Western I ndonesia National Roads I mprovement Project 4 - 23
a Complete. b Total PAP = 243 updated; Compensated = 243; Percent complete =100.
12. Monitoring Report of the LARAP Package No. 12
: Kambang - Indrapura Province
: Sumatera Barat
A. Previous Status : •
LARAP documents approved by World Bank on October 14, 2014. •
Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank. •
Monitoring Report for compensation payment of 216 PAPs submitted to WB on May 26, 2016. •
A Monitoring Report of the compensation payment progress for 60 PAPs has submitted to WB and no objection letter NOL was issued on November 14, 2016
• A Monitoring Report of the compensation payment progress for 88 PAPs has submitted to WB
and no objection letter NOL was issued on Feb 13, 2017 B. Pending Issues, Concern and Actions
a Pending of assessment process is a hindrance to complete compensation payment C. Update during this reporting month of March 2017
a Currently there are 28 Km out of the total length of 56 Km, that land aquisition is not needed.
b Assessment of the affected assets in Sub District of Lengayang being conducted by Appraisal Consultants
c Total PAP = 2,476 updated; Compensated = 1,053; Percent complete = 42.5.
13. Monitoring Report of the LARAP Package No. 13
: Sp. Rukis Tj. Kemuning
Province : Bengkulu
A. Previous Status : •
World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation.
• Signed Action Plan of LARAP was given No Objection Letter NOL by the World Bank.
• World Bank issued on August 18, 2015 No Objection Letter NOL on the monitoring Report No.1.
• World Bank issued on October 13, 2015 No Objection Letter NOL on the monitoring Report No.2.
• Monitoring Report No.3 for compensation payments of 193 PAPs in Kab. Kaur submitted to WB
which was submitted on February 23, 2016 has been issued by the Bank the NOL on March 8, 2016.
• Monitoring Report No.4 for compensation payments of 188 PAPs in Kab. Kaur submitted to WB
which was submitted on October 6, 2016 has been issued by the Bank the NOL on October 12, 2016.
• Monitoring Report of the payments progress for 333 PAPs has submitted to WB has been issued
by the Bank the NOL on November 18, 2016. •
Monitoring Report of the payments progress for 1.090 PAPs has submitted to WB has been issued by the Bank the NOL on March 20, 2017.
B. Pending Issues, Concern and Actions
Western I ndonesia National Roads I mprovement Project 4 - 24
a Compensation for the remaining 1,065 PAPs is under payment by Satker C. Update during this reporting month of March 2017
a Negotiations between the Affected Persons in Kecamatan Tanjung Kemuning and the Land Acquisition Committee still ongoing
b Total PAP = 3,198; Compensated = 2,133; Percent complete = 67.
14. Monitoring Report of the LARAP Package No. 14
: Painan - Kambang Province
: Sumatera Barat
A. Previous Status : •
World Bank issued on December 19, 2014 the No Objection Letter to the LARAP documents. •
LARAP s signed action plan was given No Objection Letter NOL by World Bank. •
Monitoring Report No.1 for compensation payments of 126 PAPs submitted to WB which was submitted on July 20, 2016 has been issued by the Bank the NOL on August 1, 2016.
• Monitoring Report of the payments progress for 62 PAPs has submitted to WB on Nov 11, 2016
B. Pending Issues, Concern and Actions a Pending of assessment process is a hindrance to complete compensation payment.
C. Update during this reporting month of March 2017 a Monitoring Report of the payments for 220 PAPs has been issued by the Bank the NOL on
March 20, 2017 b Assessment of the affected assets in Sub District of Lengayang will conducted by Appraisal
Consultants soon c Total PAP = 1,087; Compensated = 763; Percent complete = 70.2.
15. Monitoring Report of the LARAP Package No. 15
: Sibolga Bts. Tapsel
Province : Sumatera Utara
A. Previous Status : •
World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Right of Ways and removal of obstruction.
• Monitoring report No.1 for 40 of the remaining 1.554 PAPs was given No Objection Letter NOL
on November 16, 2015. •
Monitoring Report No.2 for payment of remaining 72 PAPs already submitted to World Bank. •
Monitoring Report-3 for the compensation payment for 237 from the remaining 1.439 PAPs already be submitted to WB on February 19, 2016 and Bank issued no objection letter NOL on
March 16, 2016.
• Monitoring Report No.4 for compensation payment of 55 PAPs submitted to WB on April 13,
2016 and Bank issued no objection letter NOL on May 19, 2016. •
Monitoring Report No.5 for compensation payment of 34 PAPs submitted to WB on August 8, 2016 and Bank issued no objection letter NOL on August 18, 2016.
• Monitoring Report No.6 for compensation payment of 127 PAPs is under submission to WB and
Bank issued no objection letter NOL on January 26, 2017. B. Pending Issues, Concern and Actions