Monitoring of Environmental Aspects During Construction

Monthly Progress Report September 2014 Western I ndonesia National Roads I mprovement Project 27

3. Monitoring Report of the LARAP Package No. 3

: Manggopoh Padang Sawah Province : Sumatera Barat A. Previous Status : • LARAP documents approved by World Bank on January 4, 2013 • Monitoring Report approved by World Bank on April 18, 2013 • CTC received proof of compensation payments for five 5 of the affected persons out of the remaining fifteen 15 persons and Monitoring Report was submitted to World Bank on February 28, 2014. • CTC received proof of compensation payment for 8 of the affected persons out of the 10 remaining persons and 67 from 68 new PAP and Monitoring Report submitted to World Bank on June 19, 2014. B. Pending Issues, Concerns and Actions a Documents for compensation payments for three 3 remaining identified PAP are being processed by the Local Government. b Monitoring Report concerning compensation payments to the three 3 identified PAP still to be prepared for submission to World Bank. C. Update during this reporting month of September 2014 a On-going construction b Processing of documents for the 3 remaining affected persons are under preparation by the Local Government. c Monitoring Report for the 3 remaining affected persons is under preparation for submission to World Bank..

4. Monitoring Report of the LARAP Package No. 4

: Ipuh Bantal Province : Bengkulu A. Previous Status : • LARAP documents approved by World Bank on December 10, 2012 • CTC received proof of payments for 157 affected persons out of the 227 Project Affected Persons. • Monitoring Report was submitted by PMU to World Bank on December 24, 2013 • World Bank transmitted their comments on the Monitoring Report to PMU on January 6, 2014. • For the remaining 70 affected persons, Local Government settled their compensation payments in January 2014 and February 2014. • Monitoring Report for the compensation of the remaining 70 affected persons was submitted by PMU to the World Bank on February 28, 2014. • World Bank sent letter to PMU on March 5, 2014 informing that the Bank have no further comment on the Monitoring Report. B. Pending Issues, Concern and Actions