Monthly Progress Report September 2014
Western I ndonesia National Roads I mprovement Project 4
Barring any unforeseen circumstances which will cause interruption during the bidding period, the submission and opening of bids is schedule to take place on October 3, 2014
in Bengkulu.
3. Package 13 Sp. Rukis
Tj. Kemuning AWP-2
Ten 10 interested applicant bidders have submitted their prequalification documents and out of the 10 who submitted the PQ document, 3 applicants were prequalified and
Invitation To Bid were issued to submit tenders for the execution of the Works.
Following are the three 3 qualified applicant bidders who were issued an Invitation To Bid :
1. PT. Waskita Karya Persero, Tbk 2. PT. Hutama Karya Persero
PT. Conbloc Infratecno Joint Operation 3. Halla Corporation Korea Co. in joint venture with PT. Daya Mulia Turangga.
As of this writing, the contract package is still currently under tendering period with pre- bid conferencemeeting held in Bengkulu on September 8, 2014 which was followed by
actual site visit.
During this period of bidding, Halla Corporation, submitted list of questions and queries. CTC assisted the Procurement Committee POKJA in preparing responses to the queries.
Barring any unforeseen circumstances which will cause interruption during the bidding period, the submission and opening of bids is scheduled to take place on October 3,
2014 in Bengkulu.
4. Packages 5 Simpang Rampa
Poriaha AWP-2
There were 14 fourteen contractor applicants 13 single company and 1 one joint venture operation who submitted their prequalification documents. Three 3
contractor applicants failed to prequalify due to failure to satisfy the qualification criteria. Likewise, the 11 Eleven contractors who passed the qualification criteria were
issued an Invitation To Bid to submit their respective tenders for the execution of the Works.
Ten 10 out of the eleven 11 pre-qualified applicant bidders who were issued
Invitation Bid met the deadline for submission of bids at 10:00 am on September 22, 2014 in Medan and opening of bids followed immediately at 10:15 am.
The lone prequalified bidder who failed to submit bid for unknown reason was PT. Nindya Karya Persero.
The lowest canvassed bid was submitted by PT. Nusa Konstruksi Enjiniring, Tbk with an amount of Rp. 107,321,260,000 or 26.40 below the approved Owner s Estimate of
Rp.145,815,316,000. while the highest bid was quoted by PT. Yasa Patria Perkasa in the amount of Rp. 151,361,000,000 or 3,80 above the approved Owner s Estimate.
Following are the ten 10 prequalified applicant bidders who submitted their bids
with their respective bid prices as read-out during bid opening are as follows : 1. PT. Adhi Karya Persero, Tbk Indonesia
: Rp. 113,325,400,000 2. PT. Bangun Cipta Kontraktor Indonesia
: Rp. 127,588,401,500 3. PT. Brantas Abipraya Persero Indonesia
: Rp. 115,098,070,721
Monthly Progress Report September 2014
Western I ndonesia National Roads I mprovement Project 5
4. PT. Hutama Karya Persero PT. Seneca Indonesia JO Indonesia
: Rp. 139,890,000,000 5. PT. Multi Structure Indonesia
: Rp. 123,067,753,000 6. PT. Nusa Konstruksi Enjiniring, Tbk Indonesia
: Rp. 107,321,260,000 7. PT. Pembangunan Perusahaan Persero Indonesia
: Rp. 108,270,000,000 8. PT. Waskita Karya Persero, Tbk Indonesia
: Rp. 111,625,800,000 9. PT. WIdya Sapta Colas Indonesia
: Rp. 127,716,417,000 10. PT. Yasa Patria Perkasa Indonesia
: Rp. 151,361,000,000 Bid Evaluation Report BER is under preparation and expected to finalized for
submission to DGH on before October 27, 2014.
1.5 Consolidated Update of the Progress of the Project
Other brief updates of the pre-construction activities of this reporting month are shown in Table 1.1.