CATATAN ATAS LAPORAN KEUANGAN INTERIM KONSOLIDASIAN
30 JUNI 2012 Disajikan dalam jutaan Rupiah, kecuali dinyatakan lain
____________________________________________________ PT KRAKATAU STEEL PERSERO Tbk
NOTES TO THE INTERIM CONSOLIDATED FINANCIAL STATEMENTS
JUNE 30, 2012 Expressed in millions of Rupiah, unless otherwise stated
_________________________________________________
Catatan atas laporan keuangan konsolidasi terlampir merupakan bagian yang tidak terpisahkan dari laporan
keuangan konsolidasi secara keseluruhan. The accompanying notes form an integral part of these
consolidated financial statements.
146
34. KONTINJENSI Lanjutan
h. Perusahaan merupakan Tergugat I dalam gugatan Perbuatan Melawan Hukum yang
diajukan oleh
Fathurohman, CS
melalui Pengadilan Negeri Serang yang terdaftar dalam
perkara No.25PDT.G2012PN.Srg tanggal 26 April 2012. Para Penggugat mengajukan
tuntutan ganti rugi materiil kepada Perusahaan sebesar Rp. 200.743.920.000 atas penguasaan
tanah seluas ± 285.960 M
2
yang terletak di DesaKelurahan
Kubangsari dan
DesaKelurahan Tegal
Ratu, Kecamatan
Ciwandan, Kota Cilegon Banten. Sidang Pertama telah berlangsung tanggal 12 Juni
2012, dan saat ini masih dalam proses mediasi. i. Perusahaan merupakan Turut Tergugat dalam
Gugatan Pembatalan Putusan Pengadilan Agama Serang No. 303Pdt.G2010PA.Srg
yang diajukan oleh Yati Rohayati Binti M. Tohiri melalui Pengadilan Agama Serang yang
terdaftar
dalam perkara
No. 314Pdt.G2012PA.Srg tanggal 16 April 2012.
Sidang Pertama telah berlangsung tanggal 22 Mei 2012 dan pada sidang selanjutnya
Penggugat tidak hadir sehingga sidang ditunda sampai dengan tanggal 26 Juni 2012.
j. Perusahaan merupakan tergugat II dalam gugatan perdata yang diajukan oleh Hamdan
bin Kali Adil melalui Pengadilan Agama Cilegon yang
terdaftar dalam
perkara No.331PDT.G2012PA.Clg tanggal 6 Juni
2012. Penggugat meminta kepada Majelis Hakim untuk menjatuhkan putusan kepada
Perusahaan untuk menghentikan pemotongan gaji dan mengembalikan gaji yang telah
dipotong oleh Perusahaan kepada Penggugat. Penggugat tidak hadir pada sidang pertama
tanggal 21 Juni 2012 sehingga ditunda sampai dengan tanggal 2 Juli 2012.
Manajemen dan konsultan hukum Perusahaan berkeyakinan bahwa kasus-kasus tersebut di
atas secara sendiri-sendiri atau bersama-sama tidak akan mempunyai pengaruh yang material
terhadap kondisi keuangan Perusahaan dan hasil operasinya. Manajemen berkeyakinan
untuk melakukan upaya terbaik sehingga Perusahaan dapat menyelesaikan dengan baik
perkara-perkara tersebut.
34. CONTINGENCIES continued
h. The Company is the first defendant to a unlawful lawsuit filed by Fathurohman CS
before the District Court of Serang, which was registered
under the
Case No.
25PDT.G2012PN.Srg dated April 26, 2012. The Plaintiffs claimed for indemnification from
the Company amounting IDR 200.743.920.000 against land occupation of ± 285.960 M
2
located in the village of Kubangsari and Tegalratu, sub district Ciwandan, Cilegon
Banten. The First Trial was held on June 12, 2012 and currently the case is on mediation
process.
i. The Company is the co-defendant to a lawsuit on annulment of religious court verdict No.
303Pdt.G20120PA.Srg issued by Religious Court of Serang filed by Yati Rohayati Binti M.
Tohiri before the Religious Court of Serang which was registered under the Case
No.314Pdt.G2012PA.Srg dated April 16, 2012. The First Trial was held on May 22,
2012. The trial was postponed until June 26, 2012 due to absence of the Plaintiff on the
second trial.
j. The Company is the second defendant to a lawsuit filed by Hamdan bin Kali Adil before
the Religious Court of Cilegon which was registered
under the
Case No.
331PDT.G2012PA.Clg dated June 6, 2012. The Plaintiff filed claim against the Company
to cease the deduction of his salary and to return the salary that has been deducted by
the Company. The Plaintiff is absence at the first trial so the trial is postponed until July 2,
2012.
The Company‟s management and its legal counsel believe that the above mentioned
cases individually or in the aggregate will not have any material adverse effects on the
Company‟s financial condition or results of operations. The management believes that the
Company will do its best effort to resolve the cases in order to achieve the best settlement.
CATATAN ATAS LAPORAN KEUANGAN INTERIM KONSOLIDASIAN
30 JUNI 2012 Disajikan dalam jutaan Rupiah, kecuali dinyatakan lain
____________________________________________________ PT KRAKATAU STEEL PERSERO Tbk
NOTES TO THE INTERIM CONSOLIDATED FINANCIAL STATEMENTS
JUNE 30, 2012 Expressed in millions of Rupiah, unless otherwise stated
_________________________________________________
Catatan atas laporan keuangan konsolidasi terlampir merupakan bagian yang tidak terpisahkan dari laporan
keuangan konsolidasi secara keseluruhan. The accompanying notes form an integral part of these
consolidated financial statements.
147
35. ASET DAN LIABILITAS DALAM MATA UANG ASING
Pada tanggal 30 Juni 2012, aset dan liabilitas moneter dalam mata uang asing adalah sebagai
berikut:
35. ASSETS
AND LIABILITAS
IN FOREIGN
CURRENCIES
as of June 30, 2012, monetary assets and liabilities denominated in foreign currencies are as follows:
Mata uang asing Setara dengan
Foreign currency Equivalent in
Rupiah
ASET ASSETS
Dalam Dollar Amerika Serikat In US Dollar
Kas dan setara kas 128.953.503
1.222.479 Cash and cash equivalents
Investasi jangka pendek Short term investments
Piutang usaha, bersih 2.187.539
20.738 Trade receivabes, net
Piutang lain-lain Forward 2.007.595
19.032 Other receivables forward
Piutang lain-lain Lain-lain 7.612.521
72.167 Other receivables Others
Dalam EURO In EURO
Kas dan setara kas 9.322.503
110.018 Cash and cash equivalents
Jumlah Aset 1.444.433
Total assets
LIABILITAS Dalam Dolar Amerika Serikat
In US Dollar Hutang bank jangka pendek
600.951.697 5.697.022
Short-term bank loans Hutang usaha
3.252.772 30.836
Trade payables Dalam EURO
In EURO Hutang bank jangka pendek
2.272.278 26.816
Short-term bank loans Hutang usaha
404.630 4.775
Trade payables Pinjaman jangka panjang
49.933.088 589.276
Long-term loans Dalam Dolar Singapura
In Singapore Dollar Hutang usaha
152.049 1.127
Trade payables Dalam Yen Jepang
In Japanese Yen Hutang usaha
6.531.342 781
Trade payables Jumlah Liabilitas
6.350.634 Total Liabilities
Liabilitas, bersih 4.906.200
Liabilities, net
2012
Pada tanggal 18 Juli 2012, kurs dalam angka penuh yang dikeluarkan oleh Bank Indonesia
Rp9.463 untuk US1, Rp11.633 untuk EUR1, Rp7.517 untuk SG1 dan Rp120 untuk JP¥1.
Apabila kurs tersebut digunakan pada tanggal 30 Juni 2012, maka liabilitas neto konsolidasian akan
bertambah sebesar Rp19.094. As of July 18, 2012,if the rates of exchange in full
amount published by Bank Indonesia Rp9,463 to US1, Rp11,633 to EUR1, Rp7,517 to SG1 and
Rp120 to JP¥1. If such exchange rates had been used as of June 30, 2012, the net consolidated
liabilities will increase by Rp19,094.