Monthly Progress Report September 2013
Western I ndonesia National Roads I mprovement Project 38
Group Pack
No. Name of Sub-project
Technical Design Review Road Safety Audit Submitted to
PMU Post
-Review Site
Visting Full
-Review Technical
Report
17 Sp.Gng Kemala–Pg.Tampak
Link No.061.1 18
Mukomuko – Bts.Sumbar Link No.015.3
19 Lais - Bintuan
Link No.009.1 completed completed completed
completed Final Technical Report is
submitted on 17th September 2013
20 Lubuk Alung – Sicincin
Link No.009.1 21
Lubuk Alung – Kuraitaji Link No.009.1
NEW
1 Jalan Sebelat – Ketahun
Link No.013.005 2
Betungan – Tais Link No.013.018
6.6 Environmental and Social Impact Issues 6.6.1
LARAP Study Report for Package No. 01 : Krui – Biha
The report was concurred by the World Bank on 4 January 2013. The draft Monitoring LARAP Report was prepared and submitted by the CTC to PMU on 27
March 2013. The report was then submitted to the Bank on 10 April 2013 and approved by the Bank on 18 April 2013. The package is ready for civil works contract
implementation.
The CTC was revised Monitoring LARAP Report and submitted to PMU on 18 June 2013 and to the Bank on 21 June 2013 then the Bank approval on 26 June 2013.
The SPPL report was submit to the Bank on 30 September 2013. 6.6.2
LARAP Study Report for Package No. 05 : Sp. Rampa – Poriaha
The CTC was revised LARAP Report and submitted to PMU on 30 August 2013 and to the Bank on 10 September 2013 then the Bank approval on 16 September 2013.
The bidding process can start for this package.
6.6.3 LARAP Study Report for Package No. 06: Ps. Pedati – Kerkap
The CTC was revised the LARAP report and submit to PMU on 29 October 2013, PMU will process the report to Bank.
The UKLUPL was submit to Bank on 30 September 2013
Monthly Progress Report September 2013
Western I ndonesia National Roads I mprovement Project 39
6.6.4 LARAP Study Report for Package No. 07 : Indrapura – Tapan under preparation by
Balai II
6.6.5 LARAP Study Report for Package No. 08 : Bts Kota Pariaman – Manggopoh
The CTC was revised the LARAP report and submit to PMU on 9 September 2013, PMU requested to Balai IIthe LARAP consultant to review the report based on CTC
comments.
6.6.6 LARAP Study Report for Package No. 09 : Rantau Tijang – Kota Agung
6.6.7 LARAP Study Report for Package No. 10 : Sp. Empat – Air Balam
The CTC was revised the LARAP report and submit to PMU on 9 September 2013, PMU requested to Balai IIthe LARAP consultant to review the report based on CTC
comments
6.6.8 LARAP Study Report for Package No. 12 : Kambang – Indrapura
The CTC was revised the LARAP report and submit to PMU on 9 September 2013, PMU requested to Balai IIthe LARAP consultant to review the report based on CTC
comments.
6.6.9 LARAP Study Report for Package No. 15 : SP. Gunung Kemala – Pg. Tampak
The CTC was revised LARAP Report and submitted to PMU on 30 August 2013 and to the Bank on 10 September 2013 then the Bank approval on 16 September 2013.
The bidding process can start for this package.
The AMDAL has submit to the Bank on 30 September 2013 and approved
6.6.10 LARAP Study Report for Package No. 20 : Lubuk Alung – Sicincin
The UKLUPL has submit to the Bank on 30 September 2013
6.6.11 LARAP Study Report for Package No. 20: Lubuk Alung – Kuraitaji
The UKLUPL has submit to the Bank on 30 September 2013
6.7 Management Information Systems
The Information Management Specialist has been mobilized. The activity for management information system will be reported on appendix G.