File names composition Upload documents and reports The data that included as a document or report are as follows below: Update photo galleries The data that included as media gallery is as follows below:

Western I ndonesia National Roads I mprovement Project 58 • Disclosure of information Screenshot – Article page.

b. Upload documents and reports The data that included as a document or report are as follows below:

i. Document • Project • Highway • Environment Social • Procurement • Community Development ii. Report • Project Progress • Financial • Audit Western I ndonesia National Roads I mprovement Project 59 • Annual iii. Procurement • Procurement Plan • Bidding Information • Contract Screenshot – Document and Report page.

c. Update photo galleries The data that included as media gallery is as follows below:

i. Photo ii. Video no data iii. Presentation no data Western I ndonesia National Roads I mprovement Project 60 Screeshot – Photo gallery page.

d. Upload files into The File Storage server

All documents that have been converted into a PDF file and ZIP file then it uploaded into the File Storage server. This document files will be as archived data. And it can only be accessed by internal users who are already have a username and password to login to the File Storage server. Western I ndonesia National Roads I mprovement Project 61 Screenshot – The File Storage.

6.8 Quality Assurance

The Quality Assurance Engineer has attended PCM of Package no.1, 2, 3, and 4. At the moment the Quality Assurance Engineer has explained the quality assurance aspect of administration and technical operating procedures. But the quality assurance activities for the project cannot be reported due to at the end of February 2014, there were no information quality assurance works from DSC. 6.9 Project Risks and Mitigation Measures 6.9.1 Risks Related to Delays Since the detailed engineering design DED is under responsibility of the Design and Supervision Consultant DSC, delay on DSC establishment affected to the procurement of AWP-2 and AWP-3 sub-projects. As above mentioned, the DED of several subprojects of WP-2 and WP-3 have prepared and completed by respective P2JN. The CTC has been instructed by DGH to review the DEDs of seven packages have been completed by the P2JNs Package no.5, 6, 11, 13, 15, 17, and 19.

6.9.2 Financial Risks

The following factors will be monitored during implementation of the loan project. • Loan Amount • Actual Tender Prices • Price Adjustment • Currency Fluctuation • Current Estimated Situation No risk has detected until preparation of this report since the main program of the loan civil works implementation has not been started yet.