Western I ndonesia National Roads I mprovement Project 4 - 21
has been given No Objection Letter NOL on January 5, 2016. B. Pending Issues, Concern and Actions
• No more issue, LARAP fully completed.
C. Update during this reporting month of March 2017 a On-going construction.
b Total PAP = 637; Compensated = 637; Percent complete = 100. c No update for certification process of PAP lands.
7. Monitoring Report of the LARAP Package No. 7
: Indrapura - Tapan Province
: Sumatera Barat
A. Previous Status : •
LARAP documents approved by World Bank on October 14, 2014. •
Implementation action plan of the LARAP was issued No Objection Letter NOL on March 17, 2015 by the World Bank.
• A report of the compensation payment for 276 from total 861 PAPs already submitted to World
Bank on February 9, 2016 and no objection letter NOL was issued on March 16, 2016. •
Monitoring Report No. 2 for the compensation payments of 207 PAPs submitted to WB on July 21, 2016 and no objection letter NOL was issued on August 18, 2016.
• A monitoring report of the payment progress for 89 PAPs has submitted to WB and no objection
letter NOL was issued on November 12, 2016 •
A monitoring report of the payment progress for 61 PAPs has submitted to WB and no objection letter NOL was issued on January 16, 2017.
B. Pending Issues, Concern and Actions a Compensation payment for 8 from the remaining PAPs is under payment preparation by
PPKSatker PJN II West Sumatera. C. Update during this reporting month of March 2017
a Payment compensation for the remaining 7 APs is under re-negotiation process b Total PAP = 861; Compensated = 853; Percent Complete = 99.1.
8. Monitoring Report of the LARAP Package No. 8
: Bts. Pariaman - Manggopoh Province
: Sumatera Barat
A. Previous Status : •
LARAP documents submitted to World Bank on August 7, 2014. •
LARAP documents approved by World Bank on August 12, 2014. •
Monitoring Report for the payment of 840 PAPs has been submitted to World Bank on January 14, 2016 and No Objection Letter NOL issued on March 8, 2016.
• Monitoring Report for compensation payment of 926 PAPs submitted to WB on May 9, 2016 and
no objection letter NOL was issued on May 12, 2016 •
A monitoring report of the payment progress for 440 PAPs has submitted to WB and no objection letter NOL was issued on January 6, 2017
B. Pending Issues, Concern and Actions
Western I ndonesia National Roads I mprovement Project 4 - 22
a The process of compensation payments to the remaining of the 113 APs C. Update during this reporting month March 2017
a Compensation for the remaining 113 is in the process of filing the payment of Satker PJN I to KPPN DIPA PJN I Sumbar: USD 1.5 Billion
b Total PAP = 2,339 updated; Compensated = 2,206; Percent complete = 94.3.
9. Monitoring Report of the LARAP Package No. 9
: Rantau Tijang Kota Agung
Province : Lampung
Cancelled from the WINRIP Program.
10. Monitoring Report of the LARAP Package No. 10
: Sp. Empat Sp. Air Balam
Province : Sumatera Barat
A. Previous Status : •
LARAP documents submitted to World Bank on August 7, 2014. •
LARAP documents approved by World Bank on August 12, 2014. •
Monitoring Report for payment of 1,421 PAPs has been submitted to World Bank on January 14, 2016 and Bank issued No Objection Letter NOL on March 8, 2016.
B. Pending Issues, Concern and Actions a Payments for the remaining 1,190 PAPs not yet paid by Satker PJN I West Sumatera and
Local Government. C. Update during this reporting month of March 2017
a Monitoring Report for payment of 138 PAPs on-going preparation by Satker PJN I Sumatera Barat.
b PPKSatker PJN I West Sumatera and Local Government continue the appraisal and payment processing of the remaining PAP.
c Total PAP = 2,915; Compensated = 1,725; Percent complete = 59.18. Cancelled from the WINRIP Program
11. Monitoring Report of the LARAP Package No. 11
: Bantal - Mukomuko Province
: Bengkulu
A. Previous Status : •
World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation.
• Monitoring Report No.1 and No.2 were issued No Objection Letters NOL from the World Bank.
• Monitoring Report for 15 of the remaining 123 PAPs was given No Objection Letter NOL on
November 26, 2015 •
A monitoring report of the payment progress for the remaining 89 PAPs already submitted to WB and no objection letter NOL was issued on October 28, 2016
B. Pending Issues, Concern and Actions a No more issue.
C. Update during this reporting month of March 2017