Package No.05: Sp. Rampa – Poriaha

Western I ndonesia National Roads I mprovement Project 49

6.6.7 Package No.07: Indrapura – Tapan

Social Issues: CTC received from Balai IIP2JN Padang Larap report of Package no.07 Indrapura – Tapanduring on January 2014. Larap report already reviewed by CTC, and Directorate Implementation Region I being send Memo to Balai II. Environmental Issues: Now CTC is waiting for and ensure the environmental safeguard for this package from Balai II PadangSubdit EA DTA.

6.6.8 Package No.08: Bts Kota Pariaman – Manggopoh

Social Issues: CTC received the LARAP report from Balai II PadangPMU dated 01 August 2013. Review and comment from CTC has been sent to PMU dated 9 September 2013, and PMU has forwarded to P2JNLocal Consultant and requested to revise the LARAP report based on CTC comment. Environmental Issues: Official Letter from Director of Implementation Affairs Region I has been issued to Kepala Balai Besar Pelaksanaan Jalan Nasional II dated 17 December 2013 regarding to the request of the AMDAL submission. Then on 27 December 2013 AMDAL document already sent to Director of Implementation Affairs Region I by Official Letter from Kepala Balai Besar Pelaksanaan Jalan Nasional II. The AMDAL document is under process to be submitted to the World Bank.

6.6.9 Package No.09: Rantau Tijang – Kota Agung

Social Issues: Balai III will provide a Larap Document for Rantau Tijang – Kota Agung. Environmental Issues: The environmental safeguard or UKL UPL has completed and will be sent to the WB after DGH send formal letter to the WB that no change link for this package.

6.6.10 Package No.10: Sp. Empat – Air Balam Social Issues:

CTC received the LARAP report from Balai II PadangPMU on 01 August 2013. Review and comment from CTC has been sent to PMU on 9 September 2013, and PMU forwarded to P2JNLocal Consultant and has requested to revise the LARAP report based on CTC comment. Environmental Issues: Official Letter from Director of Implementation Affairs Region I has been issued to Kepala Balai Besar Pelaksanaan Jalan Nasional II dated 17 December 2013 regarding to the request of the AMDAL submission. Then on 27 December 2013 AMDAL document already