Monthly Progress Report September 2013
Western I ndonesia National Roads I mprovement Project 30
• WINRIP Increased Threshold for Prior Review by the Bank of Procurement
Transaction •
Mobilization the Social Impact Specialist. The following table summarized the CTC personnel field activities during September
2013.
.
Date Position
Destination Purpose
16-18 September Environmental Specialist
Lampung LARAP Socialization for Package
No. 17 : Sp Gunung Kemala – Pugung Tampak
16-20 September Social Impact Specialist
Bengkulu LARAP Socialization for Package
No. 6 : Kerkap –Ps Pedati Package No. 13 : Sp. Rukis –
Tanjung Kemunging Package No. 11 : Bantal Mukomuko
16-18 September Quality
Assurance Specialist
Lampung Orientation Project and Discussion
with PPK Package NO. 1 :
24-27 September Social Impact Specialist
Bengkulu Socialization
Residents in
Kecamatan Pondok Hijau and Kecamatan
Lais for
Land Acquisition Jalan Nasional Ruas
Binturan Lais and Pondok Hijau
6.2.2 Design and Supervision Consultant DSC
The Design and Supervision Consultant DSC will be responsible for design of WP 2 and WP 3 civil works and supervision of all civil works. They will have the role of
‘Engineer’ under a FIDIC-type contract. The tasks include the preparation and maintenance of a quality assurance plan, validation and updating of designs,
supervision of all civil works, environmental and social monitoring and management, and support for financial and progress monitoring and reporting.
The DSC will also be responsible for quality assurance of materials and workmanship, certifying whether or not contractors have achieved the required
results, as well as documentation and reporting based on the financial management plan. They will prepare a Quality Assurance system covering all subprojects, and
continuously monitor the effectiveness of their supervision procedures. The team will be contracted and managed by DGH through the Bina Marga Regional Office Balai
II, and will be based in Padang, West Sumatra.
DSC contract was negotiated in Balai Besar Pelaksanaan Jalan Nasional II Balai-II of DGH. The negotiation result and draft contract have been sent to WB on 25 March
2013 for review and approval. The Bank issued no objection letter on the negotiation results and draft contract with letter dated 19 April 2013.
6.2.3 Road Sector Institutional Development
This component consists of technical assistance for capacity building for the new environmentrisk mitigation and road safety unit to enhance its capacity for disaster
risk assessment and planning, risk mapping of land-slides, coastal erosion, earthquake and floods, analysis of alternative road designs for road segments
passing through critical environmental assets and vulnerable areas.