Civil Works Progress WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
Western I ndonesia National Roads I mprovement Project 4 - 5
Package No. 5 : Sp. Rampa Poriaha
The progress, 2.22 of this month is still much lagging for the scheduled 13.15 having negative slippage -28.32 accumulatively.
The main work items leading the delayed progress are earth works, pavement works, structures. The work forces for rock excavation are to be increasesd and early start of Ap pavement works on the
stretches which were completed for aggregate class A is so necessary in order to catch-up the delayed progress.
ANNEX P-5 Executive Summary Report shows the Contractor s Progress Schedule. Package No. 6 : Kerkap
Ps. Pedati
The contract package is completed on January 28, 2017 and provisionally handed over to the Employer and currently under Defects Notification Period until after two 2 years reckoned from the issuance of TOC.
ANNEX P-6 Executive Summary Report shows the complete details of the contract package. Package No. 7: Indrapura
Tapan
The scheduled progress as of this month 55.68 was made in accordance with the 2
nd
revised schedule. Most of delayed progress as of this month -7.63 have been made from drainage works and Asphalt
Pavement works.
In case of Drainage work, the main reasons of delay were unallocated utilities espicially electrical poles, water pipes ete and the delayed reason of Asphalt pavement works were due to low products of
aggregates because of the limitted operation time 08 AM to 5 PM of stone crusher strongly required by local peoples.
ANNEX P-7 Executive Summary Report shows the complete details of the contract package. Package No. 8 : Bts. Kota Pariaman - Manggopoh
Ahead progress as of this month had been made of 5.39 comparing the scheduled 51.83 and the actual 57.22.
Owing to ample working areas for Asphalt pavement, for comming several months, the work progress of this package is to be maintained ahead.
ANNEX P-8 Executive Summary Report shows the complete details of the contract package. Package No. 11 : Bantal - Mukomuko
Ahead progress as of this month had been made of 0.53 comparing the scheduled 95.86 and the actual 96.37.
The completion date is May 26, 2017. However the most of main works are almost completed, asphalt pavement works remain only for AC-WC, 4 km from 50.7 km in total lenght.
The remain works are only minor works like lane marking, traffic signages, so on.
For more detailed of the Contract Package, refer to ANNEX P-11 Executove Summary Report .
Western I ndonesia National Roads I mprovement Project 4 - 6
Package No. 12 : Kambang - Indrapura
The progress of this month is only 0.94 likely, the last month 0.96 against the scheduled 13.31. After failure of the 1
st
test case, the client gave the 2
nd
test case March, 14 27, 2017 to the contractor
but, the results were so poor as well due to the poor management and no financial supports of the contractor.
The client is to give the final test case to the contractor soon and consider the next phase of determination in accordance with the results of the final Test Case.
Details of the Contract Package are shown in ANNEX P-12 Executive Summary Report . Package No. 13 : Sp. Rukis
Tj. Kemuning
This month progress is achieved of 1.63 against the scheduled 8.80. The reasons of delayed progress are almost same as those of the last month accordingly the client have
given the test case to the contractor. The new GS of contractor had been in duty. It is expected to settle the delayed payments to the subcontractors which was of the main reasons of delay.
The contractor is still preparing for the extension of time due to the unsettled land acquisition sta. 25 km 43 km.
Details of the work progress are shown in ANNEX P-13 Executive Summary Reports. Package No. 14: Painan - Kambang
The progress of this month is achieved of 6.37 against the scheduled 5.24. Working activities of this month have been done in extentive areas and with Earthworks, pavement works,
structures. Considering the target date of completion as of December, 2017, this package is so necessary to secure the working areas for asphalt pavement work continueosly and the unsettled land acquisition 12.9
km has to be cleared soon.
ANNEX P-14 Executive Summary Report shows the complete details of the project. Package No. 15: Sibolga Bts. Tapsel
The progress of this month is only achieved of 1.58 against the scheduled 6.50. In order to catch-up the delayed progress, the most crucial problems are the unsettled land acquisition
Apprx. 16.5 km and relocation of existing utilities electrical poles, water pipes.
Without resolutions of the above, it is so difficult to secure the working areas for pavement works which are the major works about 65 of the total contract amount.
Detailed and work progresses of the contract package are shown in ANNEX P-15 Executive Summary Report .
Package No. 16 : Seblat Ipuh
In accordance with the revised schedule, this month progress is achieved of 1.13 against the scheduled 1.08.
The major works at the early stage of the project have been done, in normal, with Drainage, Earthworks, Granular Pavement Works.