Disbursement WINRIP DOC MPR CTC MPR No.40 2016 4 20160430 00383

Western I ndonesia National Roads I mprovement Project 1 - 6 The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB method using the Full e-Procurement System. Bid Evaluation Report BER has been completed by POKJA and submitted to World Bank on January 11, 2016 for review and issuance of No Objection Letter NOL. However, per Bank s letter of January 20, 2016 regarding results of their prior review of the BER have comments on the proposed disqualification of five 5 lower priced bidders. In response with the Banks comments, POKJA explained in details the reasons to disqualify the five 5 lower priced bidders. The detailed explainations, justifications and resubmission of the Revised Bid Evaluation Report BER were forwarded to the Bank thru letter of March 21, 2016 by the Director of Road Network Development. The Revised Bid Evaluation Report BER and recommendation for award of the contract remain to be the same bidder as previously proposed in the original Bid Evaluation Report BER.

4. Package No.14 Painan - Kambang AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road length covers 31.50 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As mentioned earlier, there were four 4 applicant bidders 3 sole entity and 1 joint venture operation who submitted bids for the civil works implementation. Following are the four 4 bidders with their respective bid prices : • PT. Yasa Patria Perkasa Conbloc, JO Rp. 214,602,400,000 • PT. Waskita Karya Rp. 239,449,604,000 • PT. Jaya Konstruksi Rp. 239,628,825,000 • PT. PP Rp. 249,277,000,000 The lowest canvassed bid is submitted by the joint venture operation of PT. Yasa Patria Perkasa and Conbloc with an amount of Rp. 214,602,400,000 which is 19.80 below the approved Owner s Estimate OE of Rp. 267,590,800,000 while the 2 nd lowest bid is quoted by PT. Waskita Karya with an amount of Rp. 239,449,604,000 or 10.58 lower than the Owner s Estimate. During this reporting month, on April 4, 2016, the World Bank issued No Objection Letter NOL on the Bid Evaluation Report BER and recommendation for award of contract to the evaluated lowest responsive bidder, PT. Yasa Patria Perkasa Conbloc, JO, for a corrected contract amount of Rp.214,327,429,680. The Original expiry date of bid validity expired on April 4, 2016, but have been extended for 28 days or until May 2, 2016. However, as the month of April 2016 was about to end with still no execution of the signing of Contract Agreement, the bid validity period has been extended for the 2 nd time for another 50 days or until June 20, 2016.

5. Package No.20 Lubuk Alung - Sicincin AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Western I ndonesia National Roads I mprovement Project 1 - 7 Project road lenght covers 14.60 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As mentioned earlier, there were five 5 applicant bidders 4 sole entity and 1 joint venture operation who submitted bids for the civil works implementation. Following are the five 5 bidders with their respective bid prices : • PT. Nindya Karya Rp. 113,818,300,000 • PT. Conbloc Infratechno Statika, KSO Rp. 118,172,039,000 • PT. Waskita Karya Rp. 122,767,255,000 • PT. Jaya Konstruksi Rp. 126,670,765,000 • PT. PP Rp. 125,192,900,000 The lowest canvassed bid is submitted by PT. Nindya Karya with an amount of Rp. 113,818,300,000 which is 13.32 below the approved Owner s Estimate OE of Rp. 131,302,200,000 while the 2 nd lowest bid is quoted by PT. PT. Conbloc Infratechno Statika, KSO Joint Operation with an amount of Rp. 118,172,039,000 or 10.00 lower than the Owner s Estimate. As mentioned in previous Report, the Bid Evaluation Report BER and recommendation for award of contract has been issued No Objection Letter NOL by the World Bank on the Procurement Committee s POKJA recommending the award of contract to the evaluated lowest responsive bidder, PT. Nindya Karya Persero Tbk, for a corrected contract amount of Rp.113,818,304,610. The Original expiry date of bid validity expired on April 4, 2016, but have been extended for 28 days or until May 2, 2016. However, as the month of April 2016 was about to end with still no execution of the signing of Contract Agreement, the bid validity period has been extended for the 2 nd time for another 50 days or until June 20, 2016.

6. Package No.21 Lubuk Alung - Kuraitaji AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road lenght covers 16.80 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As mentioned earlier, there were eight 8 applicant bidders 7 sole entity and 1 joint venture operation who submitted bids for the civil works implementation. Following are the eight 8 bidders with their respective bid prices : • PT. Multi Structure Rp. 126,301,991,200 • PT. Adhi Karya Rp. 133,638,300,000 • PT. Nindya Karya Rp. 141,465,600,000 • Pan Asia Corporation Rp. 143,186,229,000 • PT. Conbloc Infratechno Statika, KSO Rp. 143,227,420,000 • PT. Jaya Konstruksi M,P Rp. 147,718,199,000 • PT. Waskita Karya Rp. 150,966,239,000