Western I ndonesia National Roads I mprovement Project 4 - 22
a The process of compensation payments to the remaining of the 113 APs C. Update during this reporting month March 2017
a Compensation for the remaining 113 is in the process of filing the payment of Satker PJN I to KPPN DIPA PJN I Sumbar: USD 1.5 Billion
b Total PAP = 2,339 updated; Compensated = 2,206; Percent complete = 94.3.
9. Monitoring Report of the LARAP Package No. 9
: Rantau Tijang Kota Agung
Province : Lampung
Cancelled from the WINRIP Program.
10. Monitoring Report of the LARAP Package No. 10
: Sp. Empat Sp. Air Balam
Province : Sumatera Barat
A. Previous Status : •
LARAP documents submitted to World Bank on August 7, 2014. •
LARAP documents approved by World Bank on August 12, 2014. •
Monitoring Report for payment of 1,421 PAPs has been submitted to World Bank on January 14, 2016 and Bank issued No Objection Letter NOL on March 8, 2016.
B. Pending Issues, Concern and Actions a Payments for the remaining 1,190 PAPs not yet paid by Satker PJN I West Sumatera and
Local Government. C. Update during this reporting month of March 2017
a Monitoring Report for payment of 138 PAPs on-going preparation by Satker PJN I Sumatera Barat.
b PPKSatker PJN I West Sumatera and Local Government continue the appraisal and payment processing of the remaining PAP.
c Total PAP = 2,915; Compensated = 1,725; Percent complete = 59.18. Cancelled from the WINRIP Program
11. Monitoring Report of the LARAP Package No. 11
: Bantal - Mukomuko Province
: Bengkulu
A. Previous Status : •
World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation.
• Monitoring Report No.1 and No.2 were issued No Objection Letters NOL from the World Bank.
• Monitoring Report for 15 of the remaining 123 PAPs was given No Objection Letter NOL on
November 26, 2015 •
A monitoring report of the payment progress for the remaining 89 PAPs already submitted to WB and no objection letter NOL was issued on October 28, 2016
B. Pending Issues, Concern and Actions a No more issue.
C. Update during this reporting month of March 2017
Western I ndonesia National Roads I mprovement Project 4 - 23
a Complete. b Total PAP = 243 updated; Compensated = 243; Percent complete =100.
12. Monitoring Report of the LARAP Package No. 12
: Kambang - Indrapura Province
: Sumatera Barat
A. Previous Status : •
LARAP documents approved by World Bank on October 14, 2014. •
Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank. •
Monitoring Report for compensation payment of 216 PAPs submitted to WB on May 26, 2016. •
A Monitoring Report of the compensation payment progress for 60 PAPs has submitted to WB and no objection letter NOL was issued on November 14, 2016
• A Monitoring Report of the compensation payment progress for 88 PAPs has submitted to WB
and no objection letter NOL was issued on Feb 13, 2017 B. Pending Issues, Concern and Actions
a Pending of assessment process is a hindrance to complete compensation payment C. Update during this reporting month of March 2017
a Currently there are 28 Km out of the total length of 56 Km, that land aquisition is not needed.
b Assessment of the affected assets in Sub District of Lengayang being conducted by Appraisal Consultants
c Total PAP = 2,476 updated; Compensated = 1,053; Percent complete = 42.5.
13. Monitoring Report of the LARAP Package No. 13
: Sp. Rukis Tj. Kemuning
Province : Bengkulu
A. Previous Status : •
World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation.
• Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank.
• World Bank issued on August 18, 2015 No Objection Letter NOL on the monitoring Report No.1.
• World Bank issued on October 13, 2015 No Objection Letter NOL on the monitoring Report No.2.
• Monitoring Report No.3 for compensation payments of 193 PAPs in Kab. Kaur submitted to WB
which was submitted on February 23, 2016 has been issued by the Bank the NOL on March 8, 2016.
• Monitoring Report No.4 for compensation payments of 188 PAPs in Kab. Kaur submitted to WB
which was submitted on October 6, 2016 has been issued by the Bank the NOL on October 12, 2016.
• Monitoring Report of the payments progress for 333 PAPs has submitted to WB has been issued
by the Bank the NOL on November 18, 2016. •
Monitoring Report of the payments progress for 1.090 PAPs has submitted to WB has been issued by the Bank the NOL on March 20, 2017.
B. Pending Issues, Concern and Actions