Package No.17: SP. Gunung Kemala – Pg. Tampak Social Issues:
Western I ndonesia National Roads I mprovement Project 53
during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank by PMU dated 13 November 2103 and approval the
World Bank dated 20 November 2013 with some comments.
Follow up the World Bank review and PMU letter, now the Larap report is being revised by CTC. A revision of the Larap report has been submitted to the World Bank dated 9 January
2014 and approval from the WB dated 16 January 2014 with request to provide 1 the Laraps are signed by Local Government, 2 using the form provided in Laraps in the
monitoring report, and 3 land appraisal value used as reference for conducting negotiation. The final revision of Larap including signed action under submission process to the World
Bank from PMU.
Environmental Issues:-
The UKLUPL has been sent to the Bank on 30 September 2013