dated 22 April 2013. All the prequalified Bidders have been announced by DGH on 17 May 2013. The results of prequalification are summarized as the table below. No Singles JO Legal Name Participate and Result of the PQ Package No.1 Package No.2 Package No.3 Package No.4 1 PT. AdhiKarya Persero, Tbk. Passed NA NA Passed 2 PT. AdhiKarya - PT. AngkasapuriKonsursindo, JO. NA Passed Passed NA 3 PT. BangunCiptaKonstruksi - PT. AmartaKarya Persero, JO. Passed NA NA NA 4 PT. BrantasAbipraya Persero Passed NA Passed NA 5 PT. Citra GadingAsritama NA NA NA Passed 6 PT. ConblocInfratecno Passed NA Passed NA 7 PT. Duta Graha Indah, Tbk. Passed Passed Passed NA 8 PT. HutamaKarya Persero NA Passed Passed NA 9 PT. HutamaKarya Persero - PT. SuciKarya Bad inusa, JO. Passed NA NA Passed 10 PT. Jaya Konstruksi MP, Tbk. Passed Passed Passed Failed 11 Kuk Dong Eng. Corp. - PT. Duta Graha Indah, Tbk., JO. NA NA NA Passed 12 PT. Multi Structure Passed Passed Passed Passed 13 PT. NindyaKarya Persero NA Failed Passed Failed 14 PT. NindyaKarya Persero - PT. RindangTigasatuPratama, JO. Passed NA NA NA 15 Pan Asia Corp. - PT. AnugerahKarya Agra Sentosa, JO. Passed NA Passed Failed Monthly Progress Report May 2013 Western I ndonesia National Roads I mprovement Project 16 No Singles JO Legal Name Participate and Result of the PQ Package No.1 Package No.2 Package No.3 Package No.4 16 PT. PP Persero, Tbk. NA Passed Passed NA 17 PT. PP Persero Tbk - PT. Tri Citra Perdana JO. Passed NA NA Passed 18 PT. WaskitaKarya Persero NA Passed Passed NA 19 PT. WaskitaKarya Persero - PT. AngkasaPuriKonsursindo, JO. Passed NA NA NA 20 PT. WaskitaKarya Persero - PT. DayaMuliaTurangga, JO. NA NA NA Passed 21 PT. WijayaKarya – PT. LubukMinturunKaryaPersada, JO. NA Passed Passed Passed 22 PT. Yasa Patria Perkasa NA NA Passed NA 23 PT. AngkasaTeknik Raya NA Failed Failed NA 24 PT. BangunCipta - Barettamuda KSO. NA NA Failed NA 25 PT. BumiRejo Failed NA NA Failed 26 PT. CiptaKarya Prima Mandiri NA Failed Failed NA 27 PT. SumberBatu NA Failed NA NA 28 Synohidro Co. Ltd. NA Failed Failed NA 29 PT. TelagaMegabuana - PT. Mawatindo Road Construction, JO NA NA Failed NA Number Of Applicants submitted the document 13 13 18 12 Number Of Qualified Applicant 12 8 13 8 Number Of Applicant failed to fulfill the qualification requirement 1 5 5 4 Note : NA = Not Applied for Prequalification . The consolidated multiple contracts ICB Bidding Documents for four 4 packages under AWP-1 had been concurred by Bank on 31 October 2012. Following the Bank’s approval for prequalified Bidders, the Invitation for Bid was sent to all prequalified Bidders on 27 May 2013 and the Bidding Document approved by the Bank was issued. Pre Bid Meeting is planned to be held in early June 2013. The WINRIP Procurement Plan is shown in Appendix E. 4.3 Civil Works Implementation Until the end of May 2013, there was no subproject contracted.

4.4 Civil Works Progress

No civil works progress can be reported since there was no subproject contracted until the end of May 2013.

4.5 Quality Assurance

The DSC will be responsible for quality assurance of materials and workmanship, certifying whether or not contractors have achieved the required results, as well as documentation and reporting based on the financial management plan. They will prepare a Quality Assurance system covering all subprojects, and continuously monitor the effectiveness of their supervision procedures. The CTC will give guidance to them preparing quality assurance system including standard operation procedures for all work items under the contract based on contract specification. He is also responsible to conduct regular monitoring on the quality assurance for all civil works implementation. A Quality Assurance Engineer of the CTC will be in charged soonest.