Monitoring Report of the LARAP Package No. 6

Western I ndonesia National Roads I mprovement Project 4 - 17 I Sumatera BaratCTC. b PPKSatker PJN I West Sumatera and Local Government continue payment proceessing of the remaining PAP. c Total PAP = 2,166 updated ; Compensated = 1,766 ; Percent complete = 81,53.

9. Monitoring Report of the LARAP Package No. 9

: Rantau Tijang Kota Agung Province : Lampung Cancelled from the WINRIP Program.

10. Monitoring Report of the LARAP Package No. 10 : Sp. Empat Sp. Air Balam

Province : Sumatera Barat A. Previous Status : • LARAP documents submitted to World Bank on August 7, 2014. • LARAP documents approved by World Bank on August 12, 2014. • Compensation payments for 1,615 from the total 2,951 PAPs already paid and Monitoring Report for payment of 1,421 PAPs has been submitted to World Bank on January 14, 2016 and Bank issued No Objection Letter NOL on March 8, 2016. B. Pending Issues, Concern and Actions a Payments for the remaining 1,190 PAPs not yet paid by PPKSatker PJN I West Sumatera and Local Government. C. Update during this reporting month of April 2016 a Monitoring Report for payment of 138 PAPs on-going preparation by Satker PJN I Sumatera BaratCTC. b PPKSatker PJN I West Sumatera and Local Government continue the appraisal and payment proceessing of the remaining PAP. c Total PAP = 2,915 ; Compensated = 1,725 ; Percent complete = 59,18.

11. Monitoring Report of the LARAP Package No. 11 : Bantal - Mukomuko

Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. • Monitoring Report No.1 and No.2 were issued No Objection Letters NOL from the World Bank. • Monitoring Report for 15 of the remaining 123 PAPs was given No Objection Letter NOL on November 26, 2015 B. Pending Issues, Concern and Actions a No more issue. C. Update during this reporting month of April 2016 a Data collection for payment progress of the remaining 108 PAPs is being done by Satker PJN l Bengkulu. b Total PAP = 262 ; Compensated = 262 ; Percent complete =100. Western I ndonesia National Roads I mprovement Project 4 - 18

12. Monitoring Report of the LARAP Package No. 12 : Kambang - Indrapura

Province : Sumatera Barat A. Previous Status : • LARAP documents approved by World Bank on October 14, 2014. • Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank. B. Pending Issues, Concern and Actions a Compensation payments to PAPs are under going finalization by Satker PJN ll West Sumatera . C. Update during this reporting month of April 2016 a No update this month. b Total PAP = 2,337 ; Compensated = nil ; Percent complete = 0.

13. Monitoring Report of the LARAP Package No. 13 : Sp. Rukis Tj. Kemuning

Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. • Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank. • World Bank issued on August 18, 2015 No Objection Letter NOL on the monitoring Report No.1. • World Bank issued on October 13, 2015 No Objection Letter NOL on the monitoring Report No.2. • Monitoring Report No.3 for compensation payments of 193 PAPs in Kab. Kaur submitted to WB which was submitted on February 23, 2016 has been issued by the Bank the NOL on March 8, 2016. B. Pending Issues, Concern and Actions a Compensation payments for 3,030 PAPs can be started upon completion of the revision of DIPA 2016. C. Update during this reporting month of April 2016 a Revision of DIPA 2016 amounting to RP. 14 Billion is under process. b Total PAP = 3,412 ; Compensated = 625 ; Percent complete = 18,32.

14. Monitoring Report of the LARAP Package No. 14 : Painan - Kambang

Province : Sumatera Barat A. Previous Status : • World Bank issued on December 19, 2014 the No Objection Letter to the LARAP documents. • LARAP s signed action plan was given No Objection Letter NOL by World Bank. B. Pending Issues, Concern and Actions a Process of compensation payment is on-going. C. Update during this reporting month of April 2016 a Compensation payment process preparation.