Monitoring Report of the LARAP Package No. 9
14. Monitoring Report of the LARAP Package No. 14
: Painan - Kambang Province : Sumatera Barat A. Previous Status : • World Bank issued on December 19, 2014 the No Objection Letter to the LARAP documents. • LARAP s signed action plan was given No Objection Letter NOL by World Bank. • Monitoring Report No.1 for compensation payments of 126 PAPs submitted to WB which was submitted on July 20, 2016 has been issued by the Bank the NOL on August 1, 2016. • Monitoring Report of the payments progress for 62 PAPs has submitted to WB on Nov 11, 2016 B. Pending Issues, Concern and Actions a Pending of assessment process is a hindrance to complete compensation payment. C. Update during this reporting month of March 2017 a Monitoring Report of the payments for 220 PAPs has been issued by the Bank the NOL on March 20, 2017 b Assessment of the affected assets in Sub District of Lengayang will conducted by Appraisal Consultants soon c Total PAP = 1,087; Compensated = 763; Percent complete = 70.2.15. Monitoring Report of the LARAP Package No. 15
: Sibolga Bts. Tapsel Province : Sumatera Utara A. Previous Status : • World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Right of Ways and removal of obstruction. • Monitoring report No.1 for 40 of the remaining 1.554 PAPs was given No Objection Letter NOL on November 16, 2015. • Monitoring Report No.2 for payment of remaining 72 PAPs already submitted to World Bank. • Monitoring Report-3 for the compensation payment for 237 from the remaining 1.439 PAPs already be submitted to WB on February 19, 2016 and Bank issued no objection letter NOL on March 16, 2016. • Monitoring Report No.4 for compensation payment of 55 PAPs submitted to WB on April 13, 2016 and Bank issued no objection letter NOL on May 19, 2016. • Monitoring Report No.5 for compensation payment of 34 PAPs submitted to WB on August 8, 2016 and Bank issued no objection letter NOL on August 18, 2016. • Monitoring Report No.6 for compensation payment of 127 PAPs is under submission to WB and Bank issued no objection letter NOL on January 26, 2017. B. Pending Issues, Concern and ActionsParts
» WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Current Implementation Situation Civil Works
» Disbursement WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» World Bank Implementation Review Mission and Site Visit
» Procurement of Civil Works Contract Under Category 1 of the Loan Agreement
» Background WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Project Development WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Project Objective WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Scope of Services CTC Consultants
» CTC Contract CTC Consultants
» DSC Consultants WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Technical Assistance for Development of Slope Stabilization, Design and
» Detailed Design Preparation WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Procurements WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Civil Works Implementation WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Civil Works Progress WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 48.20 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» -7.63 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 158 CD WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 57.22 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 56.64 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 0.52 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 62CD WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» -34.62 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 281 CD WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» -28.01 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 107 CD WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 15.63 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» -34.08 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 0.07 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 492 CD WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 61.37 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 33.37 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» 21.25 WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Quality Assurance WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Review Design Integration, Road Safety Aspects and Monitoring of Environmental Studies
» The Contractor Action Plan on Environmental Management and Monitoring RKPPL
» Environmental Quarterly Report Environmental Issues
» Socialization of HIV-AIDs Campaign
» Quarries Management. Environmental Issues
» WB Mission 15 17 February 2017 on Packages No.7,12 14
» Monitoring Report of the LARAP Package No. 1
» Monitoring Report of the LARAP Package No. 2
» Monitoring Report of the LARAP Package No. 3
» Monitoring Report of the LARAP Package No. 4
» Monitoring Report of the LARAP Package No. 5
» Monitoring Report of the LARAP Package No. 6
» Monitoring Report of the LARAP Package No. 7
» Monitoring Report of the LARAP Package No. 8
» Monitoring Report of the LARAP Package No. 9
» Monitoring Report of the LARAP Package No. 10
» Monitoring Report of the LARAP Package No. 11
» Monitoring Report of the LARAP Package No. 12
» Monitoring Report of the LARAP Package No. 13
» Monitoring Report of the LARAP Package No. 14 Monitoring Report of the LARAP Package No. 15
» Monitoring Report of the LARAP Package No.16
» Monitoring Report of the LARAP Package No.17
» Monitoring Report of the LARAP Package No.18
» Monitoring Report of the LARAP Package No.19
» Monitoring Report of the LARAP Package No. 20
» Monitoring Report of the LARAP Package No. 21
» Anti Corruption Action Plan ACAP
» Community Representative Observers CRO
» Publication Disclosure Anti Corruption Issues
» Complaints Handling Mechanism CHS
» Road Safety Audit WINRIP DOC MPR CTC MPR No.51 2017 03 20170331 00480
» Database Establish the Document Management System DMS to provide:
» World Bank Missions Agreed Key Actions and Mission Plans during Recent World Bank Mission
» Performance Indicators World Bank and GOI Compliance
» Design and Supervision Consultant DSC
» Study on Development of Slope Stabilization Design and Management
» Complaint Handling System CHS
» DMS Statistic Management Information System
» Draw Downs and Future Costs Disbursement Quality Assurance
» Financial Risks Project Risks and Mitigation Measures
» Training to Support Project Implementation
Show more