Package No.13: Sp. Rukis – Tj. Kemuning Social Issues:

Western I ndonesia National Roads I mprovement Project 51 CTC. A revision of the Larap report has been submitted to the World Bank dated 9 January 2014 and approval from the WB dated 16 January 2014 with request to provide 1 the Laraps are signed by Local Government, 2 using the form provided in Laraps in the monitoring report, and 3 land appraisal value used as reference for conducting negotiation. The final revision of Larap including signed action under submission process to the World Bank from PMU. Environmental Issues: CTC is waiting for the UKLUPL document from Satker P2JN Bengkulu Province.

6.6.14 Package No.14: Painan – Kambang Social Issues:

CTC received from Balai IIP2JN Padang Larap report of Package no.14 Painan – Kambangduring on January 2014. Larap report already reviewed by CTC, and Directorate Implementation Region I is being send Memo to Balai II. Environmental Issues: Now CTC is waiting for and ensure the environmental safeguard for this package from Balai II PadangSubtit EA DTA.

6.6.15 Package No.15: Sibolga – Bts. Tapsel Social Issues:

CTC received Final LARAP report form BalaiPMU on 30 September 2013. The report already submitted to the Bank on 22 October 2013 and approved by the Bank on 28 October 2013 with some comments. Follow up the World Bank review and PMU letter, now the Larap report is being revised by CTC. A revision Larap reports has been submitted to the WB dated 30 January 2014 and approval from the WB dated 6 February 2014. Environmental Issues: The UKLUPL has been sent to the Bank on 30 September 2013

6.6.16 Package No.16: Sebelat – Ipuh Social Issues:

CTC received a Larap report of Package no.16 Sebelat - Ipuh from Balai III PalembangPMU dated 7 October 2013. CTC has reviewed to finalize the Larap report during November 2013, and submitted to PMU dated 29 October 2013. The Larap report already submitted to the World Bank by PMU dated 13 November 2103 and approval the World Bank dated 20 November 2013 with some comments. Follow up the World Bank review and PMU letter, now the Larap report is being revised by Western I ndonesia National Roads I mprovement Project 52 CTC. A revision of the Larap report has been submitted to the World Bank dated 9 Jan 2014 and approval from the WB dated 16 Jan 2014 with request to provide 1 the Laraps are signed by Local Government, 2 using the form provided in Laraps in the monitoring report, and 3 land appraisal value used as reference for conducting negotiation. The final revision of Larap including signed action under submission process to the World Bank from PMU. Environmental Issues: AMDAL document does not complete yet, and CTC is waiting for the report from P2JN Bengkulu.

6.6.17 Package No.17: SP. Gunung Kemala – Pg. Tampak Social Issues:

The Larap report has reviewed by CTC and submitted to PMU dated 30 August 2013. The report already submitted to the World Bank by PMU dated 10 September 2013 and approval the World Bank dated 16 September 2013 with some comment The revision of Larap Report submitted to PMU by CTC dated 29 October 2013. The report already submitted to the World Bank dated 06 November 2103 and responsed by the Bank on 12 November 2013 and that documents disclosed at PMU website. Referring to letter from the World Bank, Director of Planning submit a official letter to Director of Implementation Affairs Region I dated 18 November 2013 regarding approval of the report from the World Bank to be informed to Balai III PalembangSatker in Lampung Province. Now, PMUCTC is waiting a report of Larap implementation from Satker in Lampung Province. Environmental Issues: The AMDAL was sent to the Bank on 30 September 2013, and approved by the World Bank on 20 November 2013 and requested that documents to disclosed at PMU website.

6.6.18 Package No.18: Mukomuko – Bts. Sumbar Social Issues:

Balai III will provide Larap Document for this package. Environmental Issues: The environmental safeguard or UKL UPL has completed and will be sent to the WB after DGH sent formal letter to the WB that no change link for this package. This package will be replaced with other link by DGH, so the environmental safeguard requirement is not clear yet.

6.6.19 Package No.19: Lais - Bintunan Social Issues:

CTC received a Larap report of package no.19 Lais - Bintunan from Balai III PalembangPMU dated 7 October 2013. CTC has reviewed to finalize the Larap report