All activities which have undertaken during this month

Monthly Progress Report September 2013 Western I ndonesia National Roads I mprovement Project 37 Date Activity 18 September 2013 Attendance the Meeting for WINRIP technical discussion regarding DED which is package 6111319 of AWP-2 in Benglkulu province, at Ministry of Public Workss office. The CTC teamsenior highway engineer, senior road safety auditor, highway engineer joined the Ministry of Public Works meeting with the BINTEK, P2JN, to discuss about package 1113619 of AWP-2,3 in Benglkulu province regarding DEDDetailed Engineering Design in order to finalize about identify major issues in aspect of highway road safety for the DED, and then so as to make a decision for construction amount FED through final reporting. • Project List for Technical Discussion Meeting 4 Pacakges in Bengkulu - No.11 BANTAL - MUKOMUKO Link No.015.2, Bengkulu Province - No.13 SP.RUKIS - TJ.KEMUNING Link No.006.0 , Bengkulu Province - NO.6 PS.PEDATI - KERKAP Link No.010.0 , Bengkulu Province - No. 19 LAIS - BINTUAN Link No.009.1 , Bengkulu Province

6.5.2 Current status of the project for technical field as of 30 September 2013.

The details of Progress of Technical Design Reviewing in aspect of road safety audit as of the end of September 2013 is included as Appendix B. Technical Design Review Road Safety Audit Report Status Group Pack No. Name of Sub-project Technical Design Review Road Safety Audit Submitted to PMU Post -Review Site Visting Full -Review Technical Report AWP -2 5 Sp.Rampa – Poriaha Link No.015.xx completed completed completed completed Final Technical Report is resubmitted on 17th September 2013 6 PS.Pedati - Kerkap Link No.010.0 completed completed completed completed Final Technical Report is submitted on 17th September 2013 7 Indrapura – Tapan Link No.019.0 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 27th September 2013 8 Bts.Pariaman – Manggopoh Link No.024.0 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 27th September 2013 9 Rantau Tijang – Kota Agung Link No.026.1 10 Sp.Empat – Sp. Air Balam Link No.034.1 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 27th September 2013 11 Bantal - Mukomuko Link No.015.2 completed completed completed completed Final Technical Report is resubmitted on 16th August 2013 12 Kambang – Indrapura Link No.017.2 - By DSC - By DSC - By DSC Technical Advisory Final Technical Advisory is submitted on 27th September 2013 13 SP.Rukis - TJ.Kemuning Link No.006.0 completed completed completed completed Final Technical Report is resubmitted on 16th August 2013 AWP -3 14 Painan – Kambang Link No.017.1 15 Sibolga – Bts TapSel Link No.016.1 completed completed completed completed Final Technical Report is submitted on 23th September 2013 16 Seblat – Ipuh Link No.010.0 Monthly Progress Report September 2013 Western I ndonesia National Roads I mprovement Project 38 Group Pack No. Name of Sub-project Technical Design Review Road Safety Audit Submitted to PMU Post -Review Site Visting Full -Review Technical Report 17 Sp.Gng Kemala–Pg.Tampak Link No.061.1 18 Mukomuko – Bts.Sumbar Link No.015.3 19 Lais - Bintuan Link No.009.1 completed completed completed completed Final Technical Report is submitted on 17th September 2013 20 Lubuk Alung – Sicincin Link No.009.1 21 Lubuk Alung – Kuraitaji Link No.009.1 NEW 1 Jalan Sebelat – Ketahun Link No.013.005 2 Betungan – Tais Link No.013.018 6.6 Environmental and Social Impact Issues 6.6.1 LARAP Study Report for Package No. 01 : Krui – Biha The report was concurred by the World Bank on 4 January 2013. The draft Monitoring LARAP Report was prepared and submitted by the CTC to PMU on 27 March 2013. The report was then submitted to the Bank on 10 April 2013 and approved by the Bank on 18 April 2013. The package is ready for civil works contract implementation. The CTC was revised Monitoring LARAP Report and submitted to PMU on 18 June 2013 and to the Bank on 21 June 2013 then the Bank approval on 26 June 2013. The SPPL report was submit to the Bank on 30 September 2013. 6.6.2 LARAP Study Report for Package No. 05 : Sp. Rampa – Poriaha The CTC was revised LARAP Report and submitted to PMU on 30 August 2013 and to the Bank on 10 September 2013 then the Bank approval on 16 September 2013. The bidding process can start for this package.

6.6.3 LARAP Study Report for Package No. 06: Ps. Pedati – Kerkap

The CTC was revised the LARAP report and submit to PMU on 29 October 2013, PMU will process the report to Bank. The UKLUPL was submit to Bank on 30 September 2013