Monitoring Report of the LARAP Package No. 9

Western I ndonesia National Roads I mprovement Project 4 - 24 a Compensation for the remaining 1,065 PAPs is under payment by Satker C. Update during this reporting month of March 2017 a Negotiations between the Affected Persons in Kecamatan Tanjung Kemuning and the Land Acquisition Committee still ongoing b Total PAP = 3,198; Compensated = 2,133; Percent complete = 67.

14. Monitoring Report of the LARAP Package No. 14

: Painan - Kambang Province : Sumatera Barat A. Previous Status : • World Bank issued on December 19, 2014 the No Objection Letter to the LARAP documents. • LARAP s signed action plan was given No Objection Letter NOL by World Bank. • Monitoring Report No.1 for compensation payments of 126 PAPs submitted to WB which was submitted on July 20, 2016 has been issued by the Bank the NOL on August 1, 2016. • Monitoring Report of the payments progress for 62 PAPs has submitted to WB on Nov 11, 2016 B. Pending Issues, Concern and Actions a Pending of assessment process is a hindrance to complete compensation payment. C. Update during this reporting month of March 2017 a Monitoring Report of the payments for 220 PAPs has been issued by the Bank the NOL on March 20, 2017 b Assessment of the affected assets in Sub District of Lengayang will conducted by Appraisal Consultants soon c Total PAP = 1,087; Compensated = 763; Percent complete = 70.2.

15. Monitoring Report of the LARAP Package No. 15

: Sibolga Bts. Tapsel Province : Sumatera Utara A. Previous Status : • World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Right of Ways and removal of obstruction. • Monitoring report No.1 for 40 of the remaining 1.554 PAPs was given No Objection Letter NOL on November 16, 2015. • Monitoring Report No.2 for payment of remaining 72 PAPs already submitted to World Bank. • Monitoring Report-3 for the compensation payment for 237 from the remaining 1.439 PAPs already be submitted to WB on February 19, 2016 and Bank issued no objection letter NOL on March 16, 2016. • Monitoring Report No.4 for compensation payment of 55 PAPs submitted to WB on April 13, 2016 and Bank issued no objection letter NOL on May 19, 2016. • Monitoring Report No.5 for compensation payment of 34 PAPs submitted to WB on August 8, 2016 and Bank issued no objection letter NOL on August 18, 2016. • Monitoring Report No.6 for compensation payment of 127 PAPs is under submission to WB and Bank issued no objection letter NOL on January 26, 2017. B. Pending Issues, Concern and Actions