Package No.14 Painan - Kambang AWP-3

Western I ndonesia National Roads I mprovement Project 1 - 8 • PT. PP Rp. 154,124,000,000 The lowest canvassed bid is submitted by PT. Multi Structure with an amount of Rp. 126,301,991,200 which is 23.28 below the approved Owner s Estimate OE of Rp. 164,692,268,000 while the 2 nd lowest bid is quoted by PT. Adhi Karya with an amount of Rp. 133,638,300,000 or 18.82 lower than the Owner s Estimate. As mentioned in previous Report, the Bid Evaluation Report BER and recommendation for award of contract has been issued No Objection Letter NOL by the World Bank on the Procurement Committee s POKJA recommending the award of contract to the evaluated lowest responsive bidder, PT. Multi Structure, for a corrected contract amount of Rp.126,301,991,202. The Original expiry date of bid validity expired on April 4, 2016, but have been extended for 28 days or until May 2, 2016. However, as the month of April 2016 was about to end with still no execution of the signing of Contract Agreement, the bid validity period has been extended for the 2 nd time for another 50 days or until June 20, 2016. 1.5 Procurement of Three 3 Consultancy Packages Under Category 3 of the Loan Agreement, Part 3: Road Sector Institutional Development

1. Technical Assistance for Capacity Building for Disaster Risk Reduction

The Technical Assistance for Disaster Risk Reduction was canceled based on the results of meeting between DGH and the WB on October 12, 2015. It was decided to cancel the Technical Assistance and to be replaced by a Technical Assistance for Study on Slope Stabilization Design and Management under Loan Category-2. Term of Reference TOR has already been finalized and submitted to World Bank for concurrence prior to publication on PU Website for Request of Expression of Interest REOI from interested consulting firms.

2. Technical Assistance for Capacity Building for Environmental Management

Cancelled.

3. Technical Assistance for Capacity Building for Road Safety

Cancelled.