7. Monitoring Report of the LARAP Package No. 7
: Indrapura - Tapan Province : Sumatera Barat A. Previous Status : • LARAP documents approved by World Bank on October 14, 2014. • Implementation action plan of the LARAP was issued No Objection Letter NOL on March 17, 2015 by the World Bank. • A report of the compensation payment for 276 from total 861 PAPs already submitted to World Bank on February 9, 2016 and no objection letter NOL was issued on March 16, 2016. • Monitoring Report No. 2 for the compensation payments of 207 PAPs submitted to WB on July 21, 2016 and no objection letter NOL was issued on August 18, 2016. • A monitoring report of the payment progress for 89 PAPs has submitted to WB and no objection letter NOL was issued on November 12, 2016 • A monitoring report of the payment progress for 61 PAPs has submitted to WB and no objection letter NOL was issued on January 16, 2017. B. Pending Issues, Concern and Actions a Compensation payment for 8 from the remaining PAPs is under payment preparation by PPKSatker PJN II West Sumatera. C. Update during this reporting month of March 2017 a Payment compensation for the remaining 7 APs is under re-negotiation process b Total PAP = 861; Compensated = 853; Percent Complete = 99.1.8. Monitoring Report of the LARAP Package No. 8
: Bts. Pariaman - Manggopoh Province : Sumatera Barat A. Previous Status : • LARAP documents submitted to World Bank on August 7, 2014. • LARAP documents approved by World Bank on August 12, 2014. • Monitoring Report for the payment of 840 PAPs has been submitted to World Bank on January 14, 2016 and No Objection Letter NOL issued on March 8, 2016. • Monitoring Report for compensation payment of 926 PAPs submitted to WB on May 9, 2016 and no objection letter NOL was issued on May 12, 2016 • A monitoring report of the payment progress for 440 PAPs has submitted to WB and no objection letter NOL was issued on January 6, 2017 B. Pending Issues, Concern and ActionsParts
» WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Current Implementation Situation Civil Works
» Disbursement WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» World Bank Implementation Review Mission and Site Visit
» Procurement of Civil Works Contract Under Category 1 of the Loan Agreement
» Background WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Project Development WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Project Objective WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Scope of Services CTC Consultants
» CTC Contract CTC Consultants
» DSC Consultants WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Technical Assistance for Development of Slope Stabilization, Design and
» Detailed Design Preparation WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Procurements WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Civil Works Implementation WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Civil Works Progress WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 48.20 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» -7.63 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 158 CD WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 57.22 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 56.64 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 0.52 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 62CD WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» -34.62 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 281 CD WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» -28.01 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 107 CD WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 15.63 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» -34.08 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 0.07 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 492 CD WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 61.37 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 33.37 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 21.25 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Quality Assurance WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Review Design Integration, Road Safety Aspects and Monitoring of Environmental Studies
» The Contractor Action Plan on Environmental Management and Monitoring RKPPL
» Environmental Quarterly Report Environmental Issues
» Socialization of HIV-AIDs Campaign
» Quarries Management. Environmental Issues
» WB Mission 15 17 February 2017 on Packages No.7,12 14
» Monitoring Report of the LARAP Package No. 1
» Monitoring Report of the LARAP Package No. 2
» Monitoring Report of the LARAP Package No. 3
» Monitoring Report of the LARAP Package No. 4
» Monitoring Report of the LARAP Package No. 5
» Monitoring Report of the LARAP Package No. 6
» Monitoring Report of the LARAP Package No. 7
» Monitoring Report of the LARAP Package No. 8
» Monitoring Report of the LARAP Package No. 9
» Monitoring Report of the LARAP Package No. 10
» Monitoring Report of the LARAP Package No. 11
» Monitoring Report of the LARAP Package No. 12
» Monitoring Report of the LARAP Package No. 13
» Monitoring Report of the LARAP Package No. 14 Monitoring Report of the LARAP Package No. 15
» Monitoring Report of the LARAP Package No.16
» Monitoring Report of the LARAP Package No.17
» Monitoring Report of the LARAP Package No.18
» Monitoring Report of the LARAP Package No.19
» Monitoring Report of the LARAP Package No. 20
» Monitoring Report of the LARAP Package No. 21
» Anti Corruption Action Plan ACAP
» Community Representative Observers CRO
» Publication Disclosure Anti Corruption Issues
» Complaints Handling Mechanism CHS
» Road Safety Audit WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Database Establish the Document Management System DMS to provide:
» World Bank Missions Agreed Key Actions and Mission Plans during Recent World Bank Mission
» Performance Indicators World Bank and GOI Compliance
» Design and Supervision Consultant DSC
» Study on Development of Slope Stabilization Design and Management
» Complaint Handling System CHS
» DMS Statistic Management Information System
» Draw Downs and Future Costs Disbursement Quality Assurance
» Financial Risks Project Risks and Mitigation Measures
» Training to Support Project Implementation