Western I ndonesia National Roads I mprovement Project 7 - 2
PACKAGE CURRENT ISSUES
FOLLOW-UP Actions
investigation. The cost of the design will be applied for the provisional sum.
06 Ps. Pedati - Kerkap WB requested to construct the additional drainage
system in some critical areas in order to enhance life of road.
The contractor confirmed that they are not in position to do the works owing to demobilization of equipments and work forces.
Hence, the additional works is to be done with APBN funds.
08 Bts.Pariaman- Manggopoh
TFAC findings was noticed on February 6, 2017 Remedial works have been done and the reports have been
submitted.
10 Sp. Empat Air Balam
The cancellation of package If the cancellation is to be realised, the proposal for the loan
restructuring and the extension of loan closing date will be prepared.
12 Kambang - Indrapura Packages 12 is seriously lagged behind schedule in this
month due to poor management of the contractor. •
Test Case for 2 weeks Mar. 14 27 had been failed. The 3
rd
test case will be followed soon. •
GS and key personnel of contractor have been replaced
13 Sp Rukis - Tj Kemuning Splitzing program for land acquisition in the provinces of
Lampung is still not budgeted The PIU has requested to remind the PPK to allocate the fund for
splitzing programs for provinces of Lampung Packages 13 is much lagged behind schedule in this
month due to poor management of the contractor. GS of contractor have been replaced
Unsettled Land Acquisition : STA. 25 km to STA.43 km 18 km long
The budget is already allocated in DIPA 2017. LA in STA. 25 km to STA.43 km 18 km long is to be the most critical issue and PPK
urges to settle this LA up to May 2017.
14 Painan Kambang
Unsettled Land Acquisition : 12.9 km Need to expidite LARAP Implementation.
15 Sibolga - Batas Tapsel Splitzing program for land acquisition in the provinces of
Lampung, Bengkulu, and North Sumatra is still not budgeted
The PIU has requested to remind the PPK to allocate the fund for splitzing programs especially for provinces of Lampung, Bengkulu,
and North Sumatra.
The budget of LA in Fiscal year 2017 has been allocated with 5 Billion. Rupiah only for both package no.5 15.
The PIU has requested the PPK to increase the budget up to 11 Billion. Rupiah for both packages no.5 15.
Unsettled Land Acquisition : 16.5 km. Target month of settling LA is July 2017.
Western I ndonesia National Roads I mprovement Project 7 - 3
PACKAGE CURRENT ISSUES
FOLLOW-UP Actions
Design change of rigid pavement Need to approve of DGH WB.
Land acquisition along the 4 km in the village of Pinang Baru - Pinangsori
The contractor is to propose for untilizing the existing ROW Min. 11
m
width 16 Seblat
Ipuh Field engineering is undertaken
Currently, the contractor is doing field engineering to determine the condition of the existing road. Once the field engineering is
completed, the contractor will submit alternative proposals for completion of the project
17 Sp.Gn. Kemala - Pg. Tampak
Splitzing program for land acquisition in the provinces of Lampung, Bengkulu, and North Sumatra is still not
budgeted The PIU has requested to remind the PPK to allocate the fund for
splitzing programs especially for provinces of Lampung, Bengkulu, and North Sumatra.
21 Lubuk Alung Kuraitaji
The progress of Drainage works are so poor The Contractor is increasing the works forces for drainage works
up to 9 teams gradually. Lack of financial support from the Contractor s Head
Office SCM held on March 13, 2017 in Directorate of Road Preservation
and the contractor has confirmed that the operation funds will be fully supported from the company.
Monthly Progress Report March 2017
Western I ndonesia National Roads I mprovement Project 8 - 1
8 CORRESPONDENCES
During the period the CTC received and issued letters. Lists of letters received and issued are shown in Appendix J.
Western I ndonesia National Roads I mprovement Project
ANNEXES Annex P-1 : Package No. 1
Annex P-2 : Package No. 2 Annex P-3 : Package No. 3
Annex P-4 : Package No. 4 Annex P-5 : Package No. 5
Annex P-6 : Package No. 6 Annex P-7 : Package No. 7
Annex P-8 : Package No. 8 Annex P-11: Package No.11
Annex P-12: Package No.12 Annex P-13: Package No.13
Annex P-14: Package No.14 Annex P-15: Package No.15
Annex P-16: Package No.16 Annex P-17: Package No.17
Annex P-19: Package No.19 Annex P-20: Package No.20
Annex P-21: Package No.21
ul-15
Status tanggal : 25-Mar-17
+ ,
- . ,
1
BIHA - KRUI
2 3 4 56 748 9
640 10-Jan-16
154.073 100
100 -
PT Jaya Konstruksi MP, Tbk 8-Jan-14
93 20-Jan-16
154.073 154.073
PADANG SAWAH-SIMPANG EMPAT
6-Dec-13 730
19-Apr-16
226.713 100
100 -
PT Jaya Konstruksi MP, Tbk 6-Jan-14
105 14-Apr-16
226.713 226.713
MANGGOPOH - PADANG SAWAH
6-Dec-13 730
20-Mar-16
165.157 100
100 -
PT Jaya Konstruksi MP, Tbk 6-Jan-14
75 17-Mar-16
165.157 165.157
IPUH - BANTAL 14-Nov-13
730 11-Apr-16
196.438 100
100 -
PT WASKITA KARYA - PT DMT, JO 13-Jan-14
90 31-May-16
196.438 196.438
SIMPANG RAMPA - PORIAHA 17-Mar-15
540 20-Jul-17
107.321 76,53
48,20 28,32
423 117
12,95 8,40
2,54 2,22
PT. NUSA KONSTRUKSI ENJ Tbk. 18-Jun-15
224 82.132
51.734 84,67
15,33 KERKAP - PASAR PEDATI
27-Feb-15 450
28-Jan-17 118.444
100 100
-
PT. WASKITA KARYA Tbk 11-Mar-15
240 28-Jan-17
118.444 118.444
INDRAPURA-TAPAN
26-Nov-15 630
30-Aug-17 129.700
55,68 48,05
7,63 472
158 10,39
7,86 3,43
2,44 PT. ADHI KARYA
10-Dec-15 -
72.219 62.326
74,88 25,12
BATAS KOTA PARIAMAN-MANGGOPOH 28-Jan-16
720 31-Dec-17
355.500 51,83
57,22 5,39
368 281
4,28 9,75
5,20 9,75
PT PP - STATIKA JO 23-Mar-16
-71 184.273
203.431 56,64
43,36 BANTAL - MUKOMUKO
18-Dec-14 720
26-May-17 262.611
95,86 96,37
0,52
658 62
1,81 10,07
4,38 6,60
PT. HUTAMA KARYA - PT. DMT, JO 23-Feb-15
104 251.728
253.081 92,47
7,53 KAMBANG-INDERAPURA
28-Jan-16 720
31-Dec-17 358.650
40,55 5,93
34,62 307
281 10,45
1,89 0,74
0,94 PT LANCARJAYA MA-CAHAYA TA,JO
23-May-16
-132 52,13
47,87 SIMPANG RUKIS-TANJUNG KEMUNING
18-Dec-14 720
10-Jul-17 292.700
72,34 44,34
28,01 613
107 13,92
10,31 2,46
1,63 PT. WASKITA KARYA
22-Jul-15 -
211.752 129.773
85,12 14,88
PAINAN - KAMBANG 1-Jun-16
630 31-Dec-17
214.327
20,60 15,63
4,96 235
281 9,37
6,37 1,88
6,37 KSO YASA - CONBLOC
3-Aug-16 -114
45,44 54,56
SIBOLGA - Batas TAPSEL 13-Jul-15
810 31-Dec-17
260.100 63,52
29,44 34,08
529 281
8,82 7,27
2,10 1,58
PT. PEMBANGUNAN PERUMAHAN 20-Nov-15
-37 773,00
165.215 76.576
63,60 36,40
SEBLAT - IPUH 28-Oct-16
630 30-Jul-18
211.375 2,10
2,17 0,07
138 492
6,11 1,13
0,72 1,13
PT YASA - MULTI STRUCTURE, JO 8-Nov-16
- 21,78
78,22 Sp.Gn KEMALA-PUGUNG TAMPAK
17-Nov-14 720
30-Sep-17 199.551
62,09 61,37
0,72 531
189 6,44
8,08 3,84
8,08
PT Jaya Konstruksi MP, Tbk 4-Sep-15
38 123.901
122.473 REF
75,03 24,97
BINTUNAN-LAIS 27-Feb-15
300 30-Jun-16
44.418 100
100 -
PT RODATEKNINDO PURAJAYA 11-Mar-15
178 30-Jun-16
44.418 44.418
LUBUK ALUNG - SICINCIN 1-Jun-16
540 31-Dec-17
113.818 42,24
33,37 12,21
206 281
7,40 10,23
6,67 10,23
PT NINDYA KARYA 1-Sep-16
-53 42,18
57,82 KURAI TAJI - LUBUK ALUNG
1-Jun-16 540
31-Dec-17 126.301
35,21 21,25
13,96 206
281 8,75
10,13 4,25
5,59 PT MULTI STRUCTURE
1-Sep-16 -53
42,18 57,82
Bengkulu West
Sumatra West
Sumatra Bengkulu
West Sumatra
North Sumatra
Bengkulu Lampung
Bengkulu West
Sumatra West
Sumatra Bengkulu
West Sumatra
Lampung West
Sumatra West
Sumatra Bengkulu
North Sumatra
CONTRACT SIGN DATE
COW
WESTERN INDONESIA ROAD IMPROVEMENT PROJECT WINRIP
Package No. Name PROGRESS ACHIEVEMENT
Time for Completion
TOC PHO
Time for Complation
Actual Dev
Physical Progress Sch
Time extension
contraction
20 21
04
06
19 05
13
15
17 11
07
16 14
01 02
03 Contractor
12 08
3 ESR CTC Mar 2017_E1847F
: ; ;: =:
? AB CDE
FGHI : J
K ? LMN
H G
Aug Sep
Oct Nov
Dec Jan
Feb Mar
Apr May
Jun Jul
Aug Sep
Oct Nov
Dec Jan
Feb Mar
O ;: F
? A
? : F
? P
FJ ;
? K
?
17-Mar-15 540
20-Jul-17
Q RST
Q R UQ
V R Q
W Q
RWX Q
RY Y
TRTS V
R UQ T
R X Y
6,55 1,78
8,40 1,36
1,81 1,28
3,95 0,02
7,48
0,76 2,49
2,22 12,95
PT. NUSA KONSTRUKSI ENJ Tbk. 18-Jun-15
224 No improvement
INDRAPURA-TAPAN 26-Nov-15
630 30-Aug-17
0,31 0,28
0,23 0,36
2,44 1,14
0,88 7,24
3,83 6,79
7,86 7,68
2,24 4,34
2,44 10,39
PT. ADHI KARYA 10-Dec-15
-
No improvement BATAS KOTA PARIAMAN-MANGGOPOH
28-Jan-16 720
31-Dec-17
0,27 0,85
1,25 1,22
2,62 3,48
9,10 9,61
3,75 5,78
9,55 9,75
4,28
PT PP - STATIKA JO 23-Mar-16
-71 BANTAL - MUKOMUKO
18-Dec-14 720
26-May-17
1,28 3,80
2,15 5,99
1,61 2,02
6,20 5,83
5,71 7,22
4,93 2,14
6,15 5,97
3,79 10,07
1,43 1,21
2,28 6,60
1,81
PT. HUTAMA KARYA - PT. DMT, JO 23-Feb-15
104 KAMBANG-INDERAPURA
28-Jan-16 720
31-Dec-17
0,43 0,11
0,07 0,91
0,17 1,89
0,01 0,96
0,94 10,45
PT LANCARJAYA MA-CAHAYA TA,JO 23-May-16
-132 No improvement
SIMPANG RUKIS-TANJUNG KEMUNING
18-Dec-14 720
10-Jul-17
0,36 0,52
1,32 1,20
10,31 0,14
0,53 0,24
1,40 1,32
0,91 0,30
0,51 0,19
1,27 2,24
9,86 8,48
1,60 1,63
13,92
PT. WASKITA KARYA 22-Jul-15
-
No improvement PAINAN - KAMBANG
1-Jun-16 630
31-Dec-17
0,18 0,29
2,18 1,19
0,11 2,02
3,31 6,37
9,37
KSO YASA - CONBLOC 3-Aug-16
-114 The improvement still less than target
SIBOLGA - Batas TAPSEL 13-Jul-15
810 31-Dec-17
0,32 0,46
0,46 0,50
0,27 0,65
2,38 0,87
0,37 2,99
0,04 3,05
1,21 7,27
6,46
0,88 1,58
8,82
PT. PEMBANGUNAN PERUMAHAN 20-Nov-15
-37 No significant improvement
SEBLAT - IPUH 28-Oct-16
630 30-Jul-18
0,18 0,08
0,15 0,63
1,13 6,11
PT YASA - MULTI STRUCTURE, JO 8-Nov-16
-
No significant improvement Sp.Gn KEMALA-PUGUNG TAMPAK
17-Nov-14 720
30-Sep-17
0,92 0,21
0,29 1,63
0,40 0,66
2,05 3,38
4,28 3,18
0,42 2,92
8,00 4,99
5,54 2,48
7,66 4,29
8,08
6,44
PT Jaya Konstruksi MP, Tbk 4-Sep-15
38 LUBUK ALUNG - SICINCIN
1-Jun-16 540
31-Dec-17
0,39 0,24
3,14 9,83
3,35 6,19
10,23
7,40
PT NINDYA KARYA 1-Sep-16
-53 LUBUK ALUNG - KURAI TAJI
1-Jun-16 540
31-Dec-17
0,78 1,16
0,26 1,05
10,13 2,28
5,59
8,75
PT MULTI STRUCTURE 1-Sep-16
-53 The improvement still less than target
05
North Sumatra
Contractor
COW Extension
contraction
14
West Sumatra
07
West Sumatra
08
West Sumatra
11
Bengkulu
CIVIL WORKS PROGRESS per MONTH
WESTERN INDONESIA ROAD IMPROVEMENT PROJECT WINRIP
20
West Sumatra
21
West Sumatra
15
North Sumatra
16
Bengkulu
17
Lampung
12
West Sumatra
13
Bengkulu
Ongoing Construction only
2017 2016
2015 PRO-
VINCE
PROGRESS per MONTH
Package No. Name CONTRACT
SIGN DATE Time for
Completion TOC PHO
C:\Users\Tediero\AppData\Local\Temp\3 ESR CTC Mar 2017_E1847F Per MONTH
MONTH :
Package No. Time Elapsed Days
Name Time Elapsed
Project Manager Scheduled Progress
100,00 Contractor
Actual Overall Progress 100,00
Supervision Consultant Balance
Contract Sign Progress This Month
Commencement Date Time for Complation Days
733 Take Over Date
Z [\[] _\[`
Contract Amount Rp.
a b b]c] d\[e f`
g hi j k k
Contract Amount Add-1 + VAT Rp.
Contract Amount Add-5 + VAT Rp.
Price Adjustment Rp.
Comp Add.2
Accum Actual
Accum Accum
Total Total
Last this
to this Sch to
Month Month
Month this
Month
I G e n e r a l
8,25 7,22
7,54 7,54
7,54 II
D r a i n a g e 34,19
23,78 25,35
25,35 25,35
III Earthworks
3,95 6,56
4,65 4,65
4,65 IV
Pavement Widening Shoulders
1,47 0,94
1,02 1,02
1,02 V
Granular Pavement 9,22
7,04 7,49
7,49 7,49
VI Asphalt Pavement
40,14 46,76
41,07 41,07
41,07 VII
S t r u c t u r e s 1,09
5,36 6,41
6,41 6,41
VIII Reinstatement
Minor Works
1,20 1,91
6,05 6,05
6,05 IX
Day Work 0,14
0,12 0,09
0,09 0,09
X Routine Maintenance
Works
0,36 0,32
0,33 0,33
0,33 TOTAL
100,00 100,00
100,0 -
100,0 100,0
Note : 1. 100 completed on January 2016
2. Taking-Over Certificate issued on January 20, 2016 3. Defects Liability Periode until January 19, 2018
2016 Jan
Feb Mar
Apr May
Jun Jul
Aug Sep
Oct Nov
Dec Jan
Feb Mar
Apr May
Jun Jul
Aug Sep
Oct Nov
Dec Jan
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25
0,22 0,87
1,69 5,62
11,11 18,06
24,50 31,58
38,99 46,36
52,53 60,68
67,46 31,90
35,31 40,53
47,72 56,69
65,59 75,18
84,21 94,42
100,00 88,43
91,76 96,08
100,00 0,10
0,58 0,79
1,59 2,93
3,71 4,79
5,98 8,60
11,28 12,62
16,08 18,71
21,04 25,88
32,67 37,50
42,27 45,05
55,51 65,00
70,08 76,56
91,02 100,00
0,12 0,29
0,90 4,03
8,18 14,35
19,71 25,60
30,39 35,08
39,91 44,60
48,75 14,27
14,65 15,06
19,18 23,31
30,13 28,70
29,43 18,34
15,19 5,06
- 0,48
0,21 0,80
1,34 0,78
1,08 1,19
2,62 2,68
1,34 3,46
2,63 2,33
140.255.020.000
Actual Progress Balance
Div Description
The month of time for complation Rivised Progress Schedul Add.1
Original Progress Schedul Month
Rivised Progress Schedul Add.2
25-Mar-17
PHYSICAL PROGRESS MONITORING TABLE 2014
Year
20-Jan-16
PHYSICAL WORK PROGRESS BY CATEGORY 134.909.211.000
154.073.015.000
2015
PT JAYA KONSTRUKSI MP, Tbk
EXECUTIVE SUMMARY REPORT
Mar- 17
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS MAJOR PROBLEMS
ACTION TO BE TAKEN
01
T IM
E
March 25, 2017
BIHA - KRUI
RENARDET S.A JV
Joko Wisargo, ST, MT
A M
O U
N T
08-Jan-14 25-Nov-13
DISBURSEMENT Incl VAT
140.255.020.000
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25
P H
Y S
IC A
L P
R O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 01
Original 1st Revised Shc
2nd Revised Sch ACTUAL
3 ESR CTC Mar 2017_E1847F P-1
ANNEX P-2
MONTH :
Package No. Time Elapsed Days
Name Time Elapsed
Project Manager Scheduled Progress
100,00 Contractor
PT JAYA KONSTRUKSI MP, Tbk Actual Overall Progress
100,00 Supervision Consultant
Balance Contract Sign
Progress This Month Commencement Date
Time for Complation Days 730
Time for Complation Days 835
Status date Take Over Date
Accumulative Rp.
lmm
Original Contract Amount Rp.
Include advance payment Contract Amount + VO + Price Adj
Rp.
Comp Accum
Actual Accum
Accum Total
Last this
to this Sch to
Month Month
Month this
Month
I G e n e r a l
10,46 3,378
3,38 3,38
3,38 II
D r a i n a g e 3,53
3,244 3,24
3,24 3,24
III Earthworks
4,44 4,691
4,69 4,69
4,69 IV
Pavement Widening Shoulders
2,26 1,948
1,95 1,95
1,95 V
Granular Pavement 10,49
10,944 10,94
10,94 10,94
VI Asphalt Pavement
52,09 57,028
57,03 57,03
57,03 VII
S t r u c t u r e s 14,35
16,115 16,12
16,12 16,12
VIII Reinstatement Minor
Works 1,65
2,002 2,00
2,00 2,00
IX Day Work
0,12 0,108
0,11 0,11
0,11 X
Routine Maintenance Works
0,62 0,541
0,54 0,54
0,54 TOTAL
100,00 100,00
100,00 -
100,00 100,00
Note :
Year Month
Jan Feb
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Dec
Jan Feb
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Dec
Jan Feb
Mar Apr
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 17
18 19
20 21
22 23
24 25
26 27
28 Original Progress Schedul
0,45 0,90
2,20 3,45
7,17 13,58
17,48 20,63
27,88 33,56
38,81 44,72
50,52 56,13
62,58 67,95
73,65 79,35
1st Revised Progress Schedul 66,92
71,10 81,03
87,07 91,35
95,62 100,00
2nd Revised Progress Schedul 92,53
95,62 96,75
97,25 98,21
100,00 Actual
- 0,13
1,02 2,19
4,11 5,96
9,69 13,85
22,55 25,61
31,45 33,73
40,41 44,25
49,98 55,715
58,61 58,35
63,76 71,36
77,80 83,27
92,53 93,20
92,85 95,73
96,83 100,00
Balance 0,45
0,77 1,17
1,26 3,07
7,62 7,80
6,78 5,33
7,95 7,36
10,99 10,11
11,88 12,59
12,23 15,04
8,57 7,35
9,67 9,27
8,08 3,09
2,41 3,90
1,52 1,37
0,89 1,17
1,91 1,86
3,72 4,17
8,69 3,07
5,84 2,28
6,68 3,84
38,29
1. 100 completed April 14, 2016 2. Taking-Over Certificate issued on April 14, 2016
3. Defects Liability Periode until April 13, 2018
197.936.699.000
Amandm 04
March 25, 2017
PADANG SAWAH-SIMPANG EMPAT
02
T IM
E MAJOR PROBLEMS
ACTION TO BE TAKEN ISMAN, ST
A M
O U
N T
RENARDET S.A JV 06-Dec-13
06-Jan-14
EXECUTIVE SUMMARY REPORT
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS
Mar- 1 7
The month of time for complation
DISBURSEMENT Incl VAT
25-Mar-17
247.572.130.000
PHYSICAL WORK PROGRESS BY CATEGORY Div
Description
PHYSICAL PROGRESS MONITORING TABLE
2014 2015
2016
247.572.130.000
14-Apr-16
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25 26
27 28
P H
Y S
IC A
L P
R O
GR E
S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 02
ORIGINAL 1st Revised Sch
2nd Revised Sch ACTUAL
3 ESR CTC Mar 2017_E1847F P-2
no opqrs t
MONTH :
Package No. Time Elapsed Days
Name Time Elapsed
Project Manager Scheduled Progress
100,00
There is outstanding payment of 2.4 billion rupiahs and contract Proposal of contract amendment under process
Contractor Actual Overall Progress
100,00
amount not yet amended
Supervision Consultant Balance
Contract Sign Progress This Month
Commencement Date Time for Complation Days
730 Time for Complation Days
805
u v w v
xy z
w v
{
Take Over Date
| } }
x ~
x
w v
{
6
Original Contract Amount Rp.
Include advance payment Contract Amount + VO + Price Adj
Rp.
Comp Revised
Accum Actual
Accum Accum
Total Total
Last this
to this Sch to
Month Month
Month this
Month
I G e n e r a l
10,21 10,21
2,39 2,39
2,39 II
D r a i n a g e 13,17
13,17 10,09
10,09 10,09
III Earthworks
3,04 3,04
6,99 6,99
6,99 IV
Pavement Widening Shoulders
2,45 2,45
1,92 1,92
1,92 V
Granular Pavement 11,27
11,27 11,25
11,25 11,25
VI Asphalt Pavement
55,81 55,81
59,72 59,72
59,72 VII
S t r u c t u r e s 0,80
0,80 5,28
5,28 5,28
VIII Reinstatement Minor
Works
2,27 2,27
1,02 1,02
1,02 IX
Day Work 0,22
0,22 0,69
0,69 0,69
X Routine Maintenance
Works
0,76 0,76
0,65 0,65
0,65 TOTAL
100 100
100,0 -
100 100
Note :
Jan Feb
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Dec
Jan Feb
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Dec
Jan Feb
Mar 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 17
18 19
20 21
22 23
24 25
26 27
0,26 1,00
1,67 2,45
4,78 7,45
10,70 14,27
21,53 30,10
36,95 44,01
51,62 58,67
65,63 73,03
79,97 87,04
70,14 74,54
82,69 89,96
95,17 97,89
100,00 93,78
98,11 99,31
100,00 0,24
0,48 2,07
2,43 2,87
5,45 5,70
7,01 12,43
14,45 19,30
24,38 29,11
30,11 32,97
39,72 43,28
43,98 48,56
54,37 65,63
85,01 91,15
96,30 98,38
99,13 100,00
0,02 0,52
0,40 0,02
1,91 2,00
5,00 7,26
9,10 15,65
17,65 19,63
22,51 28,56
32,66 33,31
36,69 26,16
25,98 28,32
24,33 10,16
6,74 2,52
0,27 0,18
- 0,24
1,59 0,36
0,44 2,58
0,25 1,31
5,42 2,02
4,85 5,08
4,73 1,00
Balance 2016
Rivised Progress Schedul 183.940.872.000
Rivised Progress Schedul Actual Progress
PHYSICAL PROGRESS MONITORING TABLE Year
2014 Month
The month of time for complation 2015
PHYSICAL WORK PROGRESS BY CATEGORY
Original Progress Schedul Div
Description
181.414.693.470
143.688.963.000
1. 100 completed on March 17, 2016 2. Taking-Over Certificate issued on March 17, 2016 3.
Defects Liability Periode until March 16, 2018
DISBURSEMENT Incl VAT
17-Mar-16
25-Mar-17
Opukenigara, ST
A M
O U
N T
RENARDET S.A JV 06-Dec-13
PT JAYA KONSTRUKSI MP, Tbk 06-Jan-14
EXECUTIVE SUMMARY REPORT
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS
Mar- 1 7 03
T IM
E
March 25, 2017
MANGGOPOH - PADANG SAWAH
MAJOR PROBLEMS ACTION TO BE TAKEN
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25 26
27
P H
Y S
IC A
L P
R O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 03
ORIGINAL 1st Revised Sch
2nd Revised Sch ACTUAL
3 ESR CTC Mar 2017_E1847F P-3
ANNEX P-4
MONTH :
Package No. Time Elapsed Days
Name Time Elapsed
Project Manager Scheduled Progress
100,00 Contractor
PT WASKITA KARYA - PT DAYA JO Actual Overall Progress
100,00 Supervision Consultant
Balance Contract Sign
Progress This Month Commencement Date
Time for Complation Days 730
Time for Complation Days 820
Status date Take Over Date
Accumulative Rp.
Contract Amount Rp.
Include advance payment Contract Amount Add-1
Rp. Price Adjustment
Rp. Comp
Accum Actual
Accum Accum
Total Last
this to this
Sch to Month
Month Month
this Month
I G e n e r a l
7,59 5,99
5,99 5,99
II D r a i n a g e
12,26 8,18
8,18 8,18
III Earthworks
3,58 3,06
3,06 3,06
IV Pavement Widening
Shoulders 3,39
3,05 3,05
3,05 V
Granular Pavement 18,07
16,82 16,82
16,82 VI
Asphalt Pavement 49,27
47,02 47,02
47,02 VII
S t r u c t u r e s 2,55
4,82 4,82
4,82 VIII
Reinstatement Minor Works
2,95 10,88
10,88 10,88
IX Day Work
0,14 0,00
0,00 0,00
X Routine Maintenance
Works 0,20
0,18 0,18
0,18 TOTAL
100 100,0
- 100,00
100,00
Note : 1. 100 completed on March 31, 2016
2. Taking-Over Certificate issued on March 31, 2016 3. Defects Liability Periode until March 30, 2018
Year Month
Jan Feb
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Dec
Jan Feb
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Dec
Jan Feb
Mar Apr
The month of time for complation 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 17
18 19
20 21
22 23
24 25
26 27
28
Schedl Progress Original 0,11
0,32 0,75
1,14 6,57
10,29 12,85
15,81 20,08
24,22 32,76
40,88 47,93
55,61 63,45
1st Revised Schedule 28,57
37,28 48,18
56,89 64,18
73,78 84,47
91,89 98,53
2nd Revised Schedule 61,23
62,14 76,26
86,77 96,29
100,0 Actual Progress
- 0,18
0,40 0,53
0,56 0,78
0,87 1,45
3,73 5,35
8,10 9,35
13,79 21,76
27,67 35,43
39,36 42,14
44,24 46,28
50,09 53,17
61,23 70,32
78,69 84,64
91,62 94,53
Balance 0,11
0,14 0,35
0,61 6,01
9,51 11,98
14,36 16,35
18,88 24,66
31,53 34,14
33,85 0,91
1,86 8,81
14,75 19,95
27,51 34,38
38,72 37,30
8,18 2,43
2,13 4,67
5,47 0,22
0,13 0,03
0,22 0,09
0,58 2,27
1,62 2,76
1,25 4,44
7,97 31-Mei-16
25-Mar-17
EXECUTIVE SUMMARY REPORT
Mar- 1 7
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS
04
194.902.179.000
13-Jan-14 14-Nov-13
2015
RENARDET S.A JV MAJOR PROBLEMS
ACTION TO BE TAKEN T
IM E
March 25, 2017
IPUH - BANTAL
Fathoni Ikhsan, ST
A M
O U
N T
2016 2014
PHYSICAL PROGRESS MONITORING TABLE PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
DISBURSEMENT Incl VAT 186.936.750.000
194.902.178.999,00
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25 26
27 28
P H
Y S
IC A
L P
R O
GR E
S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 04
ORIGINAL 1st Revised Sch
2nd Revised Sch ACTUAL
3 ESR CTC Mar 2017_E1847F P-4
MONTH :
Package No. Time Elapsed Days
646 Name
SIMPANG RAMPA - PORIAHA Time Elapsed
84,55 Project Manager
Scheduled Progress 76,53
Contractor PT. NUSA KONSTRUKSI ENJ Tbk.
Actual Overall Progress 48,20
Supervision Consultant Balance
-28,32 Contract Sign
Progress This Month 2,22
Commencement Date Time for Complation Days
764 Take Over Date
Contract Amount Incl VAT Rp.
6
Price Adjustment Rp.
Comp Accum
Actual Accum
Accum Total
Last this
to this Sch to this
Month Month
Month Month
I G e n e r a l
8,09 1,14
0,01 1,15
4,96 II
D r a i n a g e 2,77
1,37 -
1,37 0,95
III Earthworks
21,28 23,55
1,61 25,16
39,30 IV
Pavement Widening Shoulders
1,28 -
- -
- V
Granular Pavement 8,04
3,29 0,58
3,87 4,54
VI Asphalt Pavement
38,75 -
- -
0,90 VII
S t r u c t u r e s 16,22
16,57 0,02
16,58 20,07
VIII Reinstatement Minor
Works 3,48
- -
- 2,06
IX Day Work
0,10 0,08
- 0,08
0,06 X
Routine Maintenance Works
- -
- -
- TOTAL
100,0 45,99
2,22 48,20
72,84
Note :
Year Month
Jun Jul
Aug Sep
Oct Nov
Dec Jan
Feb Mar
Apr May
Jun Jul
Aug Sep
Oct Nov
Dec Jan
Feb Mar
Apr May
Jun Jul
The month of time for complation 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 17
18 19
20 21
22 23
24 25
26
Schedl Progress Original 0,22
0,99 3,89
8,90 16,87
23,69 36,44
40,23 46,08
50,69 56,28
60,45 66,93
69,02 78,66
88,79 96,82
100 1st Revised schedul
41,88 41,99
53,49 63,38
76,53 87,93
97,61 99,43
100 Actual Progress
- 0,57
1,09 1,69
2,72 3,08
3,53 5,77
7,37 10,11
16,66 18,44
26,83 28,19
30,00 31,28
35,23 35,25
42,73 43,50
45,99 48,20
Balance 0,22
0,42 2,80
7,20 14,16
20,61 32,91
34,45 38,70
40,58 39,63
42,02 40,10
40,83 48,66
57,51 61,59
6,63 0,74
9,99 17,39
28,32 Progress per month
- 0,57
0,52 0,60
1,03 0,37
0,44 2,25
1,60 2,74
6,55 1,78
8,40 1,36
1,81 1,28
3,95 0,02
7,5 0,8
2,49 2,22
0,57 0,52
0,60 1,03
0,37 0,44
2,25 1,60
2,74 6,55
1,78 8,40
1,36
Div Description
PHYSICAL WORK PROGRESS BY CATEGORY
25-Mar-17 55.010.640.768
20-Jul-17
Mar- 17
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS
EXECUTIVE SUMMARY REPORT
RENARDET S.A JV
05
T IM
E
March 25, 2017
MAJOR PROBLEMS ACTION TO BE TAKEN
A M
O U
N T
Saleh Samsuri, ST
Contractor is working to fix the stone crusher which often damaged
Coordination with the Ministry of LHK
DISBURSEMENT Incl VAT
18-Jun-15 17-Mar-15
2015 PHYSICAL PROGRESS MONITORING TABLE
107.321.260.310
2016 2017
Delays in AC work, 3.5 km land is ready for paving. Crushed stone aggregate is not adequate yet because
the crushing plant production is not yet effective. Renewal of License Borrow and Use for Forest Area
1.8 km is constrained by the certainty of the environmental research that will be used, whether the
revision UKL-UPL or DELH
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25 26
P H
Y S
IC A
L P
R O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 05
ORIGINAL Sch 1st REVISED Sch
ACTUAL
3 ESR CTC Mar 2017_E1847F P-05
MONTH :
Package No. Time Elapsed Days
Name Time Elapsed
Project Manager Yahya, ST
Scheduled Progress 100,00
Contractor PT. WASKITA KARYA Tbk
Actual Overall Progress 100,00
Supervision Consultant RENARDET S.A JV PT. CIPTA STRADA
Balance Contract Sign
Progress This Month Commencement Date
Time for Complation Days 450
240 Take Over Date
¡
¢£ ¤ ¡
¥
Contract Amount Incl VAT Rp.
¦ § § ¢¨ ¢ © ¡
ª«¥ ¬ ®
84,55
Price Adjustment Rp.
Add Accum
Actual Accum
Accum Last
this to this
Sch to this
Month Month
Month Month
I G e n e r a l
1,69 1,69
1,69 1,69
II D r a i n a g e
1,61 1,61
1,61 1,61
III Earthworks
8,58 8,58
8,58 8,58
IV Pavement Widening
Shoulders 2,93
2,93 2,93
2,93 V
Granular Pavement 16,48
16,48 16,48
16,48 VI
Asphalt Pavement 60,39
60,39 60,39
60,39 VII
S t r u c t u r e s 5,63
5,63 5,63
5,63 VIII
Reinstatement Minor Works
2,15 2,15
2,15 2,15
IX Day Work
- -
- -
X Routine Maintenance
Works 0,54
0,54 0,54
0,54 TOTAL
100 100,0
- 100,00
100,00
Note : 1. 100 completed on January 28, 2017
2. Taking-Over Certificate issued on January 28, 207 3. Defects Liability Periode until January 28, 2019
Year
2017
Month March
Apr May
June July
August Sep
Oct Nop
Dec Jan
Feb March
Apr May
June July
August Sep
Oct Nop
Dec Jan
The month of time for complation 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 17
18 19
20 21
22 23
Schedl Progress Original
0,17 0,59
1,28 3,09
4,38 8,17
14,27 25,82
38,49 49,93
62,08 75,00
85,36 95,41
100,00
1st Revised schedul
56,000 60,47
74,94 100,00
2nd Revised schedul
58,86 70,27
79,80 88,09
96,07 100
Actual Progress
0,07 0,33
0,76 1,04
1,18 2,27
10,03 15,13
18,75 20,54
23,04 25,89
27,55 32,701
36,020 39,34
45,15 56,31
64,44 74,87
87,78 91,23
100,00
Balance
-0,15 -0,26
-0,53 -2,04
-3,20 -5,90
-4,24 -10,69
-19,74 -29,38
-39,04 -49,11
-57,81 -62,71
-63,98 -21,12
-29,79 -2,56
-5,83 -4,93
-0,31 -4,84
0,00 0,42
0,29 0,13
1,10 7,76
5,09 3,62
1,79 2,49
2,85 1,67
5,15 PHYSICAL PROGRESS MONITORING TABLE
2015
118.444.155.000 PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
2016 100.149.616.888
EXECUTIVE SUMMARY REPORT
Mar- 17
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS 6
T IM
E March 25, 2017
KERKAP - PASAR PEDATI MAJOR PROBLEMS
25-Mar-17
28-Jan-17
DISBURSEMENT Incl VAT ACTION TO BE TAKEN
A M
O U
N T
27-Feb-15 11-Mar-15
Calendar Days +
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23
P H
Y S
IC A
L P
R O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 06
Original Sch 1st Revised Sch
2nd Revised Sch Actual
3 ESR CTC Mar 2017_E1847F P-06
¯ °
° ±² ³´ µ¶
MONTH :
Package No. Time Elapsed Days
471 Name
Time Elapsed 74,76
Sub Project Manager PPK Scheduled Progress
55,68 Contractor
PT ADHI KARYA Actual Overall Progress
48,05 Supervision Consultant
Balance -7,63
Contract Sign Progress This Month
4,34 Commencement Date
Time for Complation Days 630
Take Over Date
· ¸¹¸ º» ¼¹
¸ ½
Contract Amount Incl VAT Rp.
¾ ¿ ¿ ºÀºÁ¹¸ ÂÃ
½ ÄÅÆ
ÇÇÈ É
Price Adjustment Rp.
Comp Accum
Actual Accum
Total Last
this to this
Month Month
Month
I G e n e r a l
2,45 1,16
0,00 1,16
1,60 II
D r a i n a g e 21,84
6,03 1,19
7,22 12,67
III Earthworks
5,38 4,50
0,13 4,63
4,59 IV
Pavement Widening Shoulders
1,09 0,03
- 0,03
- V
Granular Pavement 9,22
5,04 0,28
5,31 2,87
VI Asphalt Pavement
51,16 24,24
0,97 25,21
28,46 VII
S t r u c t u r e s 6,08
3,86 0,14
3,72 4,85
VIII Reinstatement Minor
Works 2,48
0,46 0,01
0,47 0,42
IX Day Work
0,09 0,10
0,02 0,12
0,10 X
Routine Maintenance Works
0,20 0,18
0,00 0,19
0,14 TOTAL
100,0 -
45,61 2,44
48,05 55,69
Note :
Year 2015
Month Dec
Jan Feb
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Dec
Jan Feb
Mar Apr
May Jun
Jul Aug
The month for complation 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 17
18 19
20 21
Original Progress Schedul 0,16
0,31 0,59
0,67 1,24
1,92 3,90
5,63 8,72
16,79 24,44
32,37 43,74
50,84 62,90
72,65 80,61
87,11 94,03
98,20 100,0
Revised Progress Schedul Add -1 24,44
32,37 43,74
50,84 62,90
72,65 80,61
87,11 94,03
98,20 100,00
Revised Progress Schedul CCO Add -3 55,68
64,85 72,65
80,56 90,98
100,0
Actual Progress 0,15
0,31 0,59
0,82 1,18
3,62 4,75
5,63 12,87
16,70 23,49
31,35 39,03
41,27 45,61
48,054
Balance 0,01
- 0,00
0,15 0,06
1,70 0,85
0,00 4,15
0,09 0,95
1,02 4,71
9,57 17,29
7,63
Progress per month
0,31 0,28
0,23 0,36
2,44 1,14
0,88 7,24
3,83 6,79
7,86 7,68
2,24 4,34
2,44
0,59 0,23
0,36 2,44
1,14 0,88
7,24 3,83
6,79 7,86
7,68 2,24
37,65
EXECUTIVE SUMMARY REPORT
Mar- 17
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS
30-Agust-17
25-Mar-17
10-Des-15 Filino Kalani, ST
A M
O U
N T
RENARDET S.A JV PT. SEECONS 03-Dec-15
DISBURSEMENT Incl VAT
57.162.036.750
2016
7
T IM
E
INDRAPURA - TAPAN
129.699.900.000
PHYSICAL PROGRESS MONITORING TABLE
PHYSICAL WORK PROGRESS BY CATEGORY Div
Description
Amand ment
04
Accum Sch to this
Month
Lots of disturbance from the local people and they provided limit of operational time for Stone
Crusher from 8:00 to 17:00 The proposed additional work: 4 km existing
road has not been proposed by contractor Contractor has coordinated with the
Sector Police and Head of District, as well as acceleration of operating license for
additional stone crusher Waiting for approval regarding the use
of the remaining budget from cancellation of Pack 10
2017
March 25, 2017
MAJOR PROBLEMS ACTION TO BE TAKEN
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21
P H
Y S
IC A
L P
R O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 07
ORIGINAL Sch 1st REVISED Sch
2nd REVISED Sch ACTUAL
3 ESR CTC Mar 2017_E1847F P-07
ÊË Ë Ì
Í ÎÏÐ
MONTH :
Package No. Time Elapsed Days
367 Name
Time Elapsed 56,55
Sub Project Manager PPK Scheduled Progress
51,83 Contractor
PT. PP - STATIKA CONSORTIUM Actual Overall Progress
57,22 Supervision Consultant
Balance 5,39
Contract Sign Progress This Month
9,75 Commencement Date
Time for Complation Days 649
Take Over Date Status date
Contract Amount Incl VAT Rp.
Accumulative Rp.
47,5
Price Adjustment Rp.
Comp Actual
Accum to
to Total
this this
Month Month
Month
I G e n e r a l
2,13 0,43
0,00 0,44
1,58 II
D r a i n a g e 19,56
2,69 1,72
4,41 10,99
III Earthworks
6,43 3,91
0,19 4,10
3,09 IV
Pavement Widening Shoulders
3,43 0,23
- 0,23
- V
Granular Pavement 14,77
8,03 1,39
9,42 8,99
VI Asphalt Pavement
48,29 29,46
6,45 35,91
24,51 VII
S t r u c t u r e s 2,97
1,98 -
1,98 2,48
VIII Reinstatement Minor
Works 2,16
0,60 -
0,60 0,09
IX Day Work
0,05 -
- -
0,03 X
Routine Maintenance Works
0,20 0,13
0,001 0,13
0,09 TOTAL
100,0 47,48
9,75 57,22
51,83
Note :
Year Month
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Dec
Jan Feb
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Jan Feb
The month for complation 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 17
18 19
20 21
22 23
24 25
Original Progress Schedul 0,02
0,09 0,17
0,31 0,44
2,77 7,58
13,22 22,21
30,85 35,38
48,22 55,71
66,39 74,64
78,72 83,79
90,13 94,80
97,82 99,27
99,96 100,00
Revised Progress Schedul 27,55
35,38 44,13
51,83 59,73
68,69 73,96
79,40 88,40
94,40 97,52
99,37 99,91
100,00 Actual Progress
0,27 1,12
2,37 3,59
6,21 9,69
18,79 28,40
32,15 37,93
47,48 57,22
Balance 0,18
0,96 2,06
3,15 3,44
2,12 5,57
6,19 1,30
2,55 3,35
5,39
Progress per month 0,00
0,27 0,85
1,25 1,22
2,62 3,48
9,10 9,61
3,75 5,78
9,55 9,75
0,94 1,25
1,22 2,62
3,48 9,10
9,61 3,75
5,78 9,55
9,75 57,22
6,21
EXECUTIVE SUMMARY REPORT
Mar- 17
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS
08
T IM
E March 25, 2017
Bts Kota Pariaman - Manggopoh MAJOR PROBLEMS
ACTION TO BE TAKEN
168.989.212.380
RENARDET S.A JV PT. SEECONS 28-Jan-16
23-Mar-16 Opukenigara, ST
A M
O U
N T
DISBURSEMENT Incl VAT
31-Des-17
25-Mar-17
Licenses from the used two 2 Quarries expired on March 17, 2017. It is estimated that they needed the
volume of rock raw material 20,000 tons Contractor is not committed to propose additional
design for 4 Km asphalt pavement Contractor is looking for an alternative quarry
in Koto Alam, Bukit Tinggi. Will be applied Provisional Sum payment item
to finance subgrade research and preparation of asphalt pavement design.
2018 Dec
Div Description
Accum Last
Accum Sch to
this Month
PHYSICAL PROGRESS MONITORING TABLE
2016 2017
PHYSICAL WORK PROGRESS BY CATEGORY
355.500.000.000
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23
P H
Y S
IC A
L P
R O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 08
Original Sch Revised Sch
Actual
ANNEX P-11
MONTH :
Package No. Time Elapsed Days
761 Name
Time Elapsed 92,35
Project Manager Scheduled Progress
95,86 Contractor
PT. HUTAMA KARYA, Tbk JO PT. DMT Actual Overall Progress
96,37 Supervision Consultant
RENARDET S.A JV PT. CIPTA STRADA Balance
0,52 Contract Sign
Progress This Month 6,60
Commencement Date Take Over Date
Time for Complation Days 824
Calendar Days
Ñ ÒÓ ÒÔÕ ÖÓ Ò
×
Contract Amount Incl VAT Rp.
ØÙ Ù ÔÚÔ Û Ó Ò
Ü Ý ×
Þ ßà
áâ ã ä
Contract Amount Add-1 + VAT Rp.
Price Adjustment Rp.
Accum Actual
Accum Accum
Last this
to this Sch to this
Month Month
Month Month
I G e n e r a l
0,85 0,87
- 0,87
0,87 II
D r a i n a g e 2,49
2,82 0,06
2,88 2,88
III Earthworks
11,27 10,56
- 10,56
10,58 IV
Pavement Widening Shoulders
3,60 2,26
0,27 2,53
2,39 V
Granular Pavement 14,41
14,21 -
14,21 14,21
VI Asphalt Pavement
52,35 46,79
4,79 51,58
52,39 VII
S t r u c t u r e s 9,88
10,66 0,26
10,92 10,69
VIII Reinstatement Minor
Works 4,87
1,33 1,21
2,55 1,58
IX Day Work
- -
- -
- X
Routine Maintenance Works
0,28 0,26
0,00 0,26
0,27 TOTAL
100,00 89,78
6,60 96,37
95,86
Note :
Year Month
March Apr
May June
July August
Sep Oct
Nop Dec
Jan Feb
March Apr
May June
July August
Sep Oct
Nop Dec
Jan Feb
Mar Apr
May
The month of time for complation 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 17
18 19
20 21
22 23
24 25
26 27
Schedl Progress Original 0,39
2,18 4,68
7,70 9,91
14,17 18,72
22,96 20,01
22,98 25,39
29,15 36,74
43,85 51,45
58,80 66,39
70,16 77,18
84,00 89,39
93,63 96,19
99,45 100,00
75,54 92,39
95,86 98,98
100 Actual Progress
1,477 5,59
6,59 9,13
10,00 11,28
15,09 17,23
23,22 24,82
26,84 33,04
38,87 44,59
51,81 56,74
58,88 65,03
71,00 74,78
84,85 86,28
87,49 89,78
96,37 Balance
1,08 3,42
1,92 1,43
0,09 2,89
3,64 2,78
0,23 0,56
2,31 3,70
4,98 6,86
6,99 9,65
11,28 12,15
13,01 14,61
8,78 9,91
11,96 2,61
0,52
Progress per month
4,12 1,00
2,54 0,87
1,28 3,80
2,15 5,99
1,61 2,02
6,20 5,83
5,71 7,22
4,93 2,14
6,15 5,97
3,79 10,07
1,43 1,21
2,28 6,60
1,00 2,54
0,87 1,28
3,80 2,15
5,99 1,61
2,02 6,20
5,83 5,71
11 T
IM E
March 25, 2017
BANTAL - MUKOMUKO MAJOR PROBLEMS
ACTION TO BE TAKEN
EXECUTIVE SUMMARY REPORT
Mar- 17
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS
Div Description
225.608.394.983
Amend- 02
Lack of stone dust 1,100 tons The quantity of major works status of March 21,
2017 AP Paving AC-WC: 8.5 Km 5,700 tons
Road Shoulder : 20 Km Road Marking : 25 Km
25-Mar-17
23-Feb-15
DISBURSEMENT Incl VAT 26-May-17
18-Dec-14
A M
O U
N T
Fathoni Ikhsan, ST
Abu stone imported from Padang three 3 main works will be completed by the end
of April 2017 Other minor work such as traffic signs will be
completed before the PHO dated May 26, 2017
2 nd Rivised Progress Schedul
2017
1 st Rivised Progress Schedul
PHYSICAL PROGRESS MONITORING TABLE
2015 2016
228.899.717.000 262.611.303.000
PHYSICAL WORK PROGRESS BY CATEGORY
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25 26
27
PH Y
S IC
A L
PR O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 11
Original Sch 1st Revised Sch
2nd Revised Sch Actual
3 ESR CTC Mar 2017_E1847F P-11
å ææçè
éê ë ì
MONTH :
Package No. Time Elapsed Days
306 Name
Time Elapsed REF
Sub Project Manager PPK Filino Kalani, ST
Scheduled Progress 40,55
Contractor Actual Overall Progress
5,93 Balance
34,62 Supervision Consultant
RENARDET S.A JV PT. Daya Creasi Mitrayasa Progress This Month
0,94 Contract Sign
Commencement Date Take Over Date
í î ï
î ð ñ
òï î
ó
Time for Complation Days 588
Calendar Days
ôõ õ ð
ö ð
÷ ï
î ø
ù ó
ú ûü ý
8,90
Contract Amount Incl VAT Rp.
Price Adjustment Rp.
Add. Accum
Actual Accum
Accum Total
Last this
to this Sch to
Month Month
Month this
Month
I G e n e r a l
3,64 0,66
- 0,66
II D r a i n a g e
3,75 -
- -
III Earthworks
6,23 0,68
0,04 0,72
IV Pavement Widening
Shoulders 2,67
- -
- V
Granular Pavement 18,49
2,76 0,10
2,86 VI
Asphalt Pavement 57,59
- 0,61
0,61 VII
S t r u c t u r e s 5,49
0,65 0,01
0,66 VIII
Reinstatement Minor Works
1,96 0,15
0,17 0,33
IX Day Work
0,05 0,01
- 0,01
X Routine Maintenance
Works 0,13
0,08 -
0,08 TOTAL
100,00 4,99
0,94 5,93
-
Note :
May June
July Augustus
Sept October
Nov Des
January Feb
March April
May June
July Augustus
Sept October
Nov Des
January Feb
March April
May 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 17
18 19
20 21
22 23
24 25
0,09 0,58
0,84 1,26
1,61 4,10
8,31 14,09
21,50 31,99
44,07 56,50
71,44 77,99
77,99 80,17
82,88 85,50
89,12 91,76
94,29 97,31
99,45 99,78
100,00 1,50
2,34 4,93
9,39 15,87
27,24 40,55
54,23 70,99
77,90 80,34
83,37 86,33
90,58 95,17
100,0 1,50
2,34 4,93
9,39 15,87
27,24 40,55
54,23 70,99
77,90 80,34
83,37 86,33
90,58 95,17
100,0 0,192
0,44 0,87
0,98 1,05
1,97 2,13
4,02 4,03
4,99 5,928
0,10 0,14
0,03 0,28
0,56 0,37
2,80 5,37
11,84 22,25
34,62
Progress per month
0,43 0,11
0,07 0,91
0,17 1,89
0,01 0,96
0,94
0,25 0,43
0,11 0,07
0,91 0,17
1,89 0,01
0,96 0,94
5,93 -
-
12 T
IM E
March 25, 2017
Kambang - Indrapura MAJOR PROBLEMS
EXECUTIVE SUMMARY REPORT
Mar- 1 7
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS ACTION TO BE TAKEN
A M
O U
N T
PT. LANCARJAYA MANDIRI ABADI - PT. CAHAYA TUNGGAL ABADI , JO.
28-Jan-16 23-May-16
DISBURSEMENT Incl VAT
31-Dec-17 25-Mar-17
67.769.733.700 358.650.400.000
Poor management in the project operational Lack of financial support from the Central Office of Lead
Contractor GS and key personnel have been replaced
SCM 2 was held on March 13, 2017 in Directorate of Road Preservation to clarify who is
responsible for the management aspects of the joint operation management contractor for the
smoothness of management implementation at the site
Month PHYSICAL WORK PROGRESS BY CATEGORY
Div Description
PHYSICAL PROGRESS MONITORING TABLE Year
2016 2017
2018
The month of time for complation Original Progress Schedul
1st Rivised Progress Schedul
Actual Progress Balance
2nd Rivised Progress Schedul 10
20 30
40 50
60 70
80 90
100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25
P H
Y S
IC A
L P
R O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 12
ORIGINAL 1st REVISED Sch
2nd REVISED Sch ACTUAL
C:\Users\Tediero\AppData\Local\Temp\3 ESR CTC Mar 2017_E1847F P-12
þ ÿ ÿ
MONTH :
Package No. Time Elapsed Days
612 Name
SIMPANG RUKIS-TANJUNG KEMUNING Time Elapsed
85,00 Project Manager
Paides Tabril, ST,MT Scheduled Progress
72,34 Contractor
Actual Overall Progress 44,34
Supervision Consultant Balance
-28,01 Contract Sign
Progress This Month 1,63
Commencement Date Time for Complation Days
720 Take Over Date
Contract Amount Incl VAT Rp.
61
Price Adjustment Rp.
Comp Accum
Actual Accum
Accum Total
Last this
to this Sch to this
Month Month
Month Month
I G e n e r a l
0,38 0,39
0,02 0,41
0,30 II
D r a i n a g e 1,87
0,54 0,19
0,73 1,73
III Earthworks
16,52 4,87
0,01 4,88
9,08 IV
Pavement Widening Shoulders
4,11 -
0,15 0,15
2,52 V
Granular Pavement 8,43
6,62 0,70
7,31 16,01
VI Asphalt Pavement
64,33 28,50
0,54 29,04
39,69 VII
S t r u c t u r e s 2,05
1,11 0,03
1,13 1,98
VIII Reinstatement Minor
Works 2,14
0,70 -
0,70 0,90
IX Day Work
- -
- -
X Routine Maintenance
Works 0,18
- -
- 0,13
TOTAL 100,0
42,71 1,63
44,34 72,35
Note :
Year Month
Jul Aug
Sep Oct
Nov Dec
Jan Feb
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Dec
Jan Feb
Mar Apr
May Jun
Jul
The month of time for complation 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 17
18 19
20 21
22 23
24 25
Schedl Progress Original 0,02
0,21 1,65
4,18 6,69
9,61 14,62
20,36 26,94
33,58 41,24
47,87 50,63
58,32 63,60
68,28 72,97
77,66 82,62
86,79 91,19
95,75 99,36
99,74 100,00
1st Revised Schedule 0,20
0,90 2,20
4,00 5,80
7,50 9,50
11,50 13,30
15,40 16,13
20,18 24,00
27,82 32,00
36,44 41,47
46,63 54,87
63,48 72,34
81,13 90,08
97,87 100,00
Actual Progress -
0,36 0,88
2,19 3,39
13,71 13,84
14,37 14,62
16,02 17,34
18,25 18,55
19,06 19,25
20,53 22,77
32,63 41,11
42,71 44,34
Balance 0,02
0,14 0,77
1,98 3,30
4,10 0,78
5,99 12,32
17,56 23,90
29,63 32,08
39,26 44,34
47,75 50,20
45,03 41,51
20,77 28,01
Progress per month -
0,36 0,52
1,32 1,20
10,3 0,14
0,53 0,24
1,40 1,32
0,91 0,30
0,51 0,19
1,27 2,24
9,86 8,48
1,60 1,63
0,36 0,52
1,32 1,20
10,31 0,14
0,53 0,24
1,40 1,32
0,91 0,30
0,51
13
T IM
E
March 25, 2017
MAJOR PROBLEMS ACTION TO BE TAKEN
EXECUTIVE SUMMARY REPORT
Mar- 1 7
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS
A M
O U
N T
RENARDET S.A JV 18-Dec-14
22-Jul-15
Div Description
DISBURSEMENT Incl VAT
10-Jul-17
25-Mar-17
292.700.000.000
130.575.892.093
Land acquisition for Sta 25 Km to 43 Km is not completed yet segment 2. Contractor s settled
land in segment-1 of 25 km is almost depleted. Poor management at the operational contractor
no GS for about 1.5 months Amendment to the extension of time has not
been proposed The budget is already allocated in DIPA 2017, PPK attempt
to complete land acquisition on April 2017 The new GS has already started since March 8, 2017
Will be submitted by the contractor on April 2017
PHYSICAL PROGRESS MONITORING TABLE 2015
2016 2017
PHYSICAL WORK PROGRESS BY CATEGORY
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25
P H
Y S
IC A
L P
R O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 13
ORIGINAL Sch 1st REVISED Sch
ACTUAL
3 ESR CTC Mar 2017_E1847F P-13
MONTH :
Package No. Time Elapsed Days
234 Name
Time Elapsed 46,99
Sub Project Manager PPK Rahmat Donal, ST, MT
Scheduled Progress 20,60
Contractor PT YASA - CONBLOC, JV
Actual Overall Progress 15,63
Supervision Consultant RENARDET S.A JV
Balance 4,96
Contract Sign Progress This Month
6,37 Commencement Date
Time for Complation Days 498
Calendar Days Take Over Date
+ ,
Contract Amount Incl VAT Rp.
- . . 0 12
, 345
6
8,85
Price Adjustment Rp.
Comp Accum
Actual Accum
Accum Total
Last this
to this Sch to
Month Month
Month this
Month
I G e n e r a l
0,38 0,67
0,02 0,69
0,88 II
D r a i n a g e 1,87
0,65 0,24
0,90 0,86
III Earthworks
16,52 2,53
0,70 3,23
3,54 IV
Pavement Widening Shoulders
4,11 -
- -
- V
Granular Pavement 8,43
2,15 1,89
4,05 5,37
VI Asphalt Pavement
64,33 2,30
3,13 5,44
8,24 VII
S t r u c t u r e s 2,05
0,47 0,36
0,83 1,19
VIII Reinstatement
Minor Works 2,14
0,34 0,00
0,34 0,35
IX Day Work
- 0,01
0,00 0,01
0,00 X
Routine Maintenance Works
0,18 0,15
0,02 0,17
0,17 TOTAL
100,00 9,27
6,37 15,63
20,60
Note :
Augustus Sept
October Nov
Des January
Feb March
April May
June July
Augustus Sept
October Nov
Des January
Feb March
April 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 17
18 19
20 21
0,17 0,34
0,51 0,94
2,02 4,47
7,12 10,30
14,85 21,63
29,98 38,68
47,74 54,09
63,68 71,43
79,18 86,11
92,51 97,49
100,0 0,17
0,56 0,72
1,78 5,87
10,05 15,36
20,60 28,07
35,22 40,30
47,16 56,10
73,62 87,09
96,50 100,0
0,18 0,47
2,65 3,83
3,94 5,96
9,27 15,63
0,00 0,09
1,92 2,05
1,92 4,09
6,09 4,96
Progress per month 0,18
0,29 2,18
1,19 0,11
2,02 3,31
6,37 0,29
2,18 1,19
0,11 2,02
3,31 6,37
15,63 -
- -
- -
14 T
IM E
March 25, 2017
Painan - Kambang MAJOR PROBLEMS
1-Jun-16 3-Aug-16
13-Dec-17
214.322.429.680
EXECUTIVE SUMMARY REPORT
Mar- 17
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS ACTION TO BE TAKEN
A M
O U
N T
DISBURSEMENT Incl VAT
25-Mar-17 83.256.896.458
Unsettled land acquisition: 12.9 Km Production of stone crusher is smaller than the
capacity of AMP Acceleration of LARAP implementation, the
budget is already available in DIPA 2017 Additional of 1 Crushing Plant with capacity of
150 tons per day is being set up
Actual Progress Balance
2018
2017 2016
Year Month
Revise Progress Schedul The month of time for complation
Original Progress Schedul PHYSICAL PROGRESS MONITORING TABLE
PHYSICAL WORK PROGRESS BY CATEGORY Div
Description
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21
P H
Y S
IC A
L P
R O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 14
ORIGINAL Sch 1st REVISED Sch
ACTUAL
C:\Users\Tediero\AppData\Local\Temp\3 ESR CTC Mar 2017_E1847F P-14
7 8
8 9 : ;
=
MONTH :
Package No. Time Elapsed Days
491 Name
Time Elapsed 63,5
Project Manager Scheduled Progress
63,52 Contractor
PT. PEMBANGUNAN PERUMAHAN Actual Overall Progress
29,44 Supervision Consultant
Balance -34,1
Contract Sign Progress This Month
1,58 Commencement Date
Time for Complation Days 773
Take Over Date
? A BC D AE
Contract Amount Incl VAT
F GG B
H B
I A
J K E
L MN O
P Q R
Price Adjustment Rp.
Comp Accum
Actual Accum
Accum Total
Last this
to this Sch to this
Month Month
Month Month
I G e n e r a l
2,30 1,11
- 1,11
1,54 II
D r a i n a g e 5,13
0,12 0,25
0,37 4,85
III Earthworks
6,34 1,93
0,52 2,45
5,92 IV
Pavement Widening Shoulders
2,16 0,32
0,18 0,50
1,75 V
Granular Pavement 24,41
4,06 0,28
4,34 16,54
VI Asphalt Pavement
40,48 16,72
0,35 17,06
25,82 VII
S t r u c t u r e s 16,75
3,07 0,01
3,08 5,48
VIII Reinstatement Minor
Works 2,39
0,52 -
0,52 1,75
IX Day Work
0,04 0,00
0,00 0,01
0,08 X
Routine Maintenance Works
- -
- -
- TOTAL
100,0 27,86
1,58 29,44
63,74
Note :
Year Month
Nov Dec
Jan Feb
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Dec
Jan Feb
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Dec
Jan Feb
The month of time for complation 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 17
18 19
20 21
22 23
24 25
26 27
28
Schedl Progress Original 0,11
0,45 1,04
3,18 5,57
8,98 13,46
19,96 23,3
29,8 36,3
42,3 48,17
53,91 58,4
64,3 69,6
75,51 81,15
87,1 90,01
93,9 97,3
98,7 99,7
100,0 100,0
100,0 1st Revised Sch
7,4 11,8
14,1 18,5
23,8 30,1
37,5 44,4
49,9 57,0
63,5 70,6
77,5 84,7
88,2 93,1
97,6 99,4
100,0 Actual Progress
0,15 0,46
0,92 1,42
1,69 2,34
4,72 5,59
5,96 8,94
8,99 12,04
13,25 20,5
26,98 27,86
29,44 Balance
0,03 0,02
0,12 1,76
3,88 6,64
2,7 6,2
8,2 9,5
14,8 18,0
24,2 23,9
23,0 29,2
34,1
Progress per month 0,32
0,46 0,46
0,50 0,27
0,65 2,38
0,87 0,37
2,99 0,04
3,05 1,21
7,27 6,46
0,88 1,58
0,32 0,46
0,50 0,27
0,65 2,38
0,87 0,37
2,99 0,04
3,05 1,21
7,27
EXECUTIVE SUMMARY REPORT
PROGRESS STATUS
15
T IM
E
Mar- 1 7
PROJECT DATA SUMMARY OF WORK PROGRESS
March 25, 2017
MAJOR PROBLEMS ACTION TO BE TAKEN
SIBOLGA - BTS. TAPSEL
2018 2015
2016 2017
DISBURSEMENT Incl VAT A
M O
U N
T
Saleh Samsuri, ST
PHYSICAL WORK PROGRESS BY CATEGORY
31-Des-17
25-Mar-17 88.655.117.690
A Joint Venture of Renardet, S.A. 13-Jul-15
20-Nop-15
260.100.000.000
PHYSICAL PROGRESS MONITORING TABLE Div
Description
Unsettled land acquisitionz: 12.9 Km Residents in the area of Pinangsori - Pinangbaru 4 Km
length is not willing to do remeasurement of land acquisition
Changes in the design of rigid pavement for widening of the road has not been proposed
Delay in relocating the utilities of electrical poles PLN and PDAM pipe water
Acceleration of LARAP implementation After field engineering, the Contractor proposes to utilize
the width of existing road Min. Width 11 m Acceleration of the proposal process
Coordination with PLN. The contract helps provide a ruptured pipe and it was proposed to make ducting for
crossing PDAM pipe every 1 km.
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25 26
P H
Y S
IC A
L P
R O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 15
ORIGINAL Sch 1st REVISED Sch
ACTUAL
3 ESR CTC Mar 2017_E1847F P-15
STTU V
WXY
MONTH :
Package No.
16
Time Elapsed Days 137
Name
Seblat - Ipuh
Time Elapsed 21,7
Project Manager Fathoni Ikhsan, ST
Scheduled Progress 2,10
Contractor KSO PT Yasa - Multi Structure
Actual Overall Progress 2,17
Supervision Consultant A Joint Venture of Renardet, S.A.
Balance 0,07
Contract Sign Progress This Month
1,13 Commencement Date
Time for Complation Days 630
Take Over Date Status date
Contract Amount Incl VAT Rp.
Accumulative Rp. 15,37
Price Adjustment Rp.
Comp Add.2
Accum Actual
Accum Accum
Total Total
Last this
to this Sch to
Month Month
Month this
Month
I G e n e r a l
1,40 0,13
0,48 0,33
0,80 0,80
II D r a i n a g e
13,85 0,09
0,09 0,04
0,12 0,12
III Earthworks
6,57 0,32
0,36 0,20
0,56 0,64
IV Pavement Widening
Shoulders 2,32
0,08 0,08
- 0,08
- V
Granular Pavement 10,85
- -
0,53 0,53
0,46 VI
Asphalt Pavement 51,52
- -
0,00 0,00
0,00 VII
S t r u c t u r e s 8,41
0,00 0,00
- 0,00
- VIII
Reinstatement Minor Works
4,79 -
- -
- -
IX Day Work
0,05 0,00
0,00 0,01
0,01 0,01
X Routine Maintenance
Works 0,24
0,01 0,03
0,02 0,05
0,05 TOTAL
100,00 0,63
1,04 1,13
2,17 2,10
Note :
Nov Dec
Jan Feb
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Dec
Jan Feb
Mar Apr
May Jun
Jul 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 17
18 19
20 21
0,07 0,26
0,57 4,03
8,73 12,40
17,12 21,87
25,29 30,86
36,98 43,59
52,25 58,94
63,06 69,89
75,30 80,70
86,70 92,22
100,0
1st REVISED Schedul 0,16
0,26 0,57
1,02 2,10
4,32 7,15
10,78 16,24
20,83 25,94
30,14 37,57
46,70 53,77
62,47 70,59
80,97 90,76
97,97 100,0
0,18 0,260
0,407 1,04
2,17 0,11
- 0,16
2,99 0,07
Progress per month 0,18
0,08 0,15
0,63 1,13
0,08 0,15
0,63 1,13
2,17 -
- -
- -
- -
-
32.488.260.650
Year
EXECUTIVE SUMMARY REPORT
Mar- 17
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS
DISBURSEMENT Incl VAT
31-Jul-18
25-Mar-17
211.374.500.000 ACTION TO BE TAKEN
A M
O U
N T
T IM
E
March 25, 2017
2018 MAJOR PROBLEMS
Under process of field engineering After field engineering, the Contractor will
evaluate the entire quantity and propose the change to PHO date
PHYSICAL WORK PROGRESS BY CATEGORY
Balance
28-Oct-16 08-Nop-16
2016 2017
Month The month of time for complation
Original Progress Schedul Actual Progress
Div Description
PHYSICAL PROGRESS MONITORING TABLE
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21
P H
Y S
IC A
L P
R O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 16
ORIGINAL Sch 1st REVISED Sch
ACTUAL
C:\Users\Tediero\AppData\Local\Temp\3 ESR CTC Mar 2017_E1847F P-16
Z[[\] _`a
MONTH :
Package No. Time Elapsed Days
568 Name
PUGUNG TAMPAK-Sp.Gn KEMALA Time Elapsed
78,89 Project Manager
Scheduled Progress 62,09
Contractor PT. JAYA KONSTRUKSI MP, Tbk
Actual Overall Progress 61,37
Supervision Consultant Balance
-0,72 Contract Sign
Progress This Month 8,08
Commencement Date Time for Complation Days
720 Take Over Date
b cdce f g
d ch
Contract Amount Incl VAT Rp.
i j j e k e ldcm n
h opq
r st
su
Price Adjustment Rp.
Comp Accum
Actual Accum
Accum Total
Last this
to this Sch to this
Month Month
Month Month
I G e n e r a l
8,05 1,672
0,005 1,676
1,649 II
D r a i n a g e 12,92
5,69 1,211
6,90 7,68
III Earthworks
16,93 16,63
0,257 16,89
17,50 IV
Pavement Widening Shoulders
7,36 2,29
0,253 2,54
3,76 V
Granular Pavement 4,09
1,58 0,134
1,72 1,87
VI Asphalt Pavement
42,82 21,78
6,134 27,92
24,83 VII
S t r u c t u r e s 1,98
3,16 0,076
3,24 4,26
VIII Reinstatement Minor
Works 5,30
0,138 -
0,138 0,17
IX Day Work
0,23 0,07
- 0,07
0,12 X
Routine Maintenance Works
0,34 0,29
0,007 0,29
0,28 TOTAL
100,0 53,30
8,08 61,37
62,10
Note :
Year Month
Sep Oct
Nov Dec
Jan Feb
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Dec
Jan Feb
Mar Apr
May Jun
Jul Agt
Sep
The month of time for complation 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 17
18 19
20 21
22 23
24 25
Schedl Progress Original 0,18
0,70 1,18
1,51 2,39
3,80 6,10
10,09 14,15
18,21 21,04
26,32 33,01
39,79 46,73
54,12 61,80
69,15 75,00
80,05 85,25
90,26 95,19
100,0 100,0
1st Revised Progress Schedul 50,59
55,87 62,09
68,68 75,33
79,35 85,57
91,8 100,0
Actual Progress 0,921
1,13 1,42
3,05 3,45
4,11 6,16
9,54 13,81
16,99 17,41
20,33 28,34
33,32 38,86
41,34 49,01
53,30 61,37
Balance 0,74
0,43 0,23
1,54 1,06
0,30 0,06
0,55 0,34
1,23 3,63
5,99 4,68
6,47 7,87
12,78 12,80
2,57 0,72
Progress per month 0,92
0,21 0,29
1,63 0,40
0,66 2,05
3,38 4,28
3,18 0,42
2,92 8,00
4,99 5,54
2,48 7,66
4,29 8,08
0,21 0,29
1,63 0,40
0,66 2,05
3,38 4,28
3,18 0,42
2,92 8,00
4,99
EXECUTIVE SUMMARY REPORT
Mar- 17
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS
17
T IM
E March 25, 2017
MAJOR PROBLEMS ACTION TO BE TAKEN
RENARDET S.A JV 17-Nov-14
04-Sep-15
DISBURSEMENT Incl VAT A
M O
U N
T
Joko Wisargo, ST, MT
Div Description
23-Agust-17
25-Mar-17
199.551.233.000
99.608.394.983,00
Unsettled land acquisition: 138 PAPS Progress of PLN electric poles relocation has
achieved 20 from total of 588 points. The additional work: 6.8 Km to go back to the
initial target has not been proposed by contractor Acceleration of LARAP implementation
Waiting for WB approval regarding the use of the remaining budget from cancellation of Pack 10
PHYSICAL PROGRESS MONITORING TABLE 2015
2016 2017
PHYSICAL WORK PROGRESS BY CATEGORY
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25
P H
Y S
IC A
L P
R O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 17
ORIGINAL Sch 1st REVISED Sch
ACTUAL
3 ESR CTC Mar 2017_E1847F P-17
MONTH :
Package No. Time Elapsed Days
Name Time Elapsed
Project Manager Yahya, ST
Scheduled Progress 100,0
Contractor Actual Overall Progress
100,0 Supervision Consultant
Balance Contract Sign
Progress This Month Commencement Date
Time for Complation Days 300 Calendar Days
Final Time for Complation Days 477 Calendar Days
vwxwy z
{ xw|
Take Over Date
} ~ ~y y
xw|
Contract Amount Incl VAT Rp.
Contract Amount Add-1 + VAT Rp.
Comp Accum
Actual Accum
Accum Total
Last this
to this Sch to this
Month Month
Month Month
I G e n e r a l
0,43 0,32
0,32 0,32
II D r a i n a g e
3,15 2,73
2,73 2,73
III Earthworks
11,96 11,31
11,31 11,31
IV Pavement Widening
Shoulders 5,30
4,02 4,02
4,02 V
Granular Pavement 10,69
8,82 8,82
8,82 VI
Asphalt Pavement 59,66
64,4 64,4
64,41 VII
S t r u c t u r e s 2,00
4,02 4,02
4,02 VIII
Reinstatement Minor Works
6,79 4,35
4,35 4,35
IX Day Work
X Routine Maintenance
Works 0,03
0,02 0,02
0,02 TOTAL
100,00 100,00
- 100
100,00
Note : 1. 100 completed on 30 Jun 2016
2. Taking-Over Certificate issued on 30 Jun 2016 3. Defects Liability Periode until 29 Jun 2018
Year Month
March April
May June
July Aug
Sept Oct
Nov Des
Jan Feb
March April
May
The month of time for complation 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
Schedl Progress Original 0,12
1,40 8,96
18,40 21,37
23,62 37,37
58,19 87,25
100,00 43,60
52,20 67,79
79,68 98,93
100,00
Actual Progress 0,15
1,30 6,28
14,54 16,21
22,41 28,90
49,74 57,15
57,48 52,77
77,34 80,78
97,14 99,11
Balance 0,03
-0,10 -2,68
-3,86 -5,16
-1,21 -8,47
-8,45 -30,10
13,88 0,57
9,55 1,10
-1,79 -0,89
4,98 8,26
1,67 6,20
6,49 20,84
7,42 0,32
4,71 24,57
3,44 16,36
19
T IM
E March 25, 2017
BINTUNAN-LAIS
MAJOR PROBLEMS ACTION TO BE TAKEN
EXECUTIVE SUMMARY REPORT
Mar- 1 7
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS
44.419.760.000
Rivised Progress Schedul Add.1 2016
PHYSICAL PROGRESS MONITORING TABLE Div
2015 Description
PHYSICAL WORK PROGRESS BY CATEGORY
25-Mar-17 44.419.760.829
27-Feb-15 11-Mar-15
RENARDET S.A JV
30-Jun-16
DISBURSEMENT Incl VAT A
M O
U N
T PT RODATEKNINDO PURAJAYA
33.689.452.000
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15
P H
Y S
ICA L P
R O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 19
ORIGINAL REVISED SCH
ACTUAL
3 ESR CTC Mar 2017_E1847F P-19
MONTH :
Package No. Time Elapsed Days
205 Name
Time Elapsed 42,18
Project Manager Andi Mulya Rusli, ST, MT
Scheduled Progress 45,58
Contractor PT Nindya Karya Persero
Actual Overall Progress 33,37
Supervision Consultant RENARDET S.A JV PT.Yodya Persero
Balance -12,21
Contract Sign Progress This Month
10,23 Commencement Date
Time for Complation Days 486
Calendar Days Take Over Date
Contract Amount Incl VAT Rp.
¡ ¢
67
Price Adjustment Rp.
Comp Accum
Actual Accum
Accum Total
Last this
to this Sch to this
Month Month
Month Month
I G e n e r a l
0,90 0,71
- 0,71
0,62 II
D r a i n a g e 32,44
21,05 5,44
26,49 21,92
III Earthworks
6,64 -
1,20 1,20
4,22 IV
Pavement Widening Shoulders
3,78 -
- -
- V
Granular Pavement 9,52
- 1,74
1,74 4,90
VI Asphalt Pavement
42,49 -
1,62 1,62
9,21 VII
S t r u c t u r e s 1,83
0,46 0,23
0,69 1,01
VIII Reinstatement Minor
Works
1,93 -
- -
0,15 IX
Day Work 0,04
- -
- 0,02
X Routine Maintenance
Works
0,43 0,92
- 0,92
0,18 TOTAL
100,00 23,14
10,23 33,37
42,24
Note :
Year Month
Sep Oct
Nov Dec
Jan Feb
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Dec
The month of time for complation 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 Schedl Progress Original
0,30 0,57
3,95 12,38
19,58 30,48
45,58 57,67
68,57 71,76
77,66 84,15
89,19 95,47
98,66 100,00
1st Revised Progress Schedul 3,95
12,38 19,58
30,48 42,24
57,67 68,57
71,76 77,66
84,15 89,19
95,47 98,66
100,00
Actual Progress 0,39
0,63 3,77
13,60 16,95
23,14 33,37
Balance 0,09
0,06 0,18
1,22 2,63
7,34 12,21
Progress per month
0,39 0,24
3,14 9,83
3,35 6,19
10,23
3,14 9,83
3,35 6,19
10,23 33,37
- -
- -
- -
20 T
IM E
March 25, 2017
LubuK Alun - Sicincin MAJOR PROBLEMS
ACTION TO BE TAKEN
EXECUTIVE SUMMARY REPORT
Mar- 1 7
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS
2016 2017
113.818.300.000
31-Dec-17
There has been no progress of AP paving work. Trial for AC layering did not sufficient with the
temperature requirement. The layering result was not perfect because AC was already cold.
Unsettled land acquisition: 117 PAPs Obstacle in relocation of PDAM pipe
A M
O U
N T
1-Jun-16 1-Sep-16
DISBURSEMENT Incl VAT
Result of AC layering shall be dismantled
Acceleration of LARAP implementation PPK to coordinate with PDAM
Div Description
PHYSICAL PROGRESS MONITORING TABLE PHYSICAL WORK PROGRESS BY CATEGORY
25-Mar-17 33.769.202.420
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
P H
Y S
IC A
L P
R O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 20
ORIGINAL Sch 1st REVISED Sch
ACTUAL
3 ESR CTC Mar 2017_E1847F P-20
£ ¤
¤ ¥ ¦ § ¨
© ª
MONTH :
Package No. Time Elapsed Days
205 Name
Time Elapsed 42,18
Project Manager Opukenigara, ST
Scheduled Progress 35,21
Contractor PT Multi Structur
Actual Overall Progress 21,25
Supervision Consultant RENARDET S.A JV PT. CIPTA STRADA
Balance 13,96
Contract Sign Progress This Month
5,59 Commencement Date
Time for Complation Days 486
Calendar Days Take Over Date
«¬ ¬ ®¯ °
¬ ±
Contract Amount Incl VAT Rp.
² ³³
® ´
® µ
¬ ¶·
± ¸¹º
» ¼ ½» ¾
Price Adjustment Rp.
Comp Accum
Actual Accum
Accum Total
Last this
to this Sch to this Month
Month Month
Month
I G e n e r a l
3,34 3,30
- 3,30
2,34 II
D r a i n a g e 36,79
2,25 1,18
3,44 16,35
III Earthworks
6,17 1,25
0,38 1,63
3,39 IV
Pavement Widening Shoulders
2,29 -
- -
- V
Granular Pavement 7,72
1,32 0,57
1,88 2,94
VI Asphalt Pavement
37,82 5,8
2,69 8,4
6,58 VII
S t r u c t u r e s 3,29
1,21 0,73
1,94 3,29
VIII Reinstatement Minor
Works 2,24
0,51 0,04
0,56 0,17
IX Day Work
0,04 -
- -
0,02 X
Routine Maintenance Works
0,30 0,07
0,00 0,07
0,13 TOTAL
100,00 15,66
5,59 21,25
35,21
Note :
Year Month
Sep Oct
Nov Dec
Jan Feb
Mar Apr
May Jun
Jul Aug
Sep Oct
Nov Dec
The month of time for complation 1
2 3
4 5
6 7
8 9
10 11
12 13
14 15
16 Schedl Progress Original
0,56 2,40
4,37 12,27
21,33 28,48
37,16 43,98
50,80 55,91
62,73 71,26
76,82 82,58
94,28 100,00
1st Revised Progress Schedul 2,05
3,03 9,86
20,07 28,23
35,21 42,76
50,07 55,91
61,52 69,07
75,59 81,76
91,81 100,00
Actual Progress 0,78
1,94 2,20
3,25 13,38
15,66 21,25
Balance 0,22
0,11 0,83
6,61 6,69
12,57 13,96
Progress per month
0,78 1,16
0,26 1,05
10,13 2,28
5,59
0,26 1,05
10,13 2,28
5,59 21,25
- -
- -
- -
21 T
IM E
March 25, 2017
LubuK Alun - Kuraitaji MAJOR PROBLEMS
ACTION TO BE TAKEN
EXECUTIVE SUMMARY REPORT
Mar- 1 7
PROJECT DATA SUMMARY OF WORK PROGRESS
PROGRESS STATUS
2016 2017
31-Dec-17
126.301.900.000
Drainage work progress is too slow. Only 3 teams are available while it required 9 teams. The
total percentage of drainage work is 37 Compared to 38 pavement work
Lack of financial support from the Contractor s Head Office
A M
O U
N T
1-Jun-16 1-Sep-16
DISBURSEMENT Incl VAT
Contractors working team gradual increase of 3 teams into 9 teams
SCM held on March 13, 2017 in Directorate of Road Preservation to ask firmness contractor
management in allocating fund for project implementation.
Div Description
PHYSICAL PROGRESS MONITORING TABLE PHYSICAL WORK PROGRESS BY CATEGORY
25-Mar-17 34.389.954.430
10 20
30 40
50 60
70 80
90 100
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
P H
Y S
IC A
L P
R O
G R
E S
THE MONTH OF TIME FOR COMPLATION
PROGRESS SCHEDULE PACKAGE 21
ORIGINAL Sch 1st REVISED Sch
ACTUAL
3 ESR CTC Mar 2017_E1847F P-21
Western I ndonesia National Roads I mprovement Project
ATTACHMENT No. 1 Summary of Submitted Environmental Reports
¿ À
ÁÂ ÃÄÅ Æ Ç
È ÉÊË
Ì Í
Î Ï
6 7
8 9
1 Krui - Bha
Lampung 1
SPPL November 2010
1X 24 Sep 2013
30 Sep 2013 20 Nov 2013 NOL
2 AMDAL
Environmental Feasibility : 12 Oct 2012 Environmental permits: 21 Nov 2012
1X 24 Sep 2013
30 Sep 2013 20 Nov 2013NOL
3 Monitoring of Integration
AMDAL into Design
-
1X 15 August 2014
NN NN
4 AMDAL Implementation Report
PIU to BLH
-
each 6 month
17 April 2015 ; 6 Oct 2015 ;
29 April 2015 ; 19 Oct 2015
11 Mei 2015 ; 14 Des 2015
5 RKPPL
-
1X 28 Jan 2015
06 Feb 2015 23 Feb 2015NOL
6 RKPPL Implementation Report
-
Quarter 3 July 2015 ; 13 Nov
2015 ; 4 Feb 2016 ; 17 Feb 2016
31 July 2015 ; 24 Nov 2015 ; Informal to WB 4
17 Feb 2016 13 August 2015:
14 Dec 15 ; 19 Feb 2016
7 HIV - AIDS Campaign Report
-
1X 8 January 2016
15 March 2016 NN
2 Padang Sawah - Sp Empat
Sumatera Barat 1
SPPL Nov. 2013
1X -
20 Jan 2014 14 April 2014NOL
Jembatan Air Gadang Sumatera Barat
2 UKL UPL
Recommendation: Nov 2013 1X
- 09 June 2014
08 Auguts 2014NOL 3
UKLUPL Implementation Report PIU to BLH
-
each 6 month
17 April 2015 ; 6 Oct 2015 ; 28 Jun 2016
29 April 2015 ; 19 Oct 2015 : 21 Juli 2016
11 Mei 2015 ; 14 Des 2015 ; 22 Juli 2016
4 RKPPL
-
1X 11 Dec 2014
19 Dec 2014 30 Jan 2015NOL
5 RKPPL Implementation Report
-
Quarter 3 July 2015 ; 13 Nov
2015 ; 4 Feb 2016 ; 17 Feb 2016 ; 28 Jun 2016
31 July 2015 ; 24 Nov 2015 ; Informal to WB 4
17 Feb 2016 ; 21 Juli 2016
13 August 2015: 14 Dec 15 ; 19 Feb
2016 ; 22 Juli 2016 6
HIV - AIDS Campaign Report
-
1X 8 January 2016
15 March 2016 NN
3 Manggopoh - Padang Sawah
Sumatera Barat 1
SPPL 30 Dec 2013
1X -
20 Jan 2014 14 April 2014
2 SPPL Implementation Report
PIU to BLH
-
each 6 month
17 April 2015 29 April 2015
11 Mei 2015 3
RKPPL
-
1X 11 Dec 2014
19 Dec 2014 30 Jan 2015NOL
4 RKPPL Implementation Report
-
Quarter 3 July 2015 ; 13 Nov
2015 ; 4 Feb 2016 ; 17 Feb 2016
31 July 2015 ; 24 Nov 2015 ; Informal to WB 4
17 Feb 2016 13 August 2015:
14 Dec 15 ; 19 Feb 2016
5 HIV - AIDS Campaign Report
-
1X 8 January 2016
15 March 2016 NN
4 Ipuh - Bantal
Bengkulu 1
SPPL Initial study 20 Dec 2013
1X April 2013
- -
2 UKL UPL
Environmental permits : 6 Des 2014 1X
- 06 Feb 2015
Environment permits 23 Feb 2015
3 UKLUPL Implementation
Report PIU to BLH
-
each 6 month
17 April 2015 ; 6 Oct 2015 ; 28 Juni 2016
29 April 2015 ; 19 Oct 2015 : 21 Juli 2016
11 Mei 2015 ; 14 Des 2015 ; 22 Juli 2016
4
Date of Recomendation Environmental Permits
No of Package
Name of Link Province
Sent to WB CTC Letters to PMU
Durations Environmental Activity, CTC WINRIP
WB NOLLetters Environmental Safeguard
1 2
3 5
6 7
8 9
4
Environmental Permits No of
Package Name of Link
Province Sent to WB
CTC Letters to PMU Durations
WB NOLLetters Environmental Safeguard
4 RKPPL
-
1X 28 Jan 2015
06 Feb 2015 23 Feb 2015NOL
5 RKPPL Implementation Report
-
Quarter 3 July 2015 ; 13 Nov
2015 ; 4 Feb 2016 ; 17 Feb 2016 ; 28 Jun 2016
31 July 2015 ; 24 Nov 2015 ; Informal to WB 4
17 Feb 2016 ; 21 Juli 2016
13 August 2015: 14 Dec 15 ; 19 Feb
2016 ; 22 Juli 2016 6
HIV - AIDS Campaign Report
-
1X 8 January 2016
15 March 2016 NN
5 Sp. Rampa - Poriaha
Sumut 1
UKL UPL Recommendation : 8 Dec 2011
1X 24 Sep 2013
30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKLUPL into Design
-
1X 11 Nov 2014
NN NN
3 UKLUPL Implementation
Report PIU to BLH
-
each 6 month
28 Jun 2016 21 Juli 2016
22 Juli 2016 4
RKPPL
-
1X 26 April 2016
13 May 2016 30 Juni 2016
6 RKPPL Implementation Report Quarter
4 Feb 2016 ; 17 Feb 2016 ; 28 Jun 2016;11
Nov 2016 Informal to WB 4 17
Feb 2016 : 21 Juli 2016; 28 Nov 2016 ; 15 Mar
2017 informal 19 Feb 2016 ; 22 Juli
2016; 19 Des 2016 6
HIV - AIDS Campaign Report
-
1X 29 February 2016
15 March 2016 NN
6 Ps. Pedati - Kerkap
Bengkulu 1
UKL UPL Recommendation : 9 Nov 2011
1X 24 Sep 2013
30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKLUPL into Design
-
1X 29 Oct 2015
NN NN
3 UKLUPL Implementation
Report PIU to BLH
-
Quarter 28 Jun 2016
21 Juli 2016 ; 20 Nov 2016 informal
22 Juli 2016 4
RKPPL
-
one time 4 Nov 2015
24-Nop-15 14 Des 2016 NOL
5 RKPPL Implementation Report Quarter
13 Nov 2015 ; 4 Feb 2016 ; 17 Feb 2016 ; 28
Jun 2016 ; 11 Nov 2016 24 Nov 2015; Informal to
WB 4 17 Feb 2016; 21 Juli 2016; 28 Nov 2016 ;
15 Mar 2017 informal 14 Des 2016 NOL ; 19
Feb 2016 ; 22 Juli 2016; 19 Des 2016
6 HIV - AIDS Campaign Report
-
1X 12 February 2016
15 March 2016 NN
7 Indrapura - Tapan
Sumatera Barat 1
AMDAL Environmental feasibility : 05 Feb 2014 ;
environmental permits : 5 Feb 2014 1X
- 09 June 2014
08 August 2014 2
Monitoring of Integration AMDAL into Design
-
1X 2 Dec 2015
NN NN
3 AMDAL Implementation Report
PIU to BLH
-
each 6 month
1 March 2017 UP
NYS 4
RKPPL
-
1X 27 Feb 2017
20 March 2017 UP
5 RKPPL Implementation Report Quarter
15 Mar 2017 informal
15 Mar 2017 informal NN
6 HIV - AIDS Campaign Report
-
1X 29 Sept 2016
13 October 2016 NN
8 Bts. Kota Pariaman - Manggopoh
Sumatera Barat 1
AMDAL Environmental permits : 23 July 2013
1X -
20 Jan 2014 14 April 2014
2 Monitoring of Integration
AMDAL into Design
-
1X 6 Oct 2015
NN NN
1 2
3 5
6 7
8 9
4
Environmental Permits No of
Package Name of Link
Province Sent to WB
CTC Letters to PMU Durations
WB NOLLetters Environmental Safeguard
3 AMDAL Implementation Report
PIU to BLH
-
each 6 month
29 Sept 2016 13 October 2016
NY 4
RKPPL
-
1X 02 November 2016
14 November 2016 23 November 2016
5 RKPPL Implementation Report Quarter
15 Mar 2017 informal
15 Mar 2017 informal NN
6 HIV - AIDS Campaign Report
-
1X 11 November 2016
28 November 2016 NN
9 Bentungan- Tais N.013.018 ; 43,42
km Bengkulu
10 Sp. Empat - Air Balam
Sumatera Barat 1
AMDAL Environmental permits : 23 July 2013
1X -
20 Jan 2014 14 April 2014
11 Bantal - Mukomuko
Bengkulu 1
AMDAL Environmental permits : 3 April 2014
1X -
09 June 2014 08 August 2014
2 Monitoring of Integration
AMDAL into Design
-
1X 10 Dec 2014
NN NN
3 AMDAL Implementation Report
PIU to BLH
-
each 6 month
28 Jun 2016 ; 29 April 2016 informal
; 21 Juli 2016 ; 5 Des 2016 informal
22 Juli 2016 4
RKPPL
-
1X 10 Des 2015
23-Des-15 8 Jan 2016NOL
5 RKPPL Implementation Report Quarter
13 Nov 2015 ; 4 Feb 2016 ; 17 Feb 2016 ; 28
Jun 2016 ; 11 Nov 2016; 15 Mar 2017 informal
24 Nov 2015; Informal to WB 4 17 Feb 2016; 21
Juli 2016; 28 Nov 2016 ; 15 Mar 2017 informal
14 Des 2016 NOL ; 19 Feb 2016 ; 12 Juli
2016; 19 Des 2016 6
HIV - AIDS Campaign Report
-
1X 8 January 2016
15 March 2016 NN
12 Kambang - Indrapura
Sumatera Barat 1
AMDAL Environmental Feasibility : 05 Feb 2014 ;
Environmental permits : 5 Feb 2014 1X
- 09 June 2014
08 August 2014 2
Monitoring of Integration AMDAL into Design
-
1X 2 Dec 2015
NN NN
3 AMDAL Implementation Report
PIU to BLH
-
each 6 month
1 March 2017 UP
NYS 4
RKPPL
-
1X 27 Feb 2017
20 March 2017 UP
5 RKPPL Implementation Report Quarter
15 Mar 2017 informal 15 Mar 2017 informal NN
6 HIV - AIDS Campaign Report
-
1X 29 Sept 2016
13 October 2016 NN
13 Sp. Rukis - Tj. Kemuning
Bengkulu 1
UKL UPL Recommendation : 31 Jan 2012 Link of Sp
Rukis Mana-Bts Kab Kaur 4 Feb 2012 Bts Kaur - Tj Kemuning
1X -
09 June 2014 08 August 2014
2 Monitoring of Integration
UKLUPL into Design
-
1X 6 Oct 2015
NN NN
3 UKLUPL Implementation
Report PIU to BLH
-
each 6 month
28 Jun 2016 21 Juli 2016
22 Juli 2016 4
RKPPL
-
1X 4 Nov 2015
24-Nop-15 14 Dec 2015NOL
1 2
3 5
6 7
8 9
4
Environmental Permits No of
Package Name of Link
Province Sent to WB
CTC Letters to PMU Durations
WB NOLLetters Environmental Safeguard
5 RKPPL Implementation Report Quarter
4 Feb 2016 ; 17 Feb 2016 ; 28 Jun 2016 : 11
Nov 2016; 15 Maret 2017
Informal to WB 4 17 Feb 2016 : 21 Juli 2016;
28 Nov 201615; Mar 2017 informal
19 Feb 2016 ; 22 Juli 2016; 16 Des 2016
6 HIV - AIDS Campaign Report
-
1X 12 February 2016
15 March 2016 NN
14 Painan - Kambang
Sumatera Barat 1
AMDAL Environmental Feasibility : 05 Feb 2014 ;
Environmental permits : 5 Feb 2014 1X
- 09 June 2014
08 August 2014 2
Monitoring of Integration AMDAL into Design
-
1X 2 Dec 2015
NN NN
3 AMDAL Implementation Report
PIU to BLH
-
each 6 month
1 March 2017 UP
NYS 4
RKPPL
-
1X 10 Feb 2017
28 Feb 2017 17 March 2017
5 RKPPL Implementation Report Quarter
15 Mar 2017 informal 15 Mar 2017 informal NN
6 HIV - AIDS Campaign Report
-
1X 21 Des 2016
28 Des 2016 NN
15 Sibolga - Bts. Tapsel
Sumut 1
UKL UPL Recommendation : 8 Dec 2011
1X 24 Sep 2013
30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKLUPL into Design
-
1X 11 Nov 2014
NN NN
3 UKLUPL Implementation
Report PIU to BLH
-
each 6 month
28 Jun 2016 21 Juli 2016
22 Juli 2016 4
RKPPL
-
1X 02 November 2016
14 November 2016 23 November 2016
5 RKPPL Implementation Report Quarter
28 Juni 2016 : 11 Nov 2016; 15 Mar 2016
informal 21 Juli 2016; 28 Nov
2016; 15 Mar 2017 informal
22 Juli 2016; 19 Des 2016
6 HIV - AIDS Campaign Report
-
1X 29 February 2016
15 March 2016 NN
16 Sebelat-Ipuh Inc.Air Lalang Air
Gunung Bridges Bengkulu
1 AMDAL
Environmental permits : 3 April 2014 1X
- 09 June 2014
08 August 2014 2
Monitoring of Integration AMDAL into Design
-
1X 10 Dec 2014
NN NN
3 AMDAL Implementation Report
PIU to BLH
-
each 6 month
NYS NYS
NN 4
RKPPL
-
1X NYS
NYS NYS
5 RKPPL Implementation Report Quarter
NYS NYS
NN 6
HIV - AIDS Campaign Report
-
1X NYS
NYS NYS
17 Sp. Gunung Kemala-Pg. Tampak,
Inc Way Tauu Bridge Lampung
1 AMDAL
Environmental Feasibility : 12 Oct 2012 Environmental permits: 21 Nov 2012
1X 24 Sep 2013
30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
AMDAL into Design
-
1X 11 Nov 2014
NN NN
3 AMDAL Implementation Report
PIU to BLH
-
each 6 month
28 Jun 2016 21 Juli 2016 ; 28 Sept
2016 ; 20 Nov 2016 22 Juli 2016
4 RKPPL
-
1X 26 April 2016
13 May 2016 30 Juni 2016
1 2
3 5
6 7
8 9
4
Environmental Permits No of
Package Name of Link
Province Sent to WB
CTC Letters to PMU Durations
WB NOLLetters Environmental Safeguard
5 RKPPL Implementation Report Quarter
28 Juni 2016 : 11 Nov 2016;15 Mar 2017
informal 21 Juli 2016; 28 Nov
2016 ;15 Mar 2017 informal
22 Juli 2016; 19 Des 2016
6 HIV - AIDS Campaign Report
-
1X 8 January 2016
15 March 2016 NN
18 Seblat - Ketahun N.013.005 :
Panjang 42,07km Bengkulu
19 Lais- Bintunan
Bengkulu 1
UKL UPL Recommendation : 9 Nov 2011
1X 24 Sep 2013
30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKLUPL into Design
-
1X 6 Oct 2015
NN NN
3 UKLUPL Implementation
Report PIU to BLH
-
each 3 month
28 Jun 2016 21 Juli 2016 ; 20 Nov
2016 informal 22 Juli 2016
4 RKPPL
-
1X 4 Nov 2015
24-Nop-15 14 Dec 2015NOL
5 RKPPL Implementation Report Quarter
13 Nov 2015 ; 4 Feb 2016 ; 17 Feb 2016 ; 28
Jun 2016 ; 11 Nov 2016 24 Nov 2015; Informal to
WB 4 17 Feb 2016: 21 Juli 2016; 28 Nov 2016
14 Des 2016 NOL ; 19 Feb 2016 ; 22 Juli
2016; 19 Des 2016 6
HIV - AIDS Campaign Report
-
1X 12 February 2016
15 March 2016 NN
20 Lubuk Alung - Sincin
Sumatera Barat 1
UKL UPL Recommendation : 27 Dec 2011
1X 24 Sep 2013
30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKLUPL into Design
-
1X 29 Oct 2015
NN NN
3 UKLUPL Implementation
Report PIU to BLH
-
each 6 month
NYS NYS
NN 4
RKPPL
-
1X 10 Feb 2017
28 Feb 2017 17 March 2017
RKPPL Implementation Report Quarter
15 Mar 2017 informal 15 Mar 2017 informal NN
5 HIV - AIDS Campaign Report
-
1X NYS
NYS NN
21 Lubuk Alung - Kuraitaji
Sumatera Barat 1
UKL UPL Recommendation : 27 Dec 2011
1X 24 Sep 2013
30 Sep 2013 20 Nov 2013
2 Monitoring of Integration
UKLUPL into Design
-
1X 29 Oct 2015
NN NN
3 UKLUPL Implementation
Report PIU to BLH
-
each 6 month
NYS NYS
NN 4
RKPPL
-
1X 27 Feb 2017
20 March 2017 UP
5 RKPPL Implementation Report Quarter
15 Mar 2017 informal 15 Mar 2017 informal NN
6 HIV - AIDS Campaign Report
-
1X NYS
NYS NN
Keterangan :
incl. 1 Document Studi Amdal incl. 1 Document Studi Amdal
NYS: Not Yet Started incl. 1 Document Studi Amdal
NY : Not Yet NN : Not Need
UP : Under Process
Western I ndonesia National Roads I mprovement Project
Appendix A Overall Loan Progress
Estimated Contractors or
Total Est. Budget
Starting Completion
Consultants Man-Month
WB + GOI Remarks
Date Date
Name Excl. the
PIP Original
Physical Man-Month Physical Man-Month Physical Man-Month
Supp. Staff
USD, Excl.VAT In IDR
In USD Amendment No. 1 In
IDR Amendment No. 2 In
IDR Amendment No. 3 In
IDR Amendment No. 4 In
IDR Amendment No. 5 In
IDR Amendment No. 6 In
IDR Amendment No. 7 In
IDR Amendment No. 8 In
IDR
MM MM
MM
1 Betterment and Capacity
308.730.000,00 222.678.368,65
Expansion of National Roads
1.A AWP-1
ICB DGH
81.630.000,00 57.821.551,95
1. Krui-Biha 08-Jan-14
10-Jan-16 PT. Jaya Konstruksi
134.909.211.000,00 Rp
11.757.337,74 154.073.015.000
Rp 154.073.015.000
Rp 140.255.020.000
Rp 100
100 0,00
Completed
2. Pd. Sawah-Sp. Empat 06-Jan-14
19-Apr-16 PT.Jaya Konstruksi
197.936.699.896,00 Rp
17.250.183,32 226.713.217.000
Rp 249.348.931.000
Rp 247.572.130.000
Rp 100
100 0,00
Completed
3. Manggopoh-Pd. Sawah 06-Jan-14
20-Mar-16 PT. Jaya Konstruksi
143.688.963.435,00 Rp
12.522.493,13 165.157.772.000
Rp 183.940.872.000
Rp 100
100 0,00
Completed
4. Ipuh-Bantal 10-Jan-14
11-Apr-16 PT. Waskita Karya
186.936.750.000,00 Rp
16.291.537,76 196.438.084.000
Rp 194.902.179.000
Rp 100
100 0,00
Completed
1.B AWP-2 and AWP-3
ICB NCB
DGH 227.100.000,00
164.856.816,70 5. Sp. Rampa - Poriaha
18-Jun-15 08-Des-16
PT. Nusa Konstruksi Enjiniring Tbk
107.321.260.000,00 Rp
8.084.464,03 76,53
48,20 -28,33
Ongoing Construction
6. Ps Pedati - Kerkap 11-Mar-15
02-Jun-16 PT. Waskita Karya Tbk
86.517.470.000,00 Rp
6.641.396,33 118.444.156.000
Rp 100
100 0,00
Ongoing Construction
7. Indrapura - Tapan 10-Des-15
30-Agust-17 PT. Adhi Karya 129.699.900.000,00
Rp 9.350.065,79
55,68 48,05
-7,63 Ongoing Construction
8. Bts. Kt Pariaman - Manggopoh 23-Mar-16
31-Des-17 PT. PPPT. Statika
355.500.000.000,00 Rp
25.627.995,00 51,83
57,22 5,39
Ongoing Construction
9. R. Tijang - Kt. Agung Cancelled
10. Sp Empat - Sp Air Balam Propose to be Cancelled
11. Bantal - Mukomuko 23-Feb-15
11-Feb-17 PT. Hutama Karya - PT.
DMT, JO
228.899.717.000,00 Rp
18.765.198,80 262.611.303.000
Rp 95,85
96,37 0,52
Ongoing Construstion
12. Kambang - Indrapura 23-Mei-16
31-Des-17 PT. LancarjayaPT. Cahaya
T.A
358.650.400.000,00 Rp
25.855.107,34 40,55
5,93 -34,62
Ongoing Construstion
13. Sp. Rukis - Tj. Kemuning 22-Jul-15
10-Jul-17 PT. Waskita Karya
292.700.000.000,00 Rp
23.454.051,00 72,34
44,34 -28,00
Ongoing construction
14. Painan -Kambang 03-Agust-16
31-Des-17 KSO Yasa - Conbloc
214.327.429.680,00 Rp
16.286.741,38 20,60
15,63 -4,97
Ongoing Construction
15. Sibolga - Bts Tap Sel 20-Nop-15
31-Des-17 PT. PP
260.100.000.000,00 Rp
19.954.872,00 63,52
29,44 -34,08
Ongoing Construction
16. Seblat - Ipuh 211.374.500.000,00
Rp 2,10
2,17 0,07
Waiting NTP
17. Sp. Gunung Kemala - Pg. Tampak
04-Sep-15 23-Aug-17
PT. Jaya Konstruksi 199.551.233.000,00
Rp 16.335.263,93
62,09 61,37
-0,72 Ongoing construction
18. Mukomuko - Bts. Sumbar Cancelled
19. Lais- Bintunan 11-Mar-15
08-Mar-16 PT. Rodatekindo Purajaya
Rp 33.689.452.000,00 2.586.125,12 Rp 44.419.760.000
100 100
0,00 Completed
20. Lubuk Alung - Sicincin PT. Nindya Karya
Rp 113.818.300.000,00 8.578.485,27
42,24 33,37
-8,87 Ongoing Construction
21. Lubuk Alung -Kuraitaji PT. Multi Structure
Rp 126.301.900.000,00 9.519.374,20
35,21 21,25
-13,96 Ongoing Construction
1.C Contingency
- DGH
6.170.000,00
2 Implementation Support
16.000.000,00 2.A
Core Team Consultants CTC QCBS
DGH 06-Nop-12
30-Des-17 PT. Perentjana Djaja
556 5.000.000,00
1.276.700,00 1.315.925,00
1.371.925,00 1.339.925,00
1.918.158,00 212.95
187.95 25.00
Supporting PMU. Joint Venture with
Rp21.415.400.000,00 Rp22.426.175.000
Rp22.458.676.500 Rp23.934.595.000
Rp40.878.169.529 Yongma Engineering Co.Ltd.
Or US equivalent total : 25-Okt-13
03-Sep-14 30-Nop-15
04-Mar-16
PT. Epadascon Permata 3.512.681,91
3.641.077,48 2.B
Design Superv. Consultants QCBS
DGH 19-Jun-13
18-Nop-16 Renardet S.A.
1.068 10.000.000,00
820.600,00 42.33
36.33 -6.00
Design preparation and construction supervision.
Joint Venture with Rp51.818.705.000,00
PT Cipta Strada Or US equivalent total :
PT. Daya Creasi Mitrayasa 6.465.729,72
PT. Seecons PT. Yodya Karya
2.C 2.D
Incremental Operating Cost Varies
PMU 1.000.000,00
Including Technical Audits 4
Contingency for Disaster DGH
-
Risk Response 5
Unallocated DGH
18.100.000,00 Total
342.830.000,00 232.656.780,28
Appendix - A
OVERALL PROGRESS STATUS
Description
WESTERN INDONESIA NATIONAL ROADS IMPROVEMENT PROJECT WINRIP IBRD LOAN No. 8043-ID
Proc. Metho
d Category
Planned Actual
Balance
Development of Slope Stabilization, Design and
Management
31 March 2017
PROGRESS
Respon- sibility
Total WB + GOI Contract Value
Revised in 000
Western I ndonesia National Roads I mprovement Project
Appendix B Road Safety Audit Progress
Appendix B. Road Safety Audit Progresss March 2017
Old 2004 New 2009
Site Visiting Submission of
Report Site Visiting
Submission of Report
Site Visiting Submission of
Report
1. No Road Safety Audit at Design Stage. 2. Road Safety Engineering Review by CTC, Dec, 2014
3. RSA at Construction StageMonitoring of Traffic Mgmt Safety by CTC, Dec, 2014 Date
13-Nop-14 29-Des-14
13-Nop-14 29-Des-14
11-Feb-16 22-Feb-16
4. RSA at PHO stage by CTC, February, 2016 1. No Road Safety Audit at Design Stage.
2. Road Safety Engineering Review by CTC, Nov, 2014 3. RSA at Construction StageMonitoring of Traffic Mgmt Safety by CTC, Nov, 2014
Date 09-Okt-14
05-Nop-14 09-Okt-14
05-Nop-14 06-Apr-16
12-Apr-16 4. RSA at PHO stage by CTC, April, 2016
1. No Road Safety Audit at Design Stage. 2. Road Safety Engineering Review by CTC
3. RSA at Construction StageMonitoring of Traffic Mgmt Safety by CTC, Nov, 2014 Date
09-Okt-14 05-Nop-14
09-Okt-14 05-Nop-14
17-Mar-16 23-Mar-16
4. RSA at PHO stage by CTC, March, 2016 1. No Road Safety Audit at Design Stage.
2. Road Safety Engineering Review by CTC 3. RSA at Construction StageMonitoring of Traffic Mgmt Safety by CTC, Dec, 2014
Date 13-Nop-14
29-Des-14 13-Nop-14
29-Des-14 14-Apr-16
26-Apr-16 4. RSA at PHO stage by CTC, April, 2016
1. Technical Advisory Report by International RSA CTC, Sept 2013 Date
08-May-13 17-Sep-13
1. Technical Review RSA at Design Stage done by International RSA CTC 2. RSA at Construction StageMonitoring of Traffic Mgmt Safety by CTC, Sep, 2015
3. RSA at PHO stage by CTC, November, 2016 Date
18-Jul-13 17-Sep-13
25-Agust-15 08-Sep-15
17-18 Nov-16 19-Des-16
1. Technical Advisory Report by International RSA CTC, Sept 2013
27-Sep-13 2. Road Safety Audit by Dit. EA RS, May 2014
3. Result of Highway and RSA Final DED Review by CTC, Nov 2014 Date
Apr-14 Mei-14
08-Des-16 22-Des-16
1. Technical Advisory Report by CTC, Sept 2013
27-Sep-13 2. Road Safety Audit by Dit. EA RS, May 2014
3. Result of Highway and RSA Final DED Review by CTC, Nov 2014 Date
Apr-14 Mei-14
1. Technical Advisory Report by CTC, Sept 2013
27-Sep-13 2. Road Safety Audit by Dit. EA RS, May 2014
3. Result of Highway and RSA Final DED Review by CTC, Nov 2014 Date
Apr-14 Mei-14
1. Technical Review RSA at Design Stage by International RSA CTC , Jul, 2013 2. RSA at Construction StageMonitoring of Traffic Mgmt Safety by CTC, Dec, 2015
Date 18-Jul-13
18-Jul-13 17-Des-15
29-Des-15
1. Technical Advisory Report by International RSA CTC, Sept 2013
27-Sep-13 2. Road Safety Audit by Dit. EA RS, May 2014
3. Result of Highway and RSA Final DED Review by CTC, Nov 2014 Date
Apr-14 Mei-14
1. Technical Advisory Report by International RSA CTC, Sept 2013 2. RSA at Construction StageMonitoring of Traffic Mgmt Safety by CTC, Mar, 2017
Date 18-Jul-13
18-Jul-13 23-Mar-17
03-Apr-17
1. RSA DED Report by CTC, June, 2015 Date
15-Apr-15 15-Jun-15
1. Technical Advisory Report by International RSA CTC, Sept 2013 Date
08-May-13 21-Aug-13
23-Sep-13
1. RSA DED Report by CTC, Sept, 2014 Date
14-Agust-14 01-Sep-14
Date 6
255.269 Process
No Road Safety Audit at Design Stage 6
110.237 Process
33
16 17
Sp.Gng Kemala–Pg.Tampak 17.061.1
17.025.0 36.80
15 16
Seblat – Ipuh 13.010.0
13.004.0 34.50
13.006.0 13.021.0
56.30
35.86 7
376.479 Process
33 31.50
7 118.993
Process 33
6 262.611
Process 66
50.10
14 15
Sibolga – Bts TapSel 03.016.1
03.044.0
7 316.304,8
Process 66
13 14
Painan – Kambang 06.017.1
06.032.0 12
13 SP.Rukis - TJ.Kemuning
Process 33
46.80 7
374.647 Process
33
11 12
Kambang – Indrapura 06.17.2
06.033.0 10
11 Bantal - Mukomuko
13.015.2 13.002.0
45.20 7
438.675 Process
33
9 10
Sp.Empat – Sp. Air Balam 06.034.1
06.020.0
7 175.812
Process 33
8 8
Bts.Pariaman – Manggopoh 06.24.0
06.23.0 7
7 Indrapura – Tapan
06.019.0 06.34.0
19.50
61.70 7
511.375 20.88
7 92.127
Process 83
6 152.870
Process 33
9.7
6 6
PS.Pedati - Kerkap 13.010.0
13.009.0 5
5 Sp.Rampa – Poriaha
xx.xxx.x 03.075.0
42.40 7
247.105 Process
100 7
167.678 Process
100 32.00
4 4
Ipuh - Bantal 13.051.1
13.003 3
3 Manggopoh -Padangsawah
06.047.1 06.022.0
40.90 7
228.772 Process
100 7
163.535 Process
100 25.00
2 2
Padangsawah - Simpangempat 06.047.2
06.021.0 1
1 Biha - Krui
17.053.0 17.027.0
Estimated Cost
Excl.VAT mil. RP
Road Safety Audit Total Process
Remarks Status
Design Stage Construction Stage
PHO Stage No
Pkg No.
Name of Sub-project Link No
Length km
Width m
Old 2004 New 2009
Site Visiting Submission of
Report Site Visiting
Submission of Report
Site Visiting Submission of
Report Estimated
Cost Excl.VAT
mil. RP Road Safety Audit
Total Process Remarks
Status Design Stage
Construction Stage PHO Stage
No Pkg
No. Name of Sub-project
Link No Length
km Width
m
1. Technical Advisory Report by International RSA CTC, Sept 2013 2. RSA at Construction StageMonitoring of Traffic Mgmt Safety by CTC, Sep, 2015
3. RSA at PHO stage by CTC, May, 2016 Date
18-Jul-13 17-Sep-13
25-Agust-15 08-Sep-15
19-Mei-16 24-Mei-16
1. RSA DED Report by CTC, June, 2015 Date
15-Apr-15 15-Jun-15
1. RSA DED Report by CTC, June, 2015 Date
15-Apr-15 15-Jun-15
Date Date
Notes :
Road Safety Engineering Review by CTC Road Safety Audit by International RSA CTC
Road Safety Audit by Dit. EA RS DGH Road Safety Audit by CTC
16.80 7
65.788 Process
33
69.233 Process
25.80 6
9 Rantau Tijang – Kota Agung
17.026.1 17.032.0
14.60 7
54.557 Process
42.00 7
149.831 Process
18 Mukomuko – Bts.Sumbar
13.015.3 13.001.0
33
19 21
Lubuk Alung - Kuraitaji 06.027.0
06.025.0
7 35.886
Process 100
18 20
Lubuk Alung – Sicincin 06.009.1
06.041.0 17
19 Lais - Bintuan
13.009.1 13.007.0
10.80
Western I ndonesia National Roads I mprovement Project
Appendix C Financial Progress