Current status of the project for technical field as of 30 September 2013.

Monthly Progress Report September 2013 Western I ndonesia National Roads I mprovement Project 38 Group Pack No. Name of Sub-project Technical Design Review Road Safety Audit Submitted to PMU Post -Review Site Visting Full -Review Technical Report 17 Sp.Gng Kemala–Pg.Tampak Link No.061.1 18 Mukomuko – Bts.Sumbar Link No.015.3 19 Lais - Bintuan Link No.009.1 completed completed completed completed Final Technical Report is submitted on 17th September 2013 20 Lubuk Alung – Sicincin Link No.009.1 21 Lubuk Alung – Kuraitaji Link No.009.1 NEW 1 Jalan Sebelat – Ketahun Link No.013.005 2 Betungan – Tais Link No.013.018 6.6 Environmental and Social Impact Issues 6.6.1 LARAP Study Report for Package No. 01 : Krui – Biha The report was concurred by the World Bank on 4 January 2013. The draft Monitoring LARAP Report was prepared and submitted by the CTC to PMU on 27 March 2013. The report was then submitted to the Bank on 10 April 2013 and approved by the Bank on 18 April 2013. The package is ready for civil works contract implementation. The CTC was revised Monitoring LARAP Report and submitted to PMU on 18 June 2013 and to the Bank on 21 June 2013 then the Bank approval on 26 June 2013. The SPPL report was submit to the Bank on 30 September 2013. 6.6.2 LARAP Study Report for Package No. 05 : Sp. Rampa – Poriaha The CTC was revised LARAP Report and submitted to PMU on 30 August 2013 and to the Bank on 10 September 2013 then the Bank approval on 16 September 2013. The bidding process can start for this package.

6.6.3 LARAP Study Report for Package No. 06: Ps. Pedati – Kerkap

The CTC was revised the LARAP report and submit to PMU on 29 October 2013, PMU will process the report to Bank. The UKLUPL was submit to Bank on 30 September 2013 Monthly Progress Report September 2013 Western I ndonesia National Roads I mprovement Project 39

6.6.4 LARAP Study Report for Package No. 07 : Indrapura – Tapan under preparation by

Balai II

6.6.5 LARAP Study Report for Package No. 08 : Bts Kota Pariaman – Manggopoh

The CTC was revised the LARAP report and submit to PMU on 9 September 2013, PMU requested to Balai IIthe LARAP consultant to review the report based on CTC comments.

6.6.6 LARAP Study Report for Package No. 09 : Rantau Tijang – Kota Agung

6.6.7 LARAP Study Report for Package No. 10 : Sp. Empat – Air Balam

The CTC was revised the LARAP report and submit to PMU on 9 September 2013, PMU requested to Balai IIthe LARAP consultant to review the report based on CTC comments

6.6.8 LARAP Study Report for Package No. 12 : Kambang – Indrapura

The CTC was revised the LARAP report and submit to PMU on 9 September 2013, PMU requested to Balai IIthe LARAP consultant to review the report based on CTC comments.

6.6.9 LARAP Study Report for Package No. 15 : SP. Gunung Kemala – Pg. Tampak

The CTC was revised LARAP Report and submitted to PMU on 30 August 2013 and to the Bank on 10 September 2013 then the Bank approval on 16 September 2013. The bidding process can start for this package. The AMDAL has submit to the Bank on 30 September 2013 and approved

6.6.10 LARAP Study Report for Package No. 20 : Lubuk Alung – Sicincin

The UKLUPL has submit to the Bank on 30 September 2013

6.6.11 LARAP Study Report for Package No. 20: Lubuk Alung – Kuraitaji

The UKLUPL has submit to the Bank on 30 September 2013

6.7 Management Information Systems

The Information Management Specialist has been mobilized. The activity for management information system will be reported on appendix G.