Western I ndonesia National Roads I mprovement Project 32 • World Bank sent letter to PMU on March 5, 2014 informing that the Bank have no further comment on the Monitoring Report. B. Pending Issues, Concern and Actions a There are an additional 15 PAP still to be compensated. C. Update during this reporting month of November 2014 a On-going construction. b Compensation payments for the 15 PAP are under process.

5. Monitoring Report of the LARAP Package No. 5

: Sp. Rampa Poriaha Province : Sumatera Utara A. Previous Status : • Comments on LARAP documents by World Bank were transmitted to PMU on September 16, 2013 • On September 23, 2013 World Bank wrote letter to Director of Implementation Affairs thru SatkerPPK to revise the LARAP documents in line with their comments. • CTC in consultation with PMU prepared the revised LARAP documents and resubmitted it on November 6, 2013. • World Bank accepted the revised LARAP documents on November 12, 2013. • On November 18, 2013 the Director of Planning issued a letter to the Director of Implementation Affairs Region 1, that the LARAP documents can now be implemented in the acquisition of Right of Ways and removal of construction obstructions. B. Pending Issues, Concern and Actions a PMUCTC is awaiting the LARAP implementation Report from SATKER b Relocation of 1 kiosk still to done. C. Update during this reporting month of November 2014 a No update this month.

6. Monitoring Report of the LARAP Package No. 6

: Pasar Pedati - Kerkap Province : Bengkulu A. Previous Status : • September 30, 2013, CTC received the LARAP documents from BBPJN III Palembang. • After CTC s review, PMU forwarded the documents to World Bank on November 13, 2013 requesting for No Objection Letter NOL. • Bank conducted their review and their comments were relayed to PMU thru letter on November 20, 2013. • On November 27, 2013, the World Bank sent letter to the Director of Planning to request the Director of Implementation Affairs thru SatkerPPK to revise the LARAP documents by incorporating their comments.