Civil Works Implementation WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480

Western I ndonesia National Roads I mprovement Project 4 - 3

4.4 Civil Works Progress

Activities done during this month on the on-going construction packages were repair and restoration of deteriorated existing pavements, roadway excavation, embankment formation, spreading of granular pavement for roadway widening, asphalt paving, structural works, construction of stone masonry side ditches, stockpiling of raw material, production of crush aggregates, other minor works, bridge construction, finalization of Field Engineering surveys and mobilization of resources of the newly started contract package. The four 4 contract packages under implementation program AWP-1 were already completed and now under defects liability period for two 2 years since the issuance of TOCs. Under the implementation program AWP-2 and AWP-3, there are currently twelve 12 contract packages that are on-going construction implementation. Physical progress of six 6 of the packages are lagging far behind schedule with negative slippages from -34.62 to -12.21 while progress for the other four 4 packages are still slightly on or behind schedule, two 2 packages are on ahead schedule. Progress status of the on-going civil works contracts as of this reporting period are shown in Table 4.2. Following are brief status of the on-going construction contract packages: Package No. 1 : Biha Krui The contract package is completed on January 20, 2016 and provisionally handed over to the Employeer and currently under Defects Notification Period until after two 2 years reckoned from the issuance of the TOC. A more detailed previous status during the whole duration of the contract implementation of this Package is presented in ANNEX P-I Executive Summary Report. Package No. 2 : Padang Sawah Sp. Empat Including Air Gadang Bridge The contract package is completed on April 14, 2016 and provisionally handed over to the Employeer and currently under Defects Notification Period until after two 2 years reckoned from the issuance of the TOC. ANNEX P-2 Executive Summary Report present a more detailed status during the whole duration of the contract implementation of the Contract Package. Package No. 3 : Manggopoh Padang Sawah The contract package is completed on March 17, 2016 and provisionally handed over to the Employeer on March 17, 2016 and currently under Defects Notification Period until after two 2 years reckoned from the issuance of the TOC. A more detailed status of the project progress during the whole duration of the contract implementation are shown in ANNEX P-3 Executive Summary Report . Package No. 4 : Ipuh Bantal The contract package is completed on May 31, 2016 and provisionally handed over to the Employeer on May 31, 2016 and currently under Defects Notification Period until after two 2 years reckoned from the issuance of the TOC. ANNEX P-4 Executive Summary Report shows the details and status of the project. Western I ndonesia National Roads I mprovement Project 4 - 4 Table 4.2 Program Contract Package Contractor Name of Road Target Progress Schedule Ending March 2017 Actual Progress Accomplished Slippage Time Elapsed Remaining Time Remarks AWP-1 1 PT. Jaya Konstruksi Manggala Pratama Tbk Biha - Krui - - - - Completed PHO : Jan 20, 2016 2 PT. Jaya Konstruksi Manggala Pratama Tbk Padang Sawah Sp.Empat incl.Air Gadang - -- - - Completed PHO : April 14, 2016 3 PT. Jaya Konstruksi Manggala Pratama Tbk Manggopoh Padang Sawah - - - - Completed PHO : Mar 17, 2016 4 PT. Waskita Karya and PT. Mulya Turangga JO Ipuh - Bantal - - - - Completed PHO : May 31, 2016 AWP-2 5 PT. Nusa Konstruksi Enjiniring Sp. Rampa - Poriaha

76.53 48.20

-28.32 84.67 117 CD Based on revised contract time and schedule 6 PT. Waskita Karya Tbk Ps. Pedati Kerkap - - - - Completed PHO : Jan 28, 2017 7 PT. Adhi Karya Indrapura - Tapan 55.68

48.05 -7.63

74.88 158 CD

Based on revised contract time and schedule 8 PT. PPPT. Statika Mitra J.O Bts. Kota Pariaman Manggopoh

51.83 57.22

5.39 56.64

281 CD Based on revised contract time and schedule 11 PT. Hutama Karya PT. DMT Mukomuko - Bantal 95.85

96.37 0.52

92.47 62CD

Based on revised contract time and schedule 12 PT. LancarjayaPT. Cahaya T.A. JO Kambang Indrapura 40.55

5.93 -34.62

52.13 281 CD

Based on revised contract time and schedule 13 PT. Waskita Karya Persero Tbk Sp. Rukis Tj. Kemuning 72.34

44.34 -28.01

85.12 107 CD

Based on original contract time and revised schedule AWP-3 14 PT. Yasa PT. Conbloc JO Painan Kambang

20.60 15.63

-4.96 45.44 281 CD Based on revised contract time and schedule 15 PT. Pembangunan Perumahan Persero Sibolga Bts. Tapsel 63.52

29.44 -34.08

63.60 281 CD

Based on revised contract time and schedule 16 PT Yasa-Multi Structure, Jo Seblat Ipuh 2.10

2.17 0.07

21.78 492 CD

17 PT. Jaya Konstruksi Manggala Pratama Tbk Sp. Gn Kemala Pg. Tampak

62.09 61.37

-0.72 75.03 189 CD Based on revised contract time and schedule 19 PT. Rodatekindo Purajaya Lais - Bintunan - - - - Completed PHO : June 30, 2016 20 PT. Nindya Karya Lubuk Alung Sicincin

42.24 33.37

-12.21 42.18 281 CD Based on revised contract time 21 PT. Multi Structure Lubuk Alung Kuraitaji

35.21 21.25

-13.96 42.18 281 CD Based on revised contract time Under defects liability period for 720 calendar days. Western I ndonesia National Roads I mprovement Project 4 - 5 Package No. 5 : Sp. Rampa Poriaha The progress, 2.22 of this month is still much lagging for the scheduled 13.15 having negative slippage -28.32 accumulatively. The main work items leading the delayed progress are earth works, pavement works, structures. The work forces for rock excavation are to be increasesd and early start of Ap pavement works on the stretches which were completed for aggregate class A is so necessary in order to catch-up the delayed progress. ANNEX P-5 Executive Summary Report shows the Contractor s Progress Schedule. Package No. 6 : Kerkap Ps. Pedati The contract package is completed on January 28, 2017 and provisionally handed over to the Employer and currently under Defects Notification Period until after two 2 years reckoned from the issuance of TOC. ANNEX P-6 Executive Summary Report shows the complete details of the contract package. Package No. 7: Indrapura Tapan The scheduled progress as of this month 55.68 was made in accordance with the 2 nd revised schedule. Most of delayed progress as of this month -7.63 have been made from drainage works and Asphalt Pavement works. In case of Drainage work, the main reasons of delay were unallocated utilities espicially electrical poles, water pipes ete and the delayed reason of Asphalt pavement works were due to low products of aggregates because of the limitted operation time 08 AM to 5 PM of stone crusher strongly required by local peoples. ANNEX P-7 Executive Summary Report shows the complete details of the contract package. Package No. 8 : Bts. Kota Pariaman - Manggopoh Ahead progress as of this month had been made of 5.39 comparing the scheduled 51.83 and the actual 57.22. Owing to ample working areas for Asphalt pavement, for comming several months, the work progress of this package is to be maintained ahead. ANNEX P-8 Executive Summary Report shows the complete details of the contract package. Package No. 11 : Bantal - Mukomuko Ahead progress as of this month had been made of 0.53 comparing the scheduled 95.86 and the actual 96.37. The completion date is May 26, 2017. However the most of main works are almost completed, asphalt pavement works remain only for AC-WC, 4 km from 50.7 km in total lenght. The remain works are only minor works like lane marking, traffic signages, so on. For more detailed of the Contract Package, refer to ANNEX P-11 Executove Summary Report .