Detailed Design Preparation WINRIP DOC MPR CTC MPR No.9 2013 09 2013 09 09 00225.
Monthly Progress Report September 2013
Western I ndonesia National Roads I mprovement Project 14
100 billion based on Perpres 70, th. 2013, DGH has also completed the draft of consolidated multiple contract ICB Standard Bidding
Document for four 4 packages under AWP-1. The draft had been submitted to the Bank on 8 March 2012. The Bank’s comments had been issued on 12 March 2012. The draft of
consolidated SBD was revised by DGH accommodating the Bank’s comments and submitted to the Banks on 27 June 2012. Second revision of the draft consolidated SBD,
as requested by the Bank regarding synchronization between drawings and Bill of Quantities by letter dated 1 August 2012, was then concurred by the Bank on 31 October
2012.
CTC had also involved in Selection of DSC WINRIP since March 2013, started by attend the opening of Financial Proposal on March 5, 2013. Procurement committee for
Selection of DSC had sent Technical Evaluation Report TER to the Bank on December 20, 2013 and had received the approval from the Bank on February 21, 2013. The Final
Evaluation Report including Technical and Financial Evaluation and completed with Notice of Negotiation and Draft Contract then was sent to Bank by the committee on April
3
rd
, 2013. NOL from the Bank was received on April 19, 2013 to Renardet, SA Switzerland cs as the first rank of technical and financial evaluation result. Finally the
contract for this assignment was sign on June 11, 2013.
The WINRIP Procurement Plan is shown in Appendix F. 4.3 Civil Works Implementation
Until the end of September 2013, there was no subproject contracted.