Western I ndonesia National Roads I mprovement Project 4 - 3
4.4 Civil Works Progress
Activities done during this month were repair and restoration of deteriorated existing pavements, roadway excavation, embankment formation, spreading of granular pavement for roadway widening, asphalt paving,
structural works, construction of stone masonry side ditches, stockpiling of raw material, production of crush aggregates, other minor works, bridge construction and finalization of Field Engineering surveys.
The four 4 contract packages under implementation program AWP-1 were not completed on the original target dates of completion, however, time extensions ranging from 75 to 105 calendar days were granted
extending the completion dates at the earliest on January 10, 2016 and the latest on April 19, 2016.
Previously, two 2 of the contract packages has already been fully completed and recently handed and taken over by the Client, another one 1 package has been completed this period, while the remaining
other contract package under AWP-1 failed to be handed over on the target of completion.
Under the implementation program AWP-2 and AWP-3, there are currently nine 9 contract packages that are on-going construction implementation. Physical progress of three 3 of the packages are lagging far
behind schedule with negative slippages tanging from -17.56 to -62.71 while progress for the other six 6 packages are still slightly on or behind schedule.
Generally, with the exception of the three 3 contract packages with huge negative slippages, the civil works implementation is fairly in the right direction.
Progress status of the on-going civil works contracts as of this reporting period are shown in Table 4.2. Following are brief status of the on-going construction contract packages :
Package No. 1 : Biha Krui The contract package is substantially completed on January 20, 2016 and provisionally handed over to the
Employeer. Currently under Defects Notification Period until after two 2 years reckoned from the issuance of the
TOC. A more detailed previous status during the whole duration of the contract implementation of this Package is
presented in ANNEX P-I Executive Summary Report. Package No. 2 : Padang Sawah Sp. Empat Including Air Gadang Bridge
The contract package is substantially completed on April 19, 2016 and provisionally handed over to the Employeer.
Currently under Defects Notification Period until after two 2 years reckoned from the issuance of the TOC.
ANNEX P-2 Executive Summary Report present a more detailed status during the whole duration of the
contract implementation of the Contract Package.