Civil Works Implementation WINRIP DOC MPR CTC MPR No.23 2014 11 2014 11 11 00224.
Western I ndonesia National Roads I mprovement Project 24
contract packages continue to follow a downward trend of delayed schedules, while the other one 1 Package No.2 showed signs of improvement to catch up with the schedule.
With time elapsed approaching the halfway mark 50 of the contract time for each of the four 4 contract packages, the Contractors with the exception of Package No.2 will have hard time to
deliver the Works on the target dates of completion, unless a workable and realistic action plans or
Catch-up Schedules will be strictly implemented.
Package No. 1 : Biha Krui
At the end of this month, there was no substantial work accomplished to reduce previous month slippage of
-35.08, instead the behind works further slipped behind to
39.91 as 51 of the
contract time have elapsed. This problem have been going on for the past several month. The major work items which brought down the slippage to highly alarming situation are the
drainage works 34.19
granular pavement 9.22
and asphalt pavements 40.14
which accounted for a total of
83.55 of the contract. In contrast, the Contractor was able to
accomplished only 5.21
total for the three 3 major work items. The overall situation of this contract package is so critical with respect to timely completion taking
into consideration the short remaining contract time to complete the huge amount of remaining works.
As time is running out and with the balance of remaining works which is equivalent to 87.72
that is still to be completed by the Contractor within the remaining
49 of the contract period or 314
calendar days cannot be attained unless the Contractor start a workable Action Plan this coming of December 2014.
Show Cause Meetings were held in the previous months with implementation of Test Cases by the Contractor but the efforts never produce any good results to improve the progress of the Works.
To achieved successful completion of the Project, all issues and major problems which are hampering the progress of the works shall be resolved thru a high level management meeting to be
participated in by high level management of the DGH, Contractor and concerned authorities.
It is suggested that the Contractor shall be required to submit a written commitment to deliver the Project to the Owner on the target date of completion.
Further suggest that the Contractor shall commit or submit the following : a Realistic and workable Action Plan
b Mobilize additional equipment at no additional cost to the Project c Mobilize additional manpower
d Infuse additional financial resources Cash flow e Catch-up schedule showing the remaining works to be programmed within the remaining
contract time. A warning letter was issued by the Supervision Consultant concerning the continuous delays that
if no sign of the improving the progress in the coming month, Clause 8.7 of the Conditions of
Western I ndonesia National Roads I mprovement Project 25
Contract, Delay Damages for Work of 0.10 of the contract price per day equivalent to
Rp.134,909,211 per day will be recommended to the authorities concerned.
A more detailed status of this Package is presented in ANNEX P-I Executive Summary Report. Package No. 2 : Padang Sawah
Sp. Empat Including Air Gadang Bridge
During the month, the progress works slightly improved in terms of slippage delayed works. The previous month slippage of
-7.95 slightly gained a positive improvement to
-7.36 this end of
month. The Construction of Air Gadang Bridge which is yet to be started and frequent breakdown of the
Asphalt Mixing Plant were the two 2 main factors which prevented to achieved substantial progress.
To date, the delayed work is still on the manageable level and not yet of much concern.
ANNEX P-2 Executive Summary Report present a more detailed status of the Contract Package. Package No. 3 : Manggopoh
Padang Sawah
The current slippage which further slipped down from -15.65
the previous month to -17.74
this month is of much concern due to the very limited remaining contract time left.
The main reason for the minimal progress was the delayed works on the asphalt pavement item which accounted for almost
56 of the entire contract as the Asphalt Mixing Plant is frequently out
of order. To date only 3 of entire work item is completed. Due to urgency to maximize the output of paving works to attain a modest progress, the Contractor
shall maintain the AMP regularly. In addition, a high level management meeting shall be scheduled as soon as possible in order to address and resolve all issues that are presently hampering the
progress of the works.
A more detailed status of the project progress are shown in ANNEX P-3 Executive Summary Report .
Package No. 4 : Ipuh Bantal
The current status of this contract package is similar with that of Package No. 1 wherein the negative slippage of
-18.88 incurred last month further slipped down to
-24.66 as of end of this
reporting month. The actual progress of only
8.10 since the project started eleven 11 months ago is of much
concern than the slippage. Simply looking at the percentage of work accomplished, it seems that the project is only on the mobilization period, whereas by this 11
th
month period, at least 32 of the works should have been completed by this time.
As mentioned in previous monthly progress reports, Show Cause Meetings and actual implementation of Test Case for a certain period of time were conducted, but the results never
produced any sign to improve the works progress.