Monitoring Report of the LARAP Package No. 7
12. Monitoring Report of the LARAP Package No. 12
: Kambang - Indrapura Province : Sumatera Barat A. Previous Status : • LARAP documents approved by World Bank on October 14, 2014. • Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank. • Monitoring Report for compensation payment of 216 PAPs submitted to WB on May 26, 2016. • A Monitoring Report of the compensation payment progress for 60 PAPs has submitted to WB and no objection letter NOL was issued on November 14, 2016 • A Monitoring Report of the compensation payment progress for 88 PAPs has submitted to WB and no objection letter NOL was issued on Feb 13, 2017 B. Pending Issues, Concern and Actions a Pending of assessment process is a hindrance to complete compensation payment C. Update during this reporting month of March 2017 a Currently there are 28 Km out of the total length of 56 Km, that land aquisition is not needed. b Assessment of the affected assets in Sub District of Lengayang being conducted by Appraisal Consultants c Total PAP = 2,476 updated; Compensated = 1,053; Percent complete = 42.5.13. Monitoring Report of the LARAP Package No. 13
: Sp. Rukis Tj. Kemuning Province : Bengkulu A. Previous Status : • World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation. • Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank. • World Bank issued on August 18, 2015 No Objection Letter NOL on the monitoring Report No.1. • World Bank issued on October 13, 2015 No Objection Letter NOL on the monitoring Report No.2. • Monitoring Report No.3 for compensation payments of 193 PAPs in Kab. Kaur submitted to WB which was submitted on February 23, 2016 has been issued by the Bank the NOL on March 8, 2016. • Monitoring Report No.4 for compensation payments of 188 PAPs in Kab. Kaur submitted to WB which was submitted on October 6, 2016 has been issued by the Bank the NOL on October 12, 2016. • Monitoring Report of the payments progress for 333 PAPs has submitted to WB has been issued by the Bank the NOL on November 18, 2016. • Monitoring Report of the payments progress for 1.090 PAPs has submitted to WB has been issued by the Bank the NOL on March 20, 2017. B. Pending Issues, Concern and ActionsParts
» WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Current Implementation Situation Civil Works
» Disbursement WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» World Bank Implementation Review Mission and Site Visit
» Procurement of Civil Works Contract Under Category 1 of the Loan Agreement
» Background WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Project Development WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Project Objective WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Scope of Services CTC Consultants
» CTC Contract CTC Consultants
» DSC Consultants WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Technical Assistance for Development of Slope Stabilization, Design and
» Detailed Design Preparation WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Procurements WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Civil Works Implementation WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Civil Works Progress WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 48.20 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» -7.63 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 158 CD WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 57.22 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 56.64 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 0.52 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 62CD WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» -34.62 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 281 CD WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» -28.01 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 107 CD WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 15.63 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» -34.08 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 0.07 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 492 CD WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 61.37 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 33.37 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 21.25 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Quality Assurance WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Review Design Integration, Road Safety Aspects and Monitoring of Environmental Studies
» The Contractor Action Plan on Environmental Management and Monitoring RKPPL
» Environmental Quarterly Report Environmental Issues
» Socialization of HIV-AIDs Campaign
» Quarries Management. Environmental Issues
» WB Mission 15 17 February 2017 on Packages No.7,12 14
» Monitoring Report of the LARAP Package No. 1
» Monitoring Report of the LARAP Package No. 2
» Monitoring Report of the LARAP Package No. 3
» Monitoring Report of the LARAP Package No. 4
» Monitoring Report of the LARAP Package No. 5
» Monitoring Report of the LARAP Package No. 6
» Monitoring Report of the LARAP Package No. 7
» Monitoring Report of the LARAP Package No. 8
» Monitoring Report of the LARAP Package No. 9
» Monitoring Report of the LARAP Package No. 10
» Monitoring Report of the LARAP Package No. 11
» Monitoring Report of the LARAP Package No. 12
» Monitoring Report of the LARAP Package No. 13
» Monitoring Report of the LARAP Package No. 14 Monitoring Report of the LARAP Package No. 15
» Monitoring Report of the LARAP Package No.16
» Monitoring Report of the LARAP Package No.17
» Monitoring Report of the LARAP Package No.18
» Monitoring Report of the LARAP Package No.19
» Monitoring Report of the LARAP Package No. 20
» Monitoring Report of the LARAP Package No. 21
» Anti Corruption Action Plan ACAP
» Community Representative Observers CRO
» Publication Disclosure Anti Corruption Issues
» Complaints Handling Mechanism CHS
» Road Safety Audit WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Database Establish the Document Management System DMS to provide:
» World Bank Missions Agreed Key Actions and Mission Plans during Recent World Bank Mission
» Performance Indicators World Bank and GOI Compliance
» Design and Supervision Consultant DSC
» Study on Development of Slope Stabilization Design and Management
» Complaint Handling System CHS
» DMS Statistic Management Information System
» Draw Downs and Future Costs Disbursement Quality Assurance
» Financial Risks Project Risks and Mitigation Measures
» Training to Support Project Implementation
Show more