Western I ndonesia National Roads I mprovement Project 4 - 3
4.4 Civil Works Progress
Activities done during this month on the on-going construction packages were repair and restoration of deteriorated existing pavements, roadway excavation, embankment formation, spreading of granular
pavement for roadway widening, asphalt paving, structural works, construction of stone masonry side ditches, stockpiling of raw material, production of crush aggregates, other minor works, bridge construction,
finalization of Field Engineering surveys and mobilization of resources of the newly started contract package.
The four 4 contract packages under implementation program AWP-1 were already completed and now under defects liability period for two 2 years since the issuance of TOCs.
Under the implementation program AWP-2 and AWP-3, there are currently twelve 12 contract packages that are on-going construction implementation. Physical progress of six 6 of the packages are lagging far
behind schedule with negative slippages from -34.62 to -12.21 while progress for the other four 4 packages are still slightly on or behind schedule, two 2 packages are on ahead schedule.
Progress status of the on-going civil works contracts as of this reporting period are shown in Table 4.2.
Following are brief status of the on-going construction contract packages:
Package No. 1 : Biha Krui
The contract package is completed on January 20, 2016 and provisionally handed over to the Employeer and currently under Defects Notification Period until after two 2 years reckoned from the issuance of the
TOC.
A more detailed previous status during the whole duration of the contract implementation of this Package is presented in ANNEX P-I Executive Summary Report.
Package No. 2 : Padang Sawah Sp. Empat Including Air Gadang Bridge
The contract package is completed on April 14, 2016 and provisionally handed over to the Employeer and currently under Defects Notification Period until after two 2 years reckoned from the issuance of the
TOC.
ANNEX P-2 Executive Summary Report present a more detailed status during the whole duration of the contract implementation of the Contract Package.
Package No. 3 : Manggopoh Padang Sawah
The contract package is completed on March 17, 2016 and provisionally handed over to the Employeer on March 17, 2016 and currently under Defects Notification Period until after two 2 years reckoned from
the issuance of the TOC.
A more detailed status of the project progress during the whole duration of the contract implementation are shown in ANNEX P-3 Executive Summary Report .
Package No. 4 : Ipuh Bantal
The contract package is completed on May 31, 2016 and provisionally handed over to the Employeer on May 31, 2016 and currently under Defects Notification Period until after two 2 years reckoned from the
issuance of the TOC.
ANNEX P-4 Executive Summary Report shows the details and status of the project.
Western I ndonesia National Roads I mprovement Project 4 - 4
Table 4.2
Program Contract
Package Contractor
Name of Road Target Progress
Schedule Ending March 2017
Actual Progress Accomplished
Slippage Time Elapsed
Remaining Time
Remarks
AWP-1 1
PT. Jaya Konstruksi Manggala Pratama Tbk
Biha - Krui -
- -
-
Completed PHO : Jan 20, 2016
2 PT. Jaya Konstruksi Manggala
Pratama Tbk Padang Sawah
Sp.Empat incl.Air Gadang
- --
- -
Completed PHO : April 14, 2016
3 PT. Jaya Konstruksi Manggala
Pratama Tbk Manggopoh
Padang Sawah
- -
- -
Completed PHO : Mar 17, 2016
4 PT. Waskita Karya and PT.
Mulya Turangga JO Ipuh - Bantal
- -
- -
Completed PHO : May 31, 2016
AWP-2 5
PT. Nusa Konstruksi Enjiniring Sp. Rampa - Poriaha
76.53 48.20
-28.32 84.67
117 CD
Based on revised contract time and schedule
6 PT. Waskita Karya Tbk
Ps. Pedati Kerkap
- -
- -
Completed PHO : Jan 28, 2017
7 PT. Adhi Karya
Indrapura - Tapan 55.68
48.05 -7.63
74.88 158 CD
Based on revised contract time and schedule
8 PT. PPPT. Statika Mitra J.O
Bts. Kota Pariaman Manggopoh
51.83 57.22
5.39 56.64
281 CD
Based on revised contract time and schedule
11 PT. Hutama Karya PT. DMT
Mukomuko - Bantal 95.85
96.37 0.52
92.47 62CD
Based on revised contract time and schedule
12 PT. LancarjayaPT. Cahaya
T.A. JO Kambang
Indrapura 40.55
5.93 -34.62
52.13 281 CD
Based on revised contract time and schedule
13 PT. Waskita Karya Persero
Tbk Sp. Rukis
Tj. Kemuning 72.34
44.34 -28.01
85.12 107 CD
Based on original contract time and revised schedule
AWP-3 14
PT. Yasa PT. Conbloc JO
Painan Kambang
20.60 15.63
-4.96 45.44
281 CD
Based on revised contract time and schedule
15 PT. Pembangunan
Perumahan Persero Sibolga
Bts. Tapsel 63.52
29.44 -34.08
63.60 281 CD
Based on revised contract time and schedule
16 PT Yasa-Multi Structure, Jo
Seblat Ipuh 2.10
2.17 0.07
21.78 492 CD
17 PT. Jaya Konstruksi Manggala
Pratama Tbk Sp. Gn Kemala
Pg. Tampak
62.09 61.37
-0.72 75.03
189 CD
Based on revised contract time and schedule
19 PT. Rodatekindo Purajaya
Lais - Bintunan -
- -
-
Completed PHO : June 30, 2016
20 PT. Nindya Karya
Lubuk Alung Sicincin
42.24 33.37
-12.21 42.18
281 CD Based on revised contract time
21 PT. Multi Structure
Lubuk Alung Kuraitaji
35.21 21.25
-13.96 42.18
281 CD Based on revised contract time
Under defects liability period for 720 calendar days.
Western I ndonesia National Roads I mprovement Project 4 - 5
Package No. 5 : Sp. Rampa Poriaha
The progress, 2.22 of this month is still much lagging for the scheduled 13.15 having negative slippage -28.32 accumulatively.
The main work items leading the delayed progress are earth works, pavement works, structures. The work forces for rock excavation are to be increasesd and early start of Ap pavement works on the
stretches which were completed for aggregate class A is so necessary in order to catch-up the delayed progress.
ANNEX P-5 Executive Summary Report shows the Contractor s Progress Schedule. Package No. 6 : Kerkap
Ps. Pedati
The contract package is completed on January 28, 2017 and provisionally handed over to the Employer and currently under Defects Notification Period until after two 2 years reckoned from the issuance of TOC.
ANNEX P-6 Executive Summary Report shows the complete details of the contract package. Package No. 7: Indrapura
Tapan
The scheduled progress as of this month 55.68 was made in accordance with the 2
nd
revised schedule. Most of delayed progress as of this month -7.63 have been made from drainage works and Asphalt
Pavement works.
In case of Drainage work, the main reasons of delay were unallocated utilities espicially electrical poles, water pipes ete and the delayed reason of Asphalt pavement works were due to low products of
aggregates because of the limitted operation time 08 AM to 5 PM of stone crusher strongly required by local peoples.
ANNEX P-7 Executive Summary Report shows the complete details of the contract package. Package No. 8 : Bts. Kota Pariaman - Manggopoh
Ahead progress as of this month had been made of 5.39 comparing the scheduled 51.83 and the actual 57.22.
Owing to ample working areas for Asphalt pavement, for comming several months, the work progress of this package is to be maintained ahead.
ANNEX P-8 Executive Summary Report shows the complete details of the contract package. Package No. 11 : Bantal - Mukomuko
Ahead progress as of this month had been made of 0.53 comparing the scheduled 95.86 and the actual 96.37.
The completion date is May 26, 2017. However the most of main works are almost completed, asphalt pavement works remain only for AC-WC, 4 km from 50.7 km in total lenght.
The remain works are only minor works like lane marking, traffic signages, so on.
For more detailed of the Contract Package, refer to ANNEX P-11 Executove Summary Report .