Procurements WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.

Monthly Progress Report October 2014 Western I ndonesia National Roads I mprovement Project 24 Package No. 4 : Ipuh Bantal The current status of this contract package is similar with that of Package No. 1 wherein the negative slippage of -16.35 incurred last month further slipped down to -18.88 as of end of this reporting month. The actual progress of only 5.35 since the project started ten 10 months ago is of much concern than the slippage. Simply looking at the percentage of work accomplished, it seems that the project is not moving forward. As mentioned in the previous Monthly Report in September 2014, Show Cause meeting was held in Bengkulu with main agenda to address all current problems and issues that are hampering the progress of the works. A Test Case of 30 days period was agreed in the meeting to target minimum 8.75 work progress which was executed by the Contractor, However, the Test Case resulted with no success as only 1.62 of progress was attained. As only 60 of the contract time is remaining with 94.65 of the Works still to be completed, a Show Cause Meeting shall be scheduled immediately preferably a high level meeting to be held in DGH Central Office and to be attended by higher level managements of DGH, Contractor and other concerned authorities. Shown in ANNEX P-4 Executive Summary Report are the current problem and actions to be taken to attain substantial progress in order to catch-up with the schedule. For contract packages under AWP-2 and AWP-3 which have a combined total of 17 Packages, a brief summary of the actual activities and status as of this reporting period are presented in Table 1.1, page 7 of this Report.

4.5 Quality Assurance

The DSC will be responsible for quality assurance of materials and workmanship, certifying whether or not contractors have achieved the required results, as well as documentation and reporting based on the financial management plan. They will prepare a Quality Assurance system covering all subprojects, and continuously monitor the effectiveness of their supervision procedures. During the month of October 2014, the CTC s Quality Assurance Engineer conducted site inspection and quality assurance audits on two 2 on-going construction packages. The following were the results and findings during the field visits : Packages 2 : Padang Sawah Simpang Empat a Very minimal accomplished work were attained due to insufficient manpower and no sign of activities on location where there are no obstruction andor cleared areas b Excavated material are stockpiled on the road shoulders and not disposed of properly. c Completed stone masonry retaining walls to restrain embankment material for roadway Monthly Progress Report October 2014 Western I ndonesia National Roads I mprovement Project 25 widening are left open. No sign activity for embankment formation works behind the retaining walls. d Asphalt paving for AC-Base in trial section has been done. Actual paving works can proceed upon issuance of approval letter to use the Asphalt Mixing Plant by the Engineer or PM of BALAI. e Warning signs on locations with work activities were not in placed. f No work activity on the bridge site of Air Gadang Bridge. g Routine maintenance of existing road shoulders and travelledways were not being implemented. Packages 3 : Manggopoh Padang Sawah a Very minimal accomplished works were attained due to insufficient manpower and no sign of activities on location where there are no obstruction andor cleared areas b Excavated material are stockpiled on the road shoulders and not disposed of properly. c Oversize material for Aggregate B and segregations were observed d Asphalt paving for AC-Base in trial section has been done. Actual paving works can proceed upon issuance of approval letter to use the Asphalt Mixing Plant by the Engineer or PM of BALAI. e Warning signs on locations with work activities were not in placed. f Routine maintenance of existing road shoulders and travelledways were not being implemented.

4.6 Environmental and Social Considerations

4.6.1 Current Overall Situation

A project category is assigned to each package as either Category A, B or C depending on the likely degree of influence on environmental issues with a brief explanation as follows: Category A project is one which will have a significant negative impact on the environment and may have an influence on areas outside the actual project area. A project classified as such requires an AMDAL ANDAL, RKLRPL study. Category B project is one which affects the people or the environment to some extent but with a smaller impact than a Category A. The required environmental analysis is a UKLUPL study only. Category C project has minimal effect on the people or environment and an environmental analysis is not required. SPPL are used to handle any minor problem which may arise. All the twenty one 21 packages require environmental impact investigations. There are a total of fourty one 41 studies required, twenty 20 for environmental impact investigations and twenty