Monitoring of Environmental Aspects During Construction

Western I ndonesia National Roads I mprovement Project 30 b Due to resistance to partially demolished and rebuild the mosque, a new action plan is proposed, where the road alignment centerline will be shifted to the other side. c Land acquisition is required on the other side of the road centerline alignment if the new action plan push through. C. Update during this reporting month of December 2014 a On-going construction b No Update this period

2. Monitoring Report of the LARAP Package No. 2

: Padang Sawah Sp. Empat Province : Sumatera Barat A. Previous Status : • LARAP documents approved by World Bank on January 13, 2013 • Monitoring Report approved by World Bank on July 19, 2013 • Additional LARAP documents approved by World Bank on July 21, 2014 B. Pending Issues, Concern and Actions a Remaining twenty one 21 affected persons and twenty four 24 new PAPare not yet compensated by the Local Government. Five 5 of the twenty one 21 affected persons are residing along the proposed bridge site of Air Gadang Bridge. b Documents for compensation payments are being processed by the Local Government. c Monitoring Report concerning the payments to the remaining affected persons still to be prepared for submission to World Bank. C. Update during this reporting month of December 2014 a On-going construction b Compensation payments for fourty five 45 PAP are still being resolved and under preparation by the local government.

3. Monitoring Report of the LARAP Package No. 3

: Manggopoh Padang Sawah Province : Sumatera Barat A. Previous Status : • LARAP documents approved by World Bank on January 4, 2013 • Monitoring Report approved by World Bank on April 18, 2013 • CTC received proof of compensation payments for five 5 of the affected persons out of the remaining fifteen 15 persons and Monitoring Report was submitted to World Bank on February 28, 2014. • CTC received proof of compensation payment for 8 of the affected persons out of the 10 remaining persons and 67 from 68 new PAP and Monitoring Report submitted to World Bank on June 19, 2014. B. Pending Issues, Concerns and Actions a Documents for compensation payments for one 1 remaining identified PAP was Western I ndonesia National Roads I mprovement Project 31 witheld by the Local Government. b Monitoring Report concerning compensation payments to the one 1 identified PAP still to be prepared for submission to World Bank. C. Update during this reporting month of December 2014 a On-going construction b No update this month.

4. Monitoring Report of the LARAP Package No. 4

: Ipuh Bantal Province : Bengkulu A. Previous Status : • LARAP documents approved by World Bank on December 10, 2012 • CTC received proof of payments for 157 affected persons out of the 227 Project Affected Persons. • Monitoring Report was submitted by PMU to World Bank on December 24, 2013 • World Bank transmitted their comments on the Monitoring Report to PMU on January 6, 2014. • For the remaining 70 affected persons, Local Government settled their compensation payments in January 2014 and February 2014. • Monitoring Report for the compensation of the remaining 70 affected persons was submitted by PMU to the World Bank on February 28, 2014. • World Bank sent letter to PMU on March 5, 2014 informing that the Bank have no further comment on the Monitoring Report. B. Pending Issues, Concern and Actions a Monitoring Report for the compensation payments of additional 30 PAP still to be submitted to World Bank. C. Update during this reporting month of December 2014 a On-going construction. b Monitoring Report for the compensation payments of additional 30 PAP is under review and finalization by CTC.

5. Monitoring Report of the LARAP Package No. 5

: Sp. Rampa Poriaha Province : Sumatera Utara A. Previous Status : • Comments on LARAP documents by World Bank were transmitted to PMU on September 16, 2013 • On September 23, 2013 World Bank wrote letter to Director of Implementation Affairs thru SatkerPPK to revise the LARAP documents in line with their comments. • CTC in consultation with PMU prepared the revised LARAP documents and resubmitted it on November 6, 2013. • World Bank accepted the revised LARAP documents on November 12, 2013.