World Bank Implementation Review Mission and Site Visit

Western I ndonesia National Roads I mprovement Project 1 - 7 Project road lenght covers 14.60 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As mentioned earlier, there were five 5 applicant bidders 4 sole entity and 1 joint venture operation who submitted bids for the civil works implementation. Following are the five 5 bidders with their respective bid prices : • PT. Nindya Karya Rp. 113,818,300,000 • PT. Conbloc Infratechno Statika, KSO Rp. 118,172,039,000 • PT. Waskita Karya Rp. 122,767,255,000 • PT. Jaya Konstruksi Rp. 126,670,765,000 • PT. PP Rp. 125,192,900,000 The lowest canvassed bid is submitted by PT. Nindya Karya with an amount of Rp. 113,818,300,000 which is 13.32 below the approved Owner s Estimate OE of Rp. 131,302,200,000 while the 2 nd lowest bid is quoted by PT. PT. Conbloc Infratechno Statika, KSO Joint Operation with an amount of Rp. 118,172,039,000 or 10.00 lower than the Owner s Estimate. As mentioned in previous Report, the Bid Evaluation Report BER and recommendation for award of contract has been issued No Objection Letter NOL by the World Bank on the Procurement Committee s POKJA recommending the award of contract to the evaluated lowest responsive bidder, PT. Nindya Karya Persero Tbk, for a corrected contract amount of Rp.113,818,304,610. The Original expiry date of bid validity expired on April 4, 2016, but have been extended for 28 days or until May 2, 2016. However, as the month of April 2016 was about to end with still no execution of the signing of Contract Agreement, the bid validity period has been extended for the 2 nd time for another 50 days or until June 20, 2016.

6. Package No.21 Lubuk Alung - Kuraitaji AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road lenght covers 16.80 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As mentioned earlier, there were eight 8 applicant bidders 7 sole entity and 1 joint venture operation who submitted bids for the civil works implementation. Following are the eight 8 bidders with their respective bid prices : • PT. Multi Structure Rp. 126,301,991,200 • PT. Adhi Karya Rp. 133,638,300,000 • PT. Nindya Karya Rp. 141,465,600,000 • Pan Asia Corporation Rp. 143,186,229,000 • PT. Conbloc Infratechno Statika, KSO Rp. 143,227,420,000 • PT. Jaya Konstruksi M,P Rp. 147,718,199,000 • PT. Waskita Karya Rp. 150,966,239,000