Monitoring Report of the LARAP Package No. 4

Monthly Progress Report September 2014 Western I ndonesia National Roads I mprovement Project 29 b Head of Satker in Bengkulu informed PMU thru letter that LARAP implementation regarding land acquisition will be completed by the end of August 2014. C. Update during this reporting month of September 2014 a No update this month.

7. Monitoring Report of the LARAP Package No. 7

: Indrapura - Tapan Province : Sumatera Barat A. Previous Status : • CTC received the Draft Final LARAP documents from Balai IIP2JN on January 2014 • After CTC s review of the documents, comments were transmitted in the form of a MEMO DINAS to Balai II thru the Directorate of Implementation in Region I. • CTC received the correctedrevised LARAP documents from BALAI IIP2JN on June 2014. B. Pending Issues, Concern and Actions a LARAP Implementation Report to be prepared and submitted to PMUCTC for review. C. Update during this reporting month of September 2014 a LARAP documents has been submitted to World Bank for request of issuance for No Objection Letter NOL.

8. Monitoring Report of the LARAP Package No. 8

: Bts. Pariaman - Manggopoh Province : Sumatera Barat A. Previous Status : • CTC received the Draft Final LARAP documents from Balai II Padang on August 1, 2013 • CTC reviewed the documents with comments transmitted to PMU on September 9, 2013 and PMU forwarded to P2JNLocal Consultants the CTC s comments requesting the documents for revision in line with CTC s comments. • Revised LARAP documents from P2JN Consultant resubmitted in June 2014. • CTC received the correctedrevised LARAP documents from BALAI IIP2JN on June 2014. • LARAP documents submitted to World Bank on August 7, 2014. • LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions a Monitoring Report of LARAP implementation still to be prepared for submission and review by the World Bank. C. Update during this reporting month of September 2014 a LARAP is under implementation process by the Local Government. Monthly Progress Report September 2014 Western I ndonesia National Roads I mprovement Project 30

9. Monitoring Report of the LARAP Package No. 9

: Rantau Tijang Kota Agung Province : Lampung A. Previous Status : • LARAP documents are still to be prepared. B. Pending Issues, Concern and Actions a Still no issues and concerns. C. Update during this reporting month of September 2014 a Nothing to report this period.

10. Monitoring Report of the LARAP Package No. 10

: Sp. Empat Sp. Air Balam Province : Sumatera Barat A. Previous Status : • CTC received the Draft Final LARAP documents from Balai II Padang on August 1, 2013 • CTC reviewed the documents with comments transmitted to PMU on September 9, 2013 and PMU forwarded to P2JNLocal Consultants the CTC s comments requesting the documents for revision in line with CTC s comments • Revised LARAP documents from P2JN Consultant resubmitted in June 2014. • CTC received the correctedrevised LARAP documents from BALAI IIP2JN on June 2014. • LARAP documents submitted to World Bank on August 7, 2014. • LARAP documents approved by World Bank on August 12, 2014. B. Pending Issues, Concern and Actions a Monitoring Report of LARAP implementation still to be prepared for submission and review by the World Bank. C. Update during this reporting month of September 2014 a LARAP is under implementation process by the Local Government.

11. Monitoring Report of the LARAP Package No. 11

: Bantal - Mukomuko Province : Bengkulu A. Previous Status : • September 30, 2013, CTC received the LARAP documents from BBPJN III Palembang. • After CTC s review, PMU forwarded the documents to World Bank on November 13, 2013 requesting for No Objection Letter NOL. • Bank conducted their review and their comments were relayed to PMU thru letter on November 20, 2013. • On November 27, 2013, the World Bank sent letter to the Director of Planning to request the Director of Implementation Affairs thru SatkerPPK to revise the LARAP documents by incorporating their comments.