Monitoring Report of the LARAP Package No. 10 : Sp. Empat Sp. Air Balam

Western I ndonesia National Roads I mprovement Project 4 - 19 b Total PAP = 2,323 ; Compensated = nil ; Percent complete = 0.

15. Monitoring Report of the LARAP Package No. 15 : Sibolga Bts. Tapsel

Province : Sumatera Utara A. Previous Status : • World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Right of Ways and removal of obstruction. • Monitoring report No.1 for 40 of the remaining 1.554 PAPs was given No Objection Letter NOL on November 16, 2015. • Monitoring Report No.2 for payment of remaining 72 PAPs already submitted to Wolrd Bank. • Monitoring Report-3 for the compensation payment for 236 from the remaining 1.439 PAPs already be submitted to WB on February 19, 2016 and Bank issued no objection letter NOL on March 16, 2016. B. Pending Issues, Concern and Actions a Due limited to limited suppy of map fields as one of the documents needed for find disbursement by Treasury Office affect the progress of payments release. C. Update during this reporting month of April 2016 a Compensation payment for the remaining PAPs is under process. b Monitoring Report No. 4 for the compensation payments of 55 PAP s is under going preparation by SATKER PJN II North Sumatera and CTC. c Total PAP = 1,554 ; Compensated = 520 ; Percent complete = 33,46.

16. Monitoring Report of the LARAP Package No.16

: Seblat - Ipuh Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. • World Bank issued No Objection Letter NOL on Monitoring Report No.1 and 2 for LARAP implementation. • Monitoring report for 102 of the remaining 120 PAPs was given No Objection Letter NOL on November 26, 2015. • Updated LARAP documents submitted on February 22, 2016 to World Bank with NOL isued by Bank on March 8,2016. B. Pending Issues, Concern and Actions a LARAP documents for this Package covers only land acquisition for the road link. If there are land acquisition for the bridge site, a separate LARAP documents need to be prepared. b LARAP Implementation is underway for the remaining 18 PAP be allocated 2015 national budget and schedule to be settled on Dec 2015. c Monitoring Report for the compensation payments of previously paid PAPs still to be prepared for submission to World Bank. C. Update during this reporting month of April 2016 a Data of the payments to the 18 PAP Balance from 259 PAPs are under preparation by