Current status of the project for technical field as of 31 May 2013.

Monthly Progress Report May 2013 Western I ndonesia National Roads I mprovement Project 40 AWP -3 14 Painan – Kambang Link No.017.1 15 Sibolga –Bts TapSel Link No.016.1 completed completed completed ongoing Full Technical Review Report is not completed yet by CTC 16 Seblat–Ipuh Link No.010.0 17 Sp.GngKemala–Pg.Tampak Link No.061.1 18 Mukomuko –Bts.Sumbar Link No.015.3 19 Lais - Bintuan Link No.009.1 20 Lubuk Alung– Sicincin Link No.009.1 21 Lubuk Alung– Kuraitaji Link No.009.1 NEW 1 Jalan Sebelat – Ketahun Link No.013.005 2 Betungan – Tais Link No.013.018 6.6 Environmental and Social Impact Issues 6.6.1. LARAP for Package No. 01 : Krui – Biha The report was concurred by the World Bank on 4 January 2013. The draft Monitoring LARAP Report was prepared and submitted by the CTC to PMU on 27 March 2013. The report was then submitted to the Bank on 10 April 2013 and approved by the Bank on 18 April 2013. The package is ready for civil works contract implementation. The Bank visited the site on 23 to 24 May 2013 regarding compensation payment process, interview with PAPs sampling only and other information related to the land acquisition.

6.6.2. LARAP for Package No. 02 : Padang Sawah – Simpang Empat

The report was concurred by the World Bank on 13 January 2013. The draft Monitoring LARAP Report was prepared and submitted by the CTC to PMU on 27 March 2013. The report was then submitted to the Bank on 2 April 2013 and approved by the Bank on 18 April 2013. The package is ready for civil works contract implementation. The Bank visited the site on 21 to 22 May 2013 regarding compensation payment process, interview with PAPs sampling only and other information related to the land acquisition.

6.6.3. LARAP for Package No. 03 : Manggopoh – Padang Sawah

The report was concurred by the World Bank on 4 January 2013. The draft Monitoring LARAP Report was prepared and submitted by the CTC to PMU on 27 March 2013. The report was then submitted to the Bank on 2 April 2013 and approved by the Bank on 18 April 2013. The package is ready for civil works contract implementation. The Bank visited the site on 21 to 22 May 2013 regarding compensation payment process, interview with PAPs sampling only and other information related to the land acquisition. Monthly Progress Report May 2013 Western I ndonesia National Roads I mprovement Project 41

6.6.4. LARAP for Package No. 04 : Ipuh – Bantal

The report was concurred by the World Bank on 10 December 2012. The Monitoring LARAP Report is being prepared by the CTC. A site visit to Subproject Ipuh-Bantal in Bengkulu Province was conducted by Environmental Specialist during 13 – 15 March 2013 to check the status of land to be acquired, to estimate of land area which is affected by the project and to identify the type of land asset affected by project to carry out interview with PAPs, to get information related land acquisition process and to check the current status of the Appraisal Team readiness for payment of the land acquisition. The CTC found that the land and asset of PAPs have not been paid by the project. Until the end of April 2013, the land acquisition process is still ongoing.

6.6.5. CTC Site Visit Related to the Land Acquisition

CTC conducted site visit to package No.5 Sp.Rampa – Poriaha, 11.10 km and No 15 Sibolga - Batas Tapsel, 36 km in Kabupaten Tapanuli Tengah, North Sumatra Province on 8 to 9 May 2013. CTC checked the following current situation for: i the estimated number of project affected people PAP along the corridor, 2 status of land to be acquired, iii stimate of land square will be affected by the project, and iv type of land asset affected by project. During interview with seperate of PAPs sampling, the CTC found that 1 one kiosk in link of Sp.Rampa - Poriaha will be affected by project. It also found that many land square and asset of PAPs in 5 five Kecamatan along the link of Sibolga-Bts. Tapsel will be affected by project.

6.7 Management Information Systems

The Information Management Specialist has been mobilized. He started his assignment on the beginning of May 2013. During this month, he developed a file storage system as described in section 5.3.2 above. File Storage System The first step of management information system preparation is providing a file storage system. PMU, CTC, DSC and other key stakeholders will produce a lot of documents and reports during WINRIP implementation. Traffic of data and information is predicted to be crowded and busy. A tool is needed to facilitate this condition. The File Storage Server, with large data storage capacity, will serve as storage and file sharing and it can be accessed via online internet. Physically, the File Storage server is located in the CTC-WINRIP office. All of staff on CTC-WINRIP can easily and quickly to access server via local network. And an administrator can monitor and keep the data and server running well and safely. For those who are outside of CTC-WINRIP can access the server using a web browser like Internet Explorer, Mozilla Firefox or Google Chrome. They just type in the URL address http:storage.winrip-ibrd.com . A username and password are needed to log in as shown in the following figure.