Monthly Progress Report September 2013
Western I ndonesia National Roads I mprovement Project 37
Date Activity
18 September 2013
Attendance the Meeting for WINRIP technical discussion regarding DED which is package 6111319 of AWP-2 in Benglkulu province, at Ministry of Public Workss office.
The CTC teamsenior highway engineer, senior road safety auditor, highway engineer joined the Ministry of Public Works meeting with the BINTEK, P2JN, to discuss about package
1113619 of AWP-2,3 in Benglkulu province regarding DEDDetailed Engineering Design in order to finalize about identify major issues in aspect of highway road safety for the DED,
and then so as to make a decision for construction amount FED through final reporting.
•
Project List for Technical Discussion Meeting 4 Pacakges in Bengkulu
- No.11 BANTAL - MUKOMUKO Link No.015.2, Bengkulu Province
- No.13 SP.RUKIS - TJ.KEMUNING Link No.006.0 , Bengkulu Province
- NO.6 PS.PEDATI - KERKAP Link No.010.0 , Bengkulu Province
- No. 19 LAIS - BINTUAN Link No.009.1 , Bengkulu Province
6.5.2 Current status of the project for technical field as of 30 September 2013.
The details of Progress of Technical Design Reviewing in aspect of road safety audit as of the end of September 2013 is included as Appendix B.
Technical Design Review Road Safety Audit Report Status Group
Pack No.
Name of Sub-project Technical Design Review Road Safety Audit
Submitted to PMU
Post -Review
Site Visting
Full -Review
Technical Report
AWP -2
5 Sp.Rampa – Poriaha
Link No.015.xx completed completed completed
completed Final Technical Report is
resubmitted on 17th September 2013
6 PS.Pedati - Kerkap
Link No.010.0 completed completed completed
completed Final Technical Report is
submitted on 17th September 2013
7 Indrapura – Tapan
Link No.019.0 -
By DSC -
By DSC -
By DSC Technical
Advisory Final Technical Advisory is
submitted on 27th September 2013
8 Bts.Pariaman – Manggopoh
Link No.024.0 -
By DSC -
By DSC -
By DSC Technical
Advisory Final Technical Advisory is
submitted on 27th September 2013
9 Rantau Tijang – Kota Agung
Link No.026.1 10
Sp.Empat – Sp. Air Balam Link No.034.1
- By DSC
- By DSC
- By DSC
Technical Advisory
Final Technical Advisory is submitted
on 27th September 2013 11
Bantal - Mukomuko Link No.015.2
completed completed completed completed
Final Technical Report is resubmitted
on 16th August 2013 12
Kambang – Indrapura Link No.017.2
- By DSC
- By DSC
- By DSC
Technical Advisory
Final Technical Advisory is submitted
on 27th September 2013 13
SP.Rukis - TJ.Kemuning Link No.006.0
completed completed completed completed
Final Technical Report is resubmitted
on 16th August 2013
AWP -3
14 Painan – Kambang
Link No.017.1 15
Sibolga – Bts TapSel Link No.016.1
completed completed completed completed
Final Technical Report is submitted
on 23th September 2013
16 Seblat – Ipuh
Link No.010.0
Monthly Progress Report September 2013
Western I ndonesia National Roads I mprovement Project 38
Group Pack
No. Name of Sub-project
Technical Design Review Road Safety Audit Submitted to
PMU Post
-Review Site
Visting Full
-Review Technical
Report
17 Sp.Gng Kemala–Pg.Tampak
Link No.061.1 18
Mukomuko – Bts.Sumbar Link No.015.3
19 Lais - Bintuan
Link No.009.1 completed completed completed
completed Final Technical Report is
submitted on 17th September 2013
20 Lubuk Alung – Sicincin
Link No.009.1 21
Lubuk Alung – Kuraitaji Link No.009.1
NEW
1 Jalan Sebelat – Ketahun
Link No.013.005 2
Betungan – Tais Link No.013.018
6.6 Environmental and Social Impact Issues 6.6.1
LARAP Study Report for Package No. 01 : Krui – Biha
The report was concurred by the World Bank on 4 January 2013. The draft Monitoring LARAP Report was prepared and submitted by the CTC to PMU on 27
March 2013. The report was then submitted to the Bank on 10 April 2013 and approved by the Bank on 18 April 2013. The package is ready for civil works contract
implementation.
The CTC was revised Monitoring LARAP Report and submitted to PMU on 18 June 2013 and to the Bank on 21 June 2013 then the Bank approval on 26 June 2013.
The SPPL report was submit to the Bank on 30 September 2013. 6.6.2
LARAP Study Report for Package No. 05 : Sp. Rampa – Poriaha
The CTC was revised LARAP Report and submitted to PMU on 30 August 2013 and to the Bank on 10 September 2013 then the Bank approval on 16 September 2013.
The bidding process can start for this package.
6.6.3 LARAP Study Report for Package No. 06: Ps. Pedati – Kerkap
The CTC was revised the LARAP report and submit to PMU on 29 October 2013, PMU will process the report to Bank.
The UKLUPL was submit to Bank on 30 September 2013