Current Implementation Situation Civil Works

Western I ndonesia National Roads I mprovement Project 1 - 3 Length Ction Km Period J N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D 1 Krui - Biha 25,00 21 mth 8 Jan14 2 Padang Sawah - Sp.Empat 40,90 24 mth 6 Jan14 3 Manggopoh - Padang Sawah 32,00 24 mth 6 Jan14 4 Ipuh - Bantal 42,40 24 mth 10 Jan14 5 SIMPANG RAMPA - PORIAHA 11,10 18 mth 18 Jun15 11 Feb17 11 BANTAL - MUKOMUKO 50,10 24 mth 23 Feb15 11 Feb17 13 SP RUKIS - TJ KEMUNING 56,30 24 mth 11 Feb17 17 Sp.Gn.KEMALA - Pg. TAMPAK 36,80 24 mth 04 Sep15 23 Agt17 6 PS. PEDATI - KERKAP 25,00 15 mth 11 Mar15 02 Jun16 19 LAIS - BINTUNAN 11,60 10 mth 11 Mar15 CONSTRUCTION 300+125 days 08 May16 15 SIBOLGA - BATAS TAPSEL 36,00 27 mth 20 Nov15 06 Feb18 7 INDRAPURA - TAPAN 19,50 21 mth 10 Dec15 30 Agt17 8 BTS.Kt PARIAMAN-MANGGOPOH 46,80 24 mth 23 Mar 16 CONSTRUCTION 720 days 10 SIMPANG EMPAT - SP.AIR BALAM 61,70 24 mth 12 KAMBANG - INDRAPURA 55,20 24 mth 14 PAINAN KAMBANG 31,50 21 mth 16 SEBLAT IPUH 34,50 21 mth 20 LUBUK ALUNG SICINCIN 14,60 18 mth 21 LUBUK ALUNG KURAITAJI 16,80 18 mth 9 RANTAU TIJANG-KOTA AGUNG 42,00 The Road has been constructed by MPW within 2011-2013. Road condition is good. Cancelled 18 MUKOMUKO-BTS SUMBAR 25,80 The Road has been constructed by MPW within 2011-2013. Road condition is good. Cancelled Original target : 715,60 km ENVIRONMENT SOCIAL SAFEGUARD Revised target : 640,00 km Prequalification Detail Eng Design LARAP Study Road Safety Owners Estimate Appraisal Public Consultation Procurement Sign Contr Bid Document LARAP Implementation Preparation for Commencement of Work Standard Biding Document PQ ICB ICB ICB ICB ICB 10-Jan-16 CONSTRUCTION 640 + 93 days 19-Apr-16 20-Mar-16 08-Apr-16 CONSTRUCTION 540 days Pack PACKAGE NAME 2012 2013 2014 2015 2016 2017 2018 CONSTRUCTION Review DED RS PQ PROC Review DED RS PQ DED SBD OE + BD DED DED RSA REVISED DED OE BD DED RSA REVISED DED OE BD DED Review DED RS CONSTRUCTION CONSTRUCTION 450 days SBD OE + BD CONSTRUCTION 720 days CONSTRUCTION 720 days PROC PQ RS Proc COW SBD CONSTRUCTION 730 + 105 days CONSTRUCTION 730 + 75 days CONSTRUCTION 730 + 90 days DED RSA REVISED DED OE BD DED RSA REVISED DED OE BD DED OE BD Review DED RS PROC PROC PROC Review DED RS PQ Rev-DED RS PROC CONSTRUCTION 720 days ICB ICB ICB ICB NCB NCB NCB Review DED RS Review DED RS SBD OE + BD CONSTRUCTION 810 days CONSTRUCTION 630 days 22-Jul-15 PROC 12 Mar18 COW CONSTRUCTION Rev-DED RS Rev-DED RS Rev-DED RS ICB ICB ICB NCB NCB NCB NCB COW PROC COW PROC PROC PROC CONSTRUCTION CONSTRUCTION DED CONSTRUCTION Actual Implementation Timeline of WINRIP Western I ndonesia National Roads I mprovement Project 1 - 4

1.2 Disbursement

Loan Allocation and Percent Disbursement To Date REF 1.25 0.00 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00 100.00 Month Co m ple te Actual Expenditure USD 58.01 mil 23.20 WINRIP ACTUAL PROGRESS UP TO APRIL 2016 AND FORECAST UP TO JUNE 2018 ACTUAL April 2016 Original Forecast Forecast Expenditure Rev USD 37.50 mil 15.00 Forecast April 2016 Deviation = + 8.20 The total disbursement summary from the loan by The World Bank to the end of April 2016 was USD 58,007,328.01 equivalent to approximately 23.20 of the loan funds. The following table summarizes the individual disbursements as calculated by CTC but retaining the total disbursement from Client Connection at the end of April 2016. Appendix A shows the Overall Loan Progress Status. Category Description Loan Restructuring Amount US Disbursement This Period Previous Disbursement Totals Disbursed to End April in US Disbursed 1 Part 1 Betterment and Capacity Expansion of National Roads. 220,400,000.00 5,068,579.60 47,354,867.58 52,423,447.18 23.79 2 Part 2 Implementation Support 17,000,000.00 5,583,880.83 5,583,880.83 32.85 3 Part 3 Road Sector Institutional Development 4 Part 4 Contingency for Disaster Risk Response Unallocated 12,600,000.00 Original Loan Amount 250,000,000.00 5,068,579.60 52,938,748.41 58,007,328.01 23.20 Breakdown of amount disbursed during the period April 2016 are the advance payment of newly commenced subproject and for Statement of Work Accomplished for the following civil works contract packages : • Package No. 2 : MC Nos. 26 USD 365,736.04 • Package No. 2 : ESCALATION Period January 2014 April 2015 USD 451,842.24 • Package No. 3 : ESCALATION Period January 2014 April 2015 USD 309,161.60 • Package No.11 : MC Nos. 10 - 13 USD 1,931,660.82 • Package No.12 : Advance Payment USD 1,909,310.82 • Package No.17 : MC Nos. 05 and 06 USD 100,868.08 The Ending balance for Special Account end of April 2016 USD 1,032,854.71 . Western I ndonesia National Roads I mprovement Project 1 - 5

1.3 World Bank Implementation Review Mission and Site Visit

During the month, there was no implementation review mission nor site visit. Also the regular monthly meeting to eview the implementation progress and monitoring of key activities on the Agreed Key Action Plans was not held during the period.

1.4 Procurement of Civil Works Contract Under Category 1 of the Loan Agreement

The current status of Contract Packages which are under final procurement stage are as follows :

1. Package No.10 Sp. Empat Sp. Air Balam AWP-2

This sub-project is under implementation schedule AWP-2. The project roadline is located in the Province of Sumatera Barat having an approximate length of 61.70 kilometers. The Contract Package is procured thru the post qualification and International Competitive Bidding ICB procurement method using the Full e-Procurement System. The revised Bid Evaluation Report BER which was resubmitted to the Bank on February 19, 2016 has been concurred by the World Bank on February 22, 2016 by issuing a No Objection Letter NOL to award the contract to the joint operation of PT. Lancarjaya Mandiri Abadi and PT. Cahaya Tunggal Abadi in the amount of Rp.424,285,260,782.50 with 720 calendar days time completion. However, the announcement and notification of the award winner has been witheld temporarily due to conflict with the Presidential Regulation No.54 of the Year 2010, Article 79, Paragraph 2 and Ministerial Regulation No.31 of Year 2015, Article 6d, Paragraph 1 and 2 in which the post evaluation of bids is not in line with the current regulations.

2. Package No.12 Kambang - Indrapura AWP-2

This sub-project is under implementation schedule AWP-2. The project roadline is located in the Province of Sumatera Barat having an approximate length of 55.20 kilometers. The Contract Package is procured thru the post qualification and International Competitive Bidding ICB procurement method using the Full e-Procurement System. As previously mentioned in earlier reports, Contract Agreement has been executed on January 28, 2016 between the Government of Indonesia GOI and PT. Lancarjaya Mandiri Abadi PT. Cahaya Tunggal Abadi JO for a contract amount of Rp. 358,650,400,000 and 720 calendar days contract time. Copy of the signed contract has been submitted on March 7, 2016 to World Bank for request the issuance of Form 384 for disbursement purpose. A day after the submission, the Bank, on March 8, 2016, issued No Objection Letter NOL and the Form 384. Issuance of Notice To Proceed NTP to commence the works is still to be issued subject to substantial completion of compensating the Project Affected People PAP.

3. Package No.16 Seblat-Ipuh AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road length covers 34.50 kilometers and is located in the Province of Bengkulu. Western I ndonesia National Roads I mprovement Project 1 - 6 The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB method using the Full e-Procurement System. Bid Evaluation Report BER has been completed by POKJA and submitted to World Bank on January 11, 2016 for review and issuance of No Objection Letter NOL. However, per Bank s letter of January 20, 2016 regarding results of their prior review of the BER have comments on the proposed disqualification of five 5 lower priced bidders. In response with the Banks comments, POKJA explained in details the reasons to disqualify the five 5 lower priced bidders. The detailed explainations, justifications and resubmission of the Revised Bid Evaluation Report BER were forwarded to the Bank thru letter of March 21, 2016 by the Director of Road Network Development. The Revised Bid Evaluation Report BER and recommendation for award of the contract remain to be the same bidder as previously proposed in the original Bid Evaluation Report BER.

4. Package No.14 Painan - Kambang AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The Project road length covers 31.50 kilometers and is located in the Province of West Sumatera. The Contract Package is procured thru post qualification criteria and National Competitive Bidding NCB using the Full e-Procurement System. As mentioned earlier, there were four 4 applicant bidders 3 sole entity and 1 joint venture operation who submitted bids for the civil works implementation. Following are the four 4 bidders with their respective bid prices : • PT. Yasa Patria Perkasa Conbloc, JO Rp. 214,602,400,000 • PT. Waskita Karya Rp. 239,449,604,000 • PT. Jaya Konstruksi Rp. 239,628,825,000 • PT. PP Rp. 249,277,000,000 The lowest canvassed bid is submitted by the joint venture operation of PT. Yasa Patria Perkasa and Conbloc with an amount of Rp. 214,602,400,000 which is 19.80 below the approved Owner s Estimate OE of Rp. 267,590,800,000 while the 2 nd lowest bid is quoted by PT. Waskita Karya with an amount of Rp. 239,449,604,000 or 10.58 lower than the Owner s Estimate. During this reporting month, on April 4, 2016, the World Bank issued No Objection Letter NOL on the Bid Evaluation Report BER and recommendation for award of contract to the evaluated lowest responsive bidder, PT. Yasa Patria Perkasa Conbloc, JO, for a corrected contract amount of Rp.214,327,429,680. The Original expiry date of bid validity expired on April 4, 2016, but have been extended for 28 days or until May 2, 2016. However, as the month of April 2016 was about to end with still no execution of the signing of Contract Agreement, the bid validity period has been extended for the 2 nd time for another 50 days or until June 20, 2016.

5. Package No.20 Lubuk Alung - Sicincin AWP-3

The sub-project is to be implemented under implementation schedule AWP-3. The