Monitoring Report of the LARAP for Ipuh – Bantal

Western I ndonesia National Roads I mprovement Project 21

5. Monitoring Report of the LARAP for Sp. Gunung Kemala – Pugung Tampak

Larap report of the Package no.17 Sp. Gunung Kemala – Pugung Tampak in Lampung Province has been reviewed by the World Bank Ref.WINRIP133 dated 16 September 2013 with comments and issues to be addressed. The Comment and issues are as follows : a. The value of the appraisal for the affected lands for the Krui – Biha was already more than two years old. WB request the Larap should provide land appraisal value for the Sp Gunung Kemala – Pugung Tampak links. Likewise the established price standard for the building compensation should refer to the current data updated data. b. Action plan table should include a formation of the land appraising team, b relocation of 83 units of electricity utilities. c. Grievance redressed mechanism should refer to LAR Framework for WINRIP. d. Provide explanation on some data with no name in the nominative list. e. Action plan signed by the relevant local government as a commitment that the local government will provide proper budget for the action plan f. Implementation monitoring report by using the form provided in the LARAP. According to World Bank letter, PMU Ref. 1286Bp.11MD2013 dated 23 September 2013 has requested the Director of Implementation Affairs Region I via the SatkerPPK to prepare the above issues and concerns. Follow up the World Bank review and PMU letter, CTC revised the Larap report for Sp. Gunung Kemala – Pugung Tampak. A revision of the Larap report already submitted to the WB from PMU dated 6 November 2013, and response from the World Bank dated 12 November 2013 stated that the Larap document could been disclosed at PMU website. Referring to letter from the World Bank, Director of Planning submitted an official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding approval of the report from the World Bank to be informed to Balai III PalembangSatker in Lampung Province.Now, PMUCTC waiting a report of Larap implementation from Satker in Lampung Province.

6. Report of LARAP for Sp. Rampa - Poriaha

Larap report for Package no.5 Sp. Rampa – Poriaha in North Sumatera Province has reviewed by the World Bank Ref.WINRIP134 dated 16 September 2013 with comments and issues to be addressed. The comments and issues are as follows: a. Moving and providing compensation to one person kiosk owner affected by the road improvement shall be included in the action plan. b. Action plan shall be signed by the relevant local government as a commitment that the local government will provide proper budget for the action plan Western I ndonesia National Roads I mprovement Project 22 c. Implementation monitoring report by using the form provided in the LARAP. PMU has sent a letter Ref. 1286Bp.11MD2013 dated 23 September 2013 to Director of Implementation Affairs Region I requesting the SatkerPPK to take action. Follow up the World Bank review and PMU letter, CTC revised the Larap report for Sp. Rampa – Poriaha. A revision of the Larap report has submitted to the WB by PMU dated 6 November 2013, and response from the World Bank dated 12 November 2013 stated that the Larap document could be disclosed at PMU website. Referring to letter from the World Bank, Director of Planning has submited an official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding the approval of the report from the World Bank to be informed to Balai I North Sumatera. PMU and CTC are waiting a report of Larap implementation from Head of Satker North Sumatera Province.

7. Report of Five Larap in Bengkulu

CTC recieved Larap Reports for five 5 packages in Bengkulu Province from the BBPJN III Palembang dated 30 September 2013. The five Larap reports consist of Larap Package No. 13: Sp. Rukis – Tanjung Kemuning, Larap Package No. 6: Psr Pedati – Kerkap, Larap Package No. 11: Muko-muko – Bantal, Larap Package No. 16: Seblat – Ipuh, and Larap Package No. 16: Bintunan – Lais. CTC reviewed the five 5 Larap Reports, and have submitted to the World Wank by PMU dated 13 November 2013. All of the five Larap reports in Bengkulu Province has been reviewed by the World Bank Ref.WINRIP144 dated 20 November 2013 with comments and issues that need to be addressed and incorporated in the Report. The comments and issues are as follows: a. In the five Larap reports there are some assets land and building that will be totally affected. Budgets for these obstructions should be allocated. b. In the Larap report Package no.16 Ipuh – Seblat there are 126 land plots belong to governmentpublic that are affected. However the social economic survey and the inventory table don’t show the situation. PMU has sent a letter Ref. 1476Bp.11MD2013 dated 27 November 2013 to Director of Implementation Affairs Region I requested the SatkerPPK take action. A revision of five Larap reports had been submitted to the World Bank on 9 January 2014, and PMU had been received some comments from WB 16 January 2014. All of the Bank’s request will be provided by PMU on the Larap monitoring report. Final revision for five Larap reports including the signed action plan is under submission to the World Bank. PMU is waiting Larap implementation report from Head of Satker I and II Bengkulu Province.