Monthly Progress Report September 2013
Western I ndonesia National Roads I mprovement Project 40
6.8 Quality Assurance
Quality Assurance Engineer has been mobilized now. But the quality assurance activities for the project cannot be reported due to the end of September 2013, there
has been no work activity at the beginning.
6.9 Project Risks and Mitigation Measures 6.9.1
Risks Related to Delays
Since the detailed engineering design DED is under responsibility of the Design and Supervision Consultant DSC, delay on DSC establishment affected to the
procurement of AWP-2 and AWP-3 sub-projects. As discussed previously above, the DED of several subprojects of WP-2 and WP-3 were prepared and completed by
respective P2JN. The CTC has then been instructed by DGH to review the DEDs of seven packages completed by the P2JNs package 5, 6, 11, 13, 15, 17 and 19.
6.9.2 Financial Risks
The following factors will be monitored during implementation of the loan project. •
Loan Amount •
Actual Tender Prices •
Price Adjustment •
Currency Fluctuation •
Current Estimated Situation No risk was detected until preparation of this report since the main program of the
loan civil works implementation has not yet been started with contract sign.
6.9.3 Risks Related to Quality
The quality of work is inherently tied to the competence of the Contractors and the diligence of the Supervision Teams. The competence or otherwise of contractors
shall be considered at the time of bid evaluation and prior to the award of any contract.
The quality of supervision however is influenced by the following factors: •
Ensuring that supervision staff levels are fully manned with competent, honest, qualified and experienced personnel.
• The provision of properly equipped laboratories with properly trained
operators for each package. Package supervision comes under the responsibilities of the immediate supervision
teams and the relevant DSC but the Quality Assurance Engineer from CTC, when mobilized, will periodically monitor their performance.
Until now, the performances have not been reported by the Quality Assurance Engineer from CTC, because the works activity has not started
.
Monthly Progress Report September 2013
Western I ndonesia National Roads I mprovement Project 41
7 ISSUES and RECOMMENDATIONS
7.1 Current Situation
The main issue during September 2013 is the NOL Bank for BER of 4 Packages had been approved. The Ministry of Public Work through BAPEKON still review the BER for
approval. The issues was there is one bidder proposed to award contract in 3 packages.
The existing road conditions of the four packages under AWP-1, which are predicted being deteriorated rapidly by the traffic during almost a year, shall be anticipated.
Another issue is establishment and mobilization of the Design and Supervision Consultant DSC especially the Design Team. The DEDs for AWP-2 and AWP-3
packages, including the 7 packages under CTC review at the current time, shall be completed soonest and the procurement can be started immediately.
7.2 Action Required
Based on the past experience when the Pokja need long time to prepared the AER, for this bidding stage hopefully the POKJA could be finalized the Bidding Evaluation Report
BER in sufficient time as scheduled with full support from CTC WINRIP.
It is required to immediately mobilize the Design Team of DSC contract signing process following up the contract signing on June 11, 2013.