Monitoring Report of the LARAP Package No. 13

Western I ndonesia National Roads I mprovement Project 37 • On October 31, 2013, PMU requested the Director of Implementation Affairs thru SatkerPPK to address the World Bank comments • Revised LARAP documents was resubmitted to World Bank on January 30, 2014 • World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Right of Ways and removal of obstruction. • PPKSatker and the Local Government started the preparation stage of land acquisition B. Pending Issues, Concern and Actions a LARAP implementation under preparation stage by SATKERPPK. b Appraisal result still to be finalized prior to negotiation with the land owners and subsequent payments of the PAP. C. Update during this reporting month of November 2014 a Appraisal result for two 2 out of the six 6 sub-districts affected by the road improvement are ready. b Compensation payment documentations are under process.

16. Monitoring Report of the LARAP Package No.16

: Seblat - Ipuh Province : Bengkulu A. Previous Status : • September 30, 2013, CTC received the LARAP documents from BBPJN III Palembang. • After CTC s review, PMU forwarded the documents to World Bank on November 13, 2013 requesting for No Objection Letter NOL. • Bank conducted their review and their comments were relayed to PMU thru letter on November 20, 2013. • On November 27, 2013, the World Bank sent letter to the Director of Planning to request the Director of Implementation Affairs thru SatkerPPK to revise the LARAP documents by incorporating their comments. • PMU resubmitted to the World Bank on January 9, 2014 the revised LARAP documents and was resubmitted again on May 21, 2014 due to some minor corrections. • World Bank issued on May 30,2014 a No Objection Letter NOL on the revised LARAP documents for implementation. B. Pending Issues, Concern and Actions a Monitoring Reports of the LARAP s implementation have to be prepared and submitted for review and for submission to World Bank. b LARAP documents for this Package No.16 covers only land acquisition for the road link. If there are land acquisition for the bridge site, a separate LARAP documents need to be prepared. c Head of Satker in Bengkulu informed PMU thru letter that LARAP implementation regarding land acquisition will be completed by the end of August 2014 C. Update during this reporting month of November2014 a LARAP Implementation is underway. Western I ndonesia National Roads I mprovement Project 38

17. Monitoring Report of the LARAP Package No.17

: Sp. Gunung Kemala Pg. Tampak Province : Lampung A. Previous Status : • Comments on LARAP documents by the World Bank was forwarded to PMU on September 16, 2013 • World Bank issued letter on September 23, 2013 to the Director of Implementation Affairs Region I thru SatkerPPK to incorporate their comments on the LARAP documents. • CTC revised the LARAP documents taking into consideration all the Bank s comments and PMU resubmitted the documents to the World Bank on November 6, 2013 • World Bank approved the corrected documents on November 12, 2013 • Director of Planning issued letter on November 18, 2013 to the Director of Implementation Affairs to inform that World Bank had already approved the LARAP documents for implementation by the land acquisition committee. B. Pending Issues, Concern and Actions a LARAP implementation report is not yet submitted to PMUCTC. b Hiring of Appraisal committee is on-hold due to no available budget in the year 2014 budget. C. Update during this reporting month of November 2014 a Inventory of affected assets buildings, houses, plant and other obstructions is on- going.

18. Monitoring Report of the LARAP Package No.18

: Mukomuko Bts. Sumbar Province : Bengkulu A. Previous Status : • LARAP documents are still to be prepared B. Pending Issues, Concern and Actions a Still no issues and concerns C. Update during this reporting month of November 2014 a Still no update during this period. b Proposed to be replaced.

19. Monitoring Report of the LARAP Package No.19

: Lais - Bintunan Province : Bengkulu A. Previous Status : • September 30, 2013, CTC received the LARAP documents from BBPJN III Palembang. • After CTC s review, PMU forwarded the documents to World Bank on November 13, 2013 requesting for No Objection Letter NOL. • Bank conducted their review and their comments were relayed to PMU thru letter on November 20, 2013.