Technical Assistance for Capacity Building for Disaster Risks Reduction
4.4 Civil Works Progress
All the 4 Contractors substantially completed their mobilization and construction of Base Camps in all packages have been completed. Other activities done during this month were repair and restoration of deteriorated existing pavements, roadway excavation, embankment formation, spreading of granular pavement for roadway widening, asphalt paving structural works, construction of stone masonry side ditches, stockpiling of raw material, production of crush aggregates and other minor works. Progress status of the four 4 on-going civil work contracts as of this reporting period are shown in Table 4.2. Table 4.2 Program Contract Package Contractor Name of Road Target Progress Schedule Ending October 2014 Actual Progress Accomplished Slippage Time Elapsed AWP-1 1 Jaya Konstruksi Manggala Pratama Tbk Biha - Krui46.36 11.28
- 35.08 46.25 2 Jaya Konstruksi Manggala Pratama Tbk Padang Sawah Sp.Empat incl.Air Gadang Brd33.56 25.61
- 7.95 40.82 3 Jaya Konstruksi Manggala Pratama Tbk Manggopoh Padang Sawah30.10 14.45
- 15.65 40.82 4 PT. Waskita Karya and PT. Mulya Turangga JO Ipuh - Bantal 24.225.35 - 18.88
40.27 At the end of this reporting month of October 2014, all the four 4 contract packages did not achieved any significant accomplishments to catch up with the schedule and were still lagging farther behind schedule. The situation remains the same as in previous month as three 3 of the contract packages continue to follow a downward trend of delayed schedules, while the other one 1 Package No.2 which showed signs of improvement to catch up with the schedule the previous month, is also leading to a downward trend of delayed works. With time elapsed of more than 40 and approaching the halfway mark of the contract time for each of the four 4 contract packages, the Contractors will have hard time to deliver the Works on the target dates of completion, unless a realistic action plans or Catch-up Schedules will be strictly implemented. Package No. 1 : Biha Krui At the end of this month, there was no substantial work accomplished to reduce previous month slippage of -30.39, instead the behind works further slipped to 35.08. The major work items which brought down the slippage to highly alarming situation are the drainage works 20.14 and granular and asphalt pavements 19.47 which accounted for a total of 39.61 cummulative target schedule for the end of this month. In contrast, the Contractor wasParts
» WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» Current Implementation Situation Civil Works
» Disbursement WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» Visit WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» Package 17 Sp. Gunung Kemala
» Package 13 Sp. Rukis Procurement
» Packages 5 Simpang Rampa Procurement
» Package No.19 Lais Procurement
» Package No. 15 Sibolga Procurement
» Technical Assistance for Capacity Building for Disaster Risk Reduction
» Technical Assistance for Capacity Building for Environmental Management
» Technical Assistance for Capacity Building for Road Safety
» Consolidated Update of the Progress of the Project
» Background WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» Project Development WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» Project Objective WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» CTC Consultants WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» DSC Consultants WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» Technical Assistance for Capacity Building for Disaster Risks Reduction
» Detailed Design Preparation WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» Procurements WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» Civil Works Implementation WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» Civil Works Progress WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 11.28 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 25.61 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 14.45 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» - 18.88 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» Quality Assurance WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» Monitoring of Environmental Aspects During Construction
» Design Integration, Road Safety Aspects and Monitoring of Environmental Studies
» Monitoring Report of the LARAP Package No. 1 Monitoring Report of the LARAP Package No. 2
» Monitoring Report of the LARAP Package No. 3 Monitoring Report of the LARAP Package No. 4
» Monitoring Report of the LARAP Package No. 5 Monitoring Report of the LARAP Package No. 6
» Monitoring Report of the LARAP Package No. 7 Monitoring Report of the LARAP Package No. 8
» Monitoring Report of the LARAP Package No. 9 Monitoring Report of the LARAP Package No. 10
» Monitoring Report of the LARAP Package No. 11
» Monitoring Report of the LARAP Package No. 12
» Monitoring Report of the LARAP Package No. 13
» Monitoring Report of the LARAP Package No. 14
» Monitoring Report of the LARAP Package No. 15
» Monitoring Report of the LARAP Package No.16
» Monitoring Report of the LARAP Package No.17
» Monitoring Report of the LARAP Package No.18
» Monitoring Report of the LARAP Package No.19
» Monitoring Report of the LARAP Package No. 20
» Monitoring Report of the LARAP Package No. 21
» Anti Corruption Issues WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» Road Safety Audit WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» Management Information System WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» World Bank and GOI Compliance
» Implementation Support Components WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» TRAINING TO SUPPORT PROJECT IMPLEMENTATION
» Environmental and Social Impact Issues
» Quality Assurance Project Risks and Mitigation Measures
» Current Situation WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» Actions Required WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 2.35 0.22 0.84 - - 0.57 0.09 5.99 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 1.59 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 3.74 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 1.58 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 1.10 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 0.47 - WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 3.47 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 0.88 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 13.85 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» - Late of Field Engineering Decision 1.35 1.10 2.51 - - 0.56
» 0.56 - WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 0.03 - - - WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 0.06 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» -15.65 -18.88 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 2.35 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 0.22 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 0.84 - - WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 0.57 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 0.09 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 5.99 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 1.59 3.74 1.58 1.10 0.47 - 3.47 0.88 13.85 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 1.35 WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
» 2.51 - - WINRIP DOC MPR CTC MPR No.22 2014 10 2014 10 10 00224.
Show more