Western I ndonesia National Roads I mprovement Project 4 - 24
a Compensation for the remaining 1,065 PAPs is under payment by Satker C. Update during this reporting month of March 2017
a Negotiations between the Affected Persons in Kecamatan Tanjung Kemuning and the Land Acquisition Committee still ongoing
b Total PAP = 3,198; Compensated = 2,133; Percent complete = 67.
14. Monitoring Report of the LARAP Package No. 14
: Painan - Kambang Province
: Sumatera Barat
A. Previous Status : •
World Bank issued on December 19, 2014 the No Objection Letter to the LARAP documents. •
LARAP s signed action plan was given No Objection Letter NOL by World Bank. •
Monitoring Report No.1 for compensation payments of 126 PAPs submitted to WB which was submitted on July 20, 2016 has been issued by the Bank the NOL on August 1, 2016.
• Monitoring Report of the payments progress for 62 PAPs has submitted to WB on Nov 11, 2016
B. Pending Issues, Concern and Actions a Pending of assessment process is a hindrance to complete compensation payment.
C. Update during this reporting month of March 2017 a Monitoring Report of the payments for 220 PAPs has been issued by the Bank the NOL on
March 20, 2017 b Assessment of the affected assets in Sub District of Lengayang will conducted by Appraisal
Consultants soon c Total PAP = 1,087; Compensated = 763; Percent complete = 70.2.
15. Monitoring Report of the LARAP Package No. 15
: Sibolga Bts. Tapsel
Province : Sumatera Utara
A. Previous Status : •
World Bank approved the LARAP documents on February 6, 2014 for implementation in acquiring Road Right of Ways and removal of obstruction.
• Monitoring report No.1 for 40 of the remaining 1.554 PAPs was given No Objection Letter NOL
on November 16, 2015. •
Monitoring Report No.2 for payment of remaining 72 PAPs already submitted to World Bank. •
Monitoring Report-3 for the compensation payment for 237 from the remaining 1.439 PAPs already be submitted to WB on February 19, 2016 and Bank issued no objection letter NOL on
March 16, 2016.
• Monitoring Report No.4 for compensation payment of 55 PAPs submitted to WB on April 13,
2016 and Bank issued no objection letter NOL on May 19, 2016. •
Monitoring Report No.5 for compensation payment of 34 PAPs submitted to WB on August 8, 2016 and Bank issued no objection letter NOL on August 18, 2016.
• Monitoring Report No.6 for compensation payment of 127 PAPs is under submission to WB and
Bank issued no objection letter NOL on January 26, 2017. B. Pending Issues, Concern and Actions
Western I ndonesia National Roads I mprovement Project 4 - 25
a Due limited to limited supply of map fields from BPN as one of the documents needed for find disbursement by Treasury Office affect the progress of payments release.
C. Update during this reporting month of March 2017 a PPK Satker PJN II Sumatera Utara has made an Action Plan to accelerate land acquisition,
and has coordinated with the BPN to add team of the measurements b Total PAP = 2,003; Compensated = 677; Percent complete = 33.8.
16. Monitoring Report of the LARAP Package No.16
: Seblat - Ipuh Province
: Bengkulu
A. Previous Status : •
World Bank issued on May 30, 2014 a No Objection Letter NOL on the revised LARAP documents for implementation.
• World Bank issued No Objection Letter NOL on Monitoring Report No.1 and 2 for LARAP
implementation. •
Monitoring report for 102 of the remaining 120 PAPs was given No Objection Letter NOL on November 26, 2015.
• Updated LARAP documents submitted on February 22, 2016 to World Bank with NOL issued by
Bank on March 8, 2016. •
Monitoring Report No.3 for compensation payment of 33 PAPs submitted to WB on October 24, 2016 and NOL issued by Bank on November 11, 2016
B. Pending Issues, Concern and Actions a No more issue
C. Update during this reporting month of March 2017 a Total PAP = 259; Compensated = 259; Percent complete = 100.00.
17. Monitoring Report of the LARAP Package No.17
: Sp. Gunung Kemala Pg. Tampak
Province : Lampung
A. Previous Status : •
World Bank approved the corrected LARAP documents on November 12, 2013 •
Monitoring Report for 154 of the total 2.014 PAPs was given No Objection Letter NOL on October 13, 2015.
• Monitoring Report for 735 of the remaining 1.860 PAPs was given No Objection Letter NOL on
November 26, 2015. •
A Monitoring Report for the compensation payments progress for 1,156 APs was given No Objection Letter NOL on November 18, 2016.
B. Pending Issues, Concern and Actions a Compensation payment for the remaining 113 PAPs is not yet paid by Satker PJN II
Lampung b Certification 290 plots not yet resolved
A. Update during this reporting month of March 2017 a Monitoring Report No.4 for compensation payment of 462 PAPs is under submission